{"schema_version":"1.0","country":"au","country_name":"Australia","topic":"battery-storage","question":"Where can I get a list of battery storage (BESS) installations in operation in Australia, with location, power (MW), energy (MWh), operator and commissioning date?","territory":"au","territory_level":"country","parent_url":null,"published_on":"2026-11-27","research_reviewed_on":"2026-11-26","access_checked_on":"2026-11-26","answer":{"official_data":"partial","non_official_data":"usable","summary":"No single official national list exists. For the NEM (QLD, NSW/ACT, VIC, SA, TAS) AEMO's quarterly NEM Generation Information xlsx lists each battery unit with status, MW AC, MWh and owner (58 units across 'In Service' and 'In Commissioning', Oct 2026); NEMWEB MMS tables add registered participant, station address and registration dates. Neither gives coordinates and commissioning dates are mostly blank. For WA's WEM, AEMO's daily facilities CSV gives only code, participant and System Size (combined import and export rating). Open Electricity (non-official, CC BY-NC) covers NEM+WEM with coordinates, MW, MWh, owner and start date. NT/off-grid not verified.","main_caveats":["Registration is not operation: MMS START_DATE and 'COMMISSIONED' mark registration (often the 2024 IESS re-registration); GI 'In Service' needs AEMO sign-off after commissioning tests.","GI status can lag: Waratah Super Battery (WTAHB1) is 'Committed' in the Oct 2026 release while MMS SCADA shows it discharging up to 556.8 MW in Oct 2026.","WEM 'System Size' adds withdrawal to export capacity: KWINANA_ESR1 System Size 200 vs ~100 MW peak in Oct 2026 SCADA; use a documented export rating. SCADA shows observed output only.","GI and MMS give MW and MWh per generating unit (DUID row); a site or hybrid spans several rows and 'Max Site Capacity (AC)' caps the site.","Official files name owner, MSATS custodian or registered participant, not an operator; they can differ (MREHA3: owner Equis SPV, participant SEC Energy).","Open Electricity is non-official, CC BY-NC 4.0 and excludes AI training/grounding from its standard licence; its MW, MWh and dates can differ from AEMO."],"confidence":"medium","confidence_reason":"NEM and WEM official files were downloaded and cross-checked; NT/off-grid, AER and DCCEEW pages could not be opened (403/timeouts) and Overpass was unavailable.","attributes":[{"attribute":"location","covered":"partial","source_ids":["openelectricity_facilities","nemweb_mms_registration","ga_battery_storage_facilities","aemo_nem_geninfo","osm_battery_plants"],"note":"NEM official: MMS station address/locality; GA points (July 2024 fleet); GI only region. WEM: none official. Coordinates NEM+WEM: Open Electricity (non-official).","gap":"not_checked","gap_note":"Official coordinates not published for the current NEM or WEM fleet (GI, MMS, WEM CSV checked); NT/off-grid documents returned HTTP 403 and remain unchecked."},{"attribute":"power_mw","covered":"partial","source_ids":["aemo_nem_geninfo","nemweb_mms_registration","wem_facilities","openelectricity_facilities"],"note":"NEM: MW AC per unit (GI) and registered/max MW (MMS). WEM: System Size counts export plus withdrawal; SCADA gives actual MW.","gap":"not_checked","gap_note":"WEM discharge MW not published as such (System Size only); off-grid systems (NT, Horizon Power, NWIS) not verified (HTTP 403 / no list)."},{"attribute":"energy_mwh","covered":"partial","source_ids":["aemo_nem_geninfo","nemweb_mms_registration","openelectricity_facilities","osm_battery_plants"],"note":"NEM: nameplate MWh per unit (GI) and MAXSTORAGECAPACITY (MMS), disagreeing for 10 units. WEM: only non-official per unit; WATC gives an aggregate.","gap":"not_checked","gap_note":"Official per-installation MWh not published for the WEM (facilities CSV, CRC files, ESM Rules checked; WEM ESOO 403); off-grid not verified."},{"attribute":"operator","covered":"partial","source_ids":["aemo_nem_geninfo","nemweb_mms_registration","wem_facilities","openelectricity_facilities","osm_battery_plants"],"note":"Official: GI Site Owner and MSATS Custodian, MMS registered participant name, WEM Market Participant. No field labelled operator.","gap":"not_checked","gap_note":"Operator as such not published by AEMO (GI definitions, MMS, WEM CSV checked); OSM 'operator' tag only per mapped element; off-grid not verified."},{"attribute":"commissioning_date","covered":"partial","source_ids":["aemo_nem_geninfo","nemweb_mms_registration","openelectricity_facilities"],"note":"GI FCUD in 14/58 rows (19/24 in Jul 2024 release) and Change Log status dates; MMS dates are registration. Open Electricity commencement_date for all.","gap":"not_checked","gap_note":"No official in-service date field for the WEM (facilities CSV) or for most NEM units; WA pages give text dates; off-grid not verified."}]},"sources":[{"source_id":"aemo_nem_geninfo","name":"NEM Generation Information (October 2026 release) with KCI datafile","publisher":"Australian Energy Market Operator (AEMO)","official":true,"landing_url":"https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-planning-data/generation-information","data_url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","access":"direct_download","format":"XLSX","license":"AEMO copyright; use per AEMO website copyright permissions","language":"en","has_coordinates":false,"location_precision":"none","publisher_type":"operator","adds":"Official unit-level NEM list with status (In Service / In Commissioning), MW AC, nameplate MWh, site owner, MSATS custodian, DUID and status-change log.","first_seen_pass":1,"rank":1,"summary":"Official quarterly xlsx of every NEM unit with status, MW AC, MWh, owner and DUID; 58 battery rows In Service/In Commissioning (54 sites) in the Oct 2026 release.","coverage_note":"NEM only; location only as NEM region; commissioning date mostly blank (Change Log gives status-change release dates).","data_date":"2026-10-30","caveats":["Status can lag actual operation (Waratah 'Committed' while dispatching).","Site Owner/Custodian are not an explicit operator field."],"coverage":{"geographic":"National Electricity Market regions only (QLD1, NSW1 incl. ACT, VIC1, SA1, TAS1); not WA, NT or off-grid systems."},"fine_print":{"unit":{"value":"MW AC (and MW DC) nameplate per generating unit; MWh nameplate per generating unit; 'Max Site Capacity (AC)' is site-level.","quote":"Agg Nameplate Storage Capacity (MWh) | This is the total nameplate storage capacity of the generating unit.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","attempts":[]},"inclusion_rule":{"value":"Projects registered or intending to register in the NEM, as submitted by owners/operators/developers.","quote":"report information on technical and operational parameters as submitted to AEMO by the owners, operators or developers of existing, committed, and proposed  generation or storage projects that are registered, or intend to seek registration in the National Electricity Market (NEM).","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","attempts":[]},"reference_date":{"value":"Release dated 2026-10-30; each row also carries 'Survey Latest Update Date'.","quote":"30/10/2026 NEM October 2026 Generation Information 928.46 KB","url":"http://web.archive.org/web/20261114233107/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-planning-data/generation-information","attempts":[]},"update_frequency":{"value":"Quarterly, or as required.","quote":"AEMO collects generation information reported here from generation industry participants, via a web-based online system, and is committed to publishing updates of information collected every three months, or as required.","url":"http://web.archive.org/web/20261114233107/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-planning-data/generation-information","attempts":[]},"exclusions":{"value":"Units neither registered nor seeking registration are out of scope; discontinued and long-unresponsive projects are removed.","quote":"Projects are removed from the Generation Information publication if they fulfil any of the below criteria: Marked as discontinued by the project proponent","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","attempts":[{"url":"https://wa.aemo.com.au/-/media/files/electricity/nem/participant_information/registration/2024/registration-fact-sheet-nem-battery-systems.pdf?la=en","note":"AEMO battery registration fact sheet (NEM exemption threshold) returned 403."},{"url":"https://www.aemc.gov.au/","note":"AEMC (rules) site returned 403; NEM size threshold for exempt batteries not confirmed from an opened page."}]}},"key_fields":[{"field":"Technology Type","meaning":"'Battery Storage' selects batteries (655 rows, all statuses, Oct 2026)."},{"field":"Commitment Status","meaning":"'In Service' = commissioning signed off by AEMO; 'In Commissioning' = passed a hold point >=30% capacity."},{"field":"Agg Nameplate Capacity (MW AC)","meaning":"AC nameplate power of the generating unit (not the site)."},{"field":"Agg Nameplate Storage Capacity (MWh)","meaning":"Nameplate energy of the generating unit."},{"field":"Max Site Capacity (AC)","meaning":"Site registered maximum (GPS), across all technologies of a hybrid site."},{"field":"Site Owner / Custodian","meaning":"Financial owner name / MSATS participant ID delegated custody of the survey; no 'operator' field."},{"field":"Full Commercial Use Date","meaning":"Indicative date units become operationally available; filled for 14 of 58 operating battery rows."},{"field":"Region / DUID / AEMO KCI ID","meaning":"NEM region (only location field); dispatch unit ID to join MMS; ID to join the KCI datafile."},{"field":"Change Log sheet","meaning":"Publication Date, Type of Change, Note (e.g. 'Unit Status Updated From In Commissioning To In Service')."}],"how_to_use":{"example_request":"curl -sL -o gi.xlsx 'https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en'  # sheet 'Generator Information', header row 4; Technology Type='Battery Storage'; Commitment Status in ('In Service','In Commissioning')","example_result":"Hornsdale Power Reserve Unit 1 | HPRG1 | DUID HPR1 | SA1 | In Service | 100 MW AC | 117 MWh | Site Owner Hornsdale Power Reserve Pty Ltd | Custodian HORNSPR (2nd row HPRG EXP: 50 MW, 61.3 MWh)","steps":["Download the latest 'NEM <Month> <Year> Generation Information' xlsx: the file URL with its ?rev= query answered 200 to curl; the landing page and the URL without ?rev= answered 403.","Sheet 'Generator Information': rows 1-3 are notes, row 4 is the header (76 columns).","Filter Technology Type == 'Battery Storage'; keep Commitment Status 'In Service' (55 rows) and optionally 'In Commissioning' (3 rows): 58 rows on 54 sites in Oct 2026.","Group by AEMO Survey ID (site); use Max Site Capacity (AC) as the site cap of hybrids.","Join DUID to NEMWEB MMS tables for locality and registered participant; join AEMO KCI ID to the KCI datafile ('Site Location Description', free text; 29 of 58 rows have a KCI ID).","For an in-service date use the 'Change Log' sheet (status change rows with Publication Date) or the FCUD of older releases (July 2024: FCUD filled for 19 of 24 in-service battery rows)."],"reading_traps":["No coordinates or address: the only location field is the NEM region; NSW1 includes ACT sites (e.g. Capital Battery).","Status lags reality: Waratah Super Battery (WTAHB1) is 'Committed' in Oct 2026 while MMS SCADA shows it dispatching up to 556.8 MW in Oct 2026.","Full Commercial Use Date is empty for 44 of 58 operating battery rows and is indicative (NESBESS1 2026-07-31 while still 'In Commissioning').","Eraring ERB01 has a 460 MW/1073 MWh row and a 0 MW/700 MWh row (energy-only augmentation) under one DUID.","Hybrid sites list each technology as a separate unit sharing Max Site Capacity (e.g. Adelaide Desalination Plant battery 6.3 MW on a 26 MW site).","Change Log can repeat a transition (ORABESS1 'In Commissioning To In Service' on 2026-07-24 and again 2026-10-30)."]},"test":{"tested_on":"2026-11-26","method":"download","http_status":200,"content_type":"application/vnd.openxmlformats-officedocument.spreadsheetml.sheet","size_bytes":950741,"records_total":1793,"records_for_country":58,"problems":["Landing page and file URL without ?rev= return HTTP 403 (Cloudflare challenge) to automated clients."]},"evidence":[{"claim":"MWh per generating unit.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"Agg Nameplate Storage Capacity (MWh) | This is the total nameplate storage capacity of the generating unit."},{"claim":"Definition of In Service.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"In Service | Production units that have fully completed commissioning as signed-off by AEMO Onboarding & Connections."},{"claim":"Definition of In Commissioning.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"In Commissioning | Projects that have successfully completed a commissioning hold point test that is ≥ 30% capacity. Note: This will be confirmed by AEMO Onboarding & Connections."},{"claim":"Owner field.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"Site Owner | Name / Trading name of the organisation that financially owns the Generation Project / Generating System at the site."},{"claim":"Custodian field.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"Custodian | MSATS Participant ID of the organisation that has been delegated custody of this Survey."},{"claim":"FCUD meaning.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"\"Full Commercial Use\" requires the successful completion of all NER 5.7.3 commissioning tests, including sign-off by AEMO and the Network Service Provider."},{"claim":"Oct 2026 battery totals (Summary sheet).","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"Commitment Status | ... | Battery Storage ... In Service | ... | 7828.619999999999 ... In Commissioning | ... | 187.6"},{"claim":"Hybrids split by technology.","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","quote":"Hybrid projects are comprised of separate generating units of which each is represented under its technology, subject to a site maximum capacity."}],"members":[],"members_summary":null},{"source_id":"nemweb_mms_registration","name":"NEMWEB MMS Data Model monthly archive: DUDETAIL, DUDETAILSUMMARY, STATION, STATIONOPERATINGSTATUS and DISPATCH_UNIT_SCADA","publisher":"Australian Energy Market Operator (AEMO)","official":true,"landing_url":"https://nemweb.com.au/Reports/Current/","data_url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip","access":"direct_download","format":"ZIP of CSV (AEMO MMS I/D/C row format)","license":"unknown","language":"en","has_coordinates":false,"location_precision":"address","publisher_type":"operator","adds":"Registered bidirectional units with registered/max MW and MAXSTORAGECAPACITY, registered participant ID, station address/locality, registration dates and 5-minute SCADA (first output).","first_seen_pass":1,"rank":2,"summary":"AEMO MMS monthly CSVs: every registered NEM battery (BIDIRECTIONAL DUID) with registered and max MW, MAXSTORAGECAPACITY, participant, station address/locality and registration dates; SCADA shows first output.","coverage_note":"NEM registered units only (70 bidirectional DUIDs, Oct 2026); no in-service flag.","data_date":"2026-11-09","caveats":["Registration dates are not commissioning dates (IESS re-registration in 2024).","MAXSTORAGECAPACITY and GI MWh disagree for 10 units."],"coverage":{"geographic":"NEM registered units only (QLD, NSW, ACT, VIC, SA, TAS)."},"fine_print":{"unit":{"value":"REGISTEREDCAPACITY and MAXCAPACITY in MW; MAXSTORAGECAPACITY in MWh per DUID.","quote":null,"url":null,"attempts":[{"url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip","note":"CSV header has MAXSTORAGECAPACITY but no unit text; values within 10% of GI MWh for 54 of the 64 DUIDs in both files."},{"url":"https://nemweb.com.au/Reports/Current/","note":"Report index has no data dictionary; the MMS Data Model report folder was not opened."}]},"inclusion_rule":{"value":"DUIDs registered in the NEM; batteries are DISPATCHTYPE 'BIDIRECTIONAL' (70 DUIDs in the Oct 2026 archive).","quote":null,"url":null,"attempts":[{"url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip","note":"Counted from the file; no inclusion text in the file."},{"url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","note":"Registration page describes the human-readable list, not MMS tables."}]},"reference_date":{"value":"Monthly archive MMSDM_2026_10 extracted 2026/11/09.","quote":"C,SETP.WORLD,DVD_DUDETAIL,AEMO,PUBLIC,2026/11/09,14:43:32","url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip","attempts":[]},"update_frequency":{"value":"Monthly archive folders (MMSDM_YYYY_MM).","quote":null,"url":null,"attempts":[{"url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/","note":"Folder lists MMSDM_2026_06 ... MMSDM_2026_10 zips; no stated schedule."},{"url":"https://nemweb.com.au/Reports/Current/","note":"No schedule text."}]},"exclusions":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip","note":"Exempt (unregistered) units are absent by construction; no exclusion text."},{"url":"https://www.aemo.com.au/-/media/files/electricity/nem/participant_information/nem-registration-and-exemption-list.xlsx?rev=2a09052d2f1d448fb33582038a290bd6&sc_lang=en","note":"Exemption list that would show exempt units is blocked (403)."}]}},"key_fields":[{"field":"DUDETAIL.DISPATCHTYPE","meaning":"'BIDIRECTIONAL' = battery unit registered under IESS rules (from mid-2024)."},{"field":"DUDETAIL.MAXSTORAGECAPACITY","meaning":"Registered storage capacity (MWh) per DUID; use the latest EFFECTIVEDATE/VERSIONNO."},{"field":"DUDETAIL.REGISTEREDCAPACITY / MAXCAPACITY","meaning":"Registered MW vs maximum MW (e.g. Blyth 281 vs 200)."},{"field":"DUDETAILSUMMARY.START_DATE / PARTICIPANTID / STATIONID","meaning":"Validity window of a registration row; registered participant; station."},{"field":"STATION.ADDRESS1 / CITY / STATE / POSTCODE","meaning":"Station address or locality (sometimes a PO box)."},{"field":"STATIONOPERATINGSTATUS.STATUS","meaning":"'COMMISSIONED' with EFFECTIVEDATE at registration, not commercial operation."},{"field":"DISPATCH_UNIT_SCADA.SCADAVALUE","meaning":"5-minute MW per DUID (negative = charging)."},{"field":"PARTICIPANT.NAME","meaning":"Legal name of the registered participant ID (all 70 battery DUIDs resolve)."}],"how_to_use":{"example_request":"curl -sL -o dudetail.zip 'https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip'  # unzip; rows 'D'; DISPATCHTYPE=='BIDIRECTIONAL'; latest EFFECTIVEDATE/VERSIONNO per DUID","example_result":"DUID BLYTHB1, EFFECTIVEDATE 2024/08/20, REGISTEREDCAPACITY 281, MAXCAPACITY 200, MAXSTORAGECAPACITY 400; STATION BLYTHB CITY Blyth STATE SA; DUDETAILSUMMARY PARTICIPANTID BLYTHBAT","steps":["In MMSDM_YYYY_MM/MMSDM_Historical_Data_SQLLoader/DATA/ download PUBLIC_ARCHIVE#DUDETAIL, #DUDETAILSUMMARY, #STATION, #STATIONOPERATINGSTATUS zips ('#' encoded as %23).","Each CSV has 'C' (comment), 'I' (header) and 'D' (data) rows; use the 'I' row as header.","DUDETAIL is versioned: keep max (EFFECTIVEDATE, VERSIONNO) per DUID; filter DISPATCHTYPE == 'BIDIRECTIONAL' (70 DUIDs).","DUDETAILSUMMARY rows with END_DATE in the future give current PARTICIPANTID/STATIONID/REGIONID; earliest START_DATE per DUID is the BDU registration.","Join STATIONID to STATION for address/locality/postcode and DUID to GI for status and owner.","For pre-2024 batteries look for GENERATOR/LOAD DUIDs on the same STATIONID (e.g. HPRG1/HPRL1 from 2017/11/14 at HORNSDPR).","For first output, scan PUBLIC_ARCHIVE#DISPATCH_UNIT_SCADA (~30-34 MB per month) for the first |SCADAVALUE| > 0 of the DUID.","Join PARTICIPANTID to PUBLIC_ARCHIVE#PARTICIPANT for the participant's legal name (e.g. KESSB1 -> Shell Energy Retail Pty Ltd)."],"reading_traps":["BDU START_DATE is mostly the mid-2024 IESS re-registration: Hornsdale HPR1 starts 2024/09/12, HPRG1 2017/11/14.","STATIONOPERATINGSTATUS 'COMMISSIONED' is set at registration: WTAHBESS 'COMMISSIONED' since 2024/09/03 while GI Oct 2026 says 'Committed'.","MAXSTORAGECAPACITY differs from GI MWh by >10% for 10 of 64 matched DUIDs (e.g. ADPBA1 6 vs 12.6; LIMBESS1 536 vs 400).","70 BIDIRECTIONAL DUIDs vs 58 operating GI rows: 6 DUIDs (BLUEGB1, MOORABS1, PLBESS1, STABESS1, TRGBESS1, WOORB1) are not in the Oct 2026 GI.","STATION address can be postal (e.g. Callide 'PO BOX 392'); treat as locality unless it names a road or lot.","SCADA right after registration can exceed nameplate: NESBESS1 reached 191.7 MW on 2026-02-18 for a 100 MW unit."]},"test":{"tested_on":"2026-11-26","method":"download","http_status":200,"content_type":"application/x-zip-compressed","size_bytes":80645,"records_total":4488,"records_for_country":70,"problems":[]},"evidence":[{"claim":"DUDETAIL has a storage capacity column.","url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip","quote":"I,PARTICIPANT_REGISTRATION,DUDETAIL,7,EFFECTIVEDATE,DUID,VERSIONNO,CONNECTIONPOINTID,VOLTLEVEL,REGISTEREDCAPACITY,...,MAXSTORAGECAPACITY,STORAGEIMPORTEFFICIENCYFACTOR,STORAGEEXPORTEFFICIENCYFACTOR"},{"claim":"Station address and locality.","url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23STATION%23FILE01%23202610010000.zip","quote":"D,PARTICIPANT_REGISTRATION,STATION,1,HORNSDPR,\"Hornsdale Power Reserve\",\"Sec 188 Tarcowie Caltowie Road\",,,,Caltowie,SA,5490,\"2017/11/13 11:40:52\","},{"claim":"'COMMISSIONED' is set at registration (Waratah, still 'Committed' in GI Oct 2026).","url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23STATIONOPERATINGSTATUS%23FILE01%23202610010000.zip","quote":"D,PARTICIPANT_REGISTRATION,STATIONOPERATINGSTATUS,1,\"2024/09/03 00:00:00\",WTAHBESS,1,COMMISSIONED,..."},{"claim":"Waratah dispatching 556.8 MW in Oct 2026.","url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DISPATCH_UNIT_SCADA%23FILE01%23202610010000.zip","quote":"D,DISPATCH,UNIT_SCADA,1,\"2026/10/17 05:55:00\",WTAHB1,556.82233,\"2026/10/17 05:50:05\""},{"claim":"Registered participant of MREHA3 (GI Site Owner is an Equis SPV).","url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23PARTICIPANT%23FILE01%23202610010000.zip","quote":"D,PARTICIPANT_REGISTRATION,PARTICIPANT,1,SECGEN,\"MARKET PARTICIPANT\",\"SEC Energy Pty Ltd\",,,,\"2025/11/21 14:08:04\""}],"members":[],"members_summary":null},{"source_id":"wem_facilities","name":"WEM Market Data: Facilities (post-reform) and Facility SCADA","publisher":"Australian Energy Market Operator (AEMO), Western Australia","official":true,"landing_url":"https://data.wa.aemo.com.au/","data_url":"https://data.wa.aemo.com.au/datafiles/post-facilities/facilities.csv","access":"direct_download","format":"CSV","license":"unknown","language":"en","has_coordinates":false,"location_precision":"none","publisher_type":"operator","adds":"Only official public list for Western Australia's SWIS: registered facility codes incl. ESR facilities, Market Participant and System Size (MW), updated daily; SCADA gives actual MW.","first_seen_pass":1,"rank":3,"summary":"Daily CSV of all WEM registered facilities with participant and System Size (MW); 8 storage facilities identifiable by ESR/BESS codes on 2026-11-26.","coverage_note":"Western Australia SWIS only; no MWh, location or dates.","data_date":"2026-11-26","caveats":["System Size for storage counts export plus withdrawal (about 2x discharge MW).","Storage identified only by facility code."],"coverage":{"geographic":"Western Australia, South West Interconnected System (WEM) only."},"fine_print":{"unit":{"value":"System Size in MW; for a facility with storage it adds the maximum withdrawal capacity to the sent-out capacity, so it is about twice the discharge MW of a stand-alone battery.","quote":"System Size: In respect of a Facility, a quantity equalling the sum of: (a) the minimum of: i. the Declared Sent Out Capacity at the Connection Point for the Facility; ... (b) if the Facility contains no Electric Storage Resource, then zero, otherwise the minimum of: i. the absolute value of the maximum Withdrawal capacity for all Electric Storage Resource units, expressed in MW","url":"https://www.wa.gov.au/system/files/2026-09/electricity_system_and_market_rules_-_1_october_2026.pdf","attempts":[]},"inclusion_rule":{"value":"All Registered Facilities in the WEM.","quote":"The Facility name and System Size, in MW, of all Registered Facilities in the WEM.","url":"https://data.wa.aemo.com.au/datasets/definitions/facilities-definition.yaml","attempts":[]},"reference_date":{"value":"Extracted At 2026-11-26 06:30:16 (WST).","quote":"Extracted At ... 2026-11-26 06:30:16","url":"https://data.wa.aemo.com.au/datafiles/post-facilities/facilities.csv","attempts":[]},"update_frequency":{"value":"Daily.","quote":"Daily; updated at 06:30 AWST.","url":"https://data.wa.aemo.com.au/datasets/definitions/facilities-definition.yaml","attempts":[]},"exclusions":{"value":"Facilities below 10 MW System Size may be exempt from registration (5-10 MW apply for registration or exemption).","quote":"A person that owns, controls or operates a Facility containing an Energy Producing System with a System Size of less than 10 MW, but which equals or exceeds 5 MW, ... must apply to AEMO: (a) for registration ... or (b) for an exemption","url":"https://www.wa.gov.au/system/files/2026-09/electricity_system_and_market_rules_-_1_october_2026.pdf","attempts":[]}},"key_fields":[{"field":"Facility Code","meaning":"Batteries recognisable only by '_ESR' or '_BESS' in the code (8 on 2026-11-26)."},{"field":"Participant Name","meaning":"Registered Market Participant (e.g. Synergy); no operator field."},{"field":"System Size (MW)","meaning":"ESM Rules 'System Size' (export + withdrawal for storage); no MWh."},{"field":"Facility SCADA 'Average MWh'","meaning":"Energy per 5-minute dispatch interval; x12 gives MW."}],"how_to_use":{"example_request":"curl -sL -o facilities.csv 'https://data.wa.aemo.com.au/datafiles/post-facilities/facilities.csv'  # keep Facility Code containing '_ESR' or '_BESS'","example_result":"WPGENER,Synergy,KWINANA_ESR2,Scheduled Facility,450,,2026-11-26 06:30:16 | COL_BESS,Collie Battery Pty Ltd ATF Collie Battery Trust,COLLIE_BESS2,Scheduled Facility,600,,2026-11-26 06:30:16","steps":["Read https://data.wa.aemo.com.au/manifests/post-facilities.yaml for the current file URL; download facilities.csv (UTF-8 with BOM).","Select Facility Code containing '_ESR' or '_BESS': ALINTA_WGP_ESR1 200, COLLIE_BESS2 600, COLLIE_ESR1 400, COLLIE_ESR4 500, COLLIE_ESR5 500, KWINANA_ESR1 200, KWINANA_ESR2 450, MERREDIN_ESR1 200.","Divide System Size by 2 for an approximate discharge MW, or take max(Average MWh) x 12 from the monthly FacilityScada-YYYY-MM.csv."],"reading_traps":["System Size is not discharge MW: KWINANA_ESR1 System Size 200 vs max 8.329 MWh per 5 min (~100 MW) in Oct 2026 SCADA; COLLIE_ESR4 500 vs ~250 MW.","No technology column: four 'TESLA_*_G1' 9.999 MW Scheduled Facilities have no stated technology.","No MWh, location or dates in the file.","Registration threshold: facilities with System Size >= 10 MW must register; 5-10 MW may be exempt, so small batteries can be missing."]},"test":{"tested_on":"2026-11-26","method":"download","http_status":200,"content_type":"application/octet-stream","size_bytes":14403,"records_total":178,"records_for_country":8,"problems":["AEMO's WEM registered facilities web page returns HTTP 403 to automated clients; the data portal file is served."]},"evidence":[{"claim":"Dataset content.","url":"https://data.wa.aemo.com.au/datasets/definitions/facilities-definition.yaml","quote":"The Facility name and System Size, in MW, of all Registered Facilities in the WEM."},{"claim":"Legal basis.","url":"https://www.wa.gov.au/system/files/2026-09/electricity_system_and_market_rules_-_1_october_2026.pdf","quote":"2.34B.1. AEMO must publish details of all Rule Participants, including: ... (e) names and System Sizes of Registered Facilities"},{"claim":"Government paper halves System Size for storage.","url":"https://www.wa.gov.au/system/files/2025-11/cc2t_review_working_group_2025_12_04_papers.pdf","quote":"2. Converted from System Size by dividing by 2."},{"claim":"SCADA unit.","url":"https://data.wa.aemo.com.au/datasets/definitions/facility-scada-csv-definition.yaml","quote":"The average injection / withdrawal quantity for the Facility in MWh measured by SCADA during the Dispatch Interval."},{"claim":"Registration threshold.","url":"https://www.wa.gov.au/system/files/2026-09/electricity_system_and_market_rules_-_1_october_2026.pdf","quote":"a person who owns, controls or operates a Facility containing an Energy Producing System with a System Size that equals or exceeds 10 MW ... must register as a Rule Participant in the Market Participant class."}],"members":[],"members_summary":null},{"source_id":"ga_battery_storage_facilities","name":"Battery Storage Facilities (MapServer layer)","publisher":"Geoscience Australia","official":true,"landing_url":"https://ecat.ga.gov.au/geonetwork/srv/api/records/747fc5c7-efcc-4df4-99d2-7d314d29ce57","data_url":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer/0/query?where=1%3D1&outFields=*&returnGeometry=true&outSR=4326&f=json","access":"api","format":"ArcGIS REST MapServer (JSON); File GDB zip on eCat","license":"CC BY 4.0 (service copyright text); data.gov.au shows 'notspecified'","language":"en","has_coordinates":true,"location_precision":"exact","publisher_type":"national_government","adds":"Official point coordinates for NEM batteries (in service and committed), with GI attributes as of July 2024.","first_seen_pass":1,"rank":4,"summary":"Official GA point layer of NEM batteries with coordinates, MW, MWh, owner and status copied from AEMO GI July 2024 (40 records, 25 In Service).","coverage_note":"NEM only and stale (July 2024 inventory).","data_date":"2024-07","caveats":["Two records with latitude 0.0.","Misses batteries commissioned after mid-2024."],"coverage":{"geographic":"NEM only (QLD, NSW, VIC, SA); 40 records, 25 In Service, as of NEM Generation Information July 2024."},"fine_print":{"unit":{"value":"NameplateCapacity_MW (MW) and StorageCapacity_MWh (MWh) copied from GI.","quote":"('NameplateCapacity_MW', ...), ('StorageCapacity_MWh', ...)","url":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer/0?f=json","attempts":[]},"inclusion_rule":{"value":"In-service and committed large-scale NEM batteries.","quote":"This web map service provides visualisations of in-service and committed, large-scale battery installations connected to the National Energy Market (NEM) power system in eastern and south-eastern Australia.","url":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer?f=json","attempts":[]},"reference_date":{"value":"Attributes from GI July 2024; locations checked with Google Maps.","quote":"Attribute data compiled from the Australian Energy Market Operator’s National Generation Inventory July 2024 and locations checked with Google Maps.","url":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer/0?f=json","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://ecat.ga.gov.au/geonetwork/srv/api/records/747fc5c7-efcc-4df4-99d2-7d314d29ce57","note":"Metadata has a maintenance frequency code but no readable value in the JSON extract."},{"url":"https://data.gov.au/data/api/3/action/package_show?id=battery-storage-facilities-mapserver","note":"data.gov.au record modified 2026-01-08; no frequency stated."}]},"exclusions":{"value":"Only NEM, large-scale; WA, NT and off-grid not included.","quote":"large-scale battery installations connected to the National Energy Market (NEM) power system in eastern and south-eastern Australia","url":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer?f=json","attempts":[]}},"key_fields":[{"field":"Latitude / Longitude","meaning":"Point location (WGS84), placed from Google Maps."},{"field":"UnitStatus","meaning":"In Service / Committed / Committed* (as of July 2024)."},{"field":"NameplateCapacity_MW / StorageCapacity_MWh","meaning":"MW and MWh from GI July 2024."},{"field":"Owner / DUID / FullCommercialUseDate","meaning":"GI owner text, legacy generator DUID (e.g. GANNBG1), FCUD as text (e.g. 'December 2021')."}],"how_to_use":{"example_request":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer/0/query?where=1%3D1&outFields=*&returnGeometry=true&outSR=4326&f=json","example_result":"Victorian Big Battery | In Service | Owner Victorian Big Battery Pty Ltd | FCUD 'December 2021' | lat -38.03872 lon 144.29587","steps":["Query layer 0 with where=1=1, outFields=*, outSR=4326 (40 features; maxRecordCount 2000).","Keep UnitStatus == 'In Service' (25 features) and join on Site_Name to the current GI release; DUIDs are pre-IESS generator DUIDs."],"reading_traps":["Frozen at GI July 2024: misses batteries commissioned since (e.g. Tarong BESS, Orana BESS).","2 records (HBESS) have latitude 0.0; 8 records have coordinates with only 2 decimals (~1 km).","The related GA 'Major Power Stations' layer (430 records) contains no batteries."]},"test":{"tested_on":"2026-11-26","method":"api_query","http_status":200,"content_type":"application/json","size_bytes":31173,"records_total":40,"records_for_country":25,"problems":["Two records have latitude 0.0 (Hazelwood BESS)."]},"evidence":[{"claim":"Scope and lineage.","url":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer/0?f=json","quote":"This layer shows the location of large-scale battery installations connected to the National Energy Market (NEM) in Australia. Attribute data compiled from the Australian Energy Market Operator’s National Generation Inventory July 2024 and locations checked with Google Maps."},{"claim":"eCat record abstract.","url":"https://ecat.ga.gov.au/geonetwork/srv/api/records/747fc5c7-efcc-4df4-99d2-7d314d29ce57","quote":"This dataset provides locations of in-service, large-scale battery installations connected to the National Energy Market (NEM) power system in eastern and south-eastern Australia.  Data compiled from the Australian Energy Market Operator (AEMO)."}],"members":[],"members_summary":null},{"source_id":"openelectricity_facilities","name":"Open Electricity facilities (NEM and WEM)","publisher":"Open Electricity (The Superpower Institute)","official":false,"landing_url":"https://openelectricity.org.au/facilities","data_url":"https://openelectricity.org.au/facilities","access":"web_viewer_only","format":"HTML page with embedded JavaScript data object; API (JSON) requires an API key","license":"CC BY-NC 4.0 (standard licence); commercial use and AI training/grounding need an Enterprise licence","language":"en","has_coordinates":true,"location_precision":"exact","publisher_type":"community","adds":"Only single list covering NEM and WEM batteries with coordinates, MW, MWh, commencement date and owner per facility.","first_seen_pass":1,"rank":5,"summary":"Non-official facility list (NEM + WEM) with coordinates, MW, MWh, commencement date and owner; 68 operating battery units on 2026-11-26.","coverage_note":"Covers NEM and WA SWIS; no NT or off-grid systems found.","data_date":"2026-11-26","caveats":["CC BY-NC 4.0; AI training/grounding excluded from the standard licence.","Commencement date and MWh can differ from AEMO figures."],"coverage":{"geographic":"NEM (QLD, NSW, ACT, VIC, SA, TAS) and WEM (Western Australia SWIS); no NT or other off-grid systems seen."},"fine_print":{"unit":{"value":"capacity_registered / capacity_maximum in MW, capacity_storage in MWh per unit (page labels 'MW' and 'MWh').","quote":"Total Capacity 225 MW Storage 900 MWh","url":"https://openelectricity.org.au/facility/KWINANA_ESR2","attempts":[]},"inclusion_rule":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://openelectricity.org.au/facilities","note":"No inclusion rule text on the facilities page; content mirrors market-registered units (NEM DUIDs, WEM facility codes)."},{"url":"https://platform.openelectricity.org.au/license","note":"Licence page does not describe coverage."}]},"reference_date":{"value":"Live; units carry data_last_seen (e.g. 2026-11-27T00:10+08:00 for KWINANA_ESR2) and updated_at.","quote":"data_last_seen:\"2026-11-27T00:10:00+08:00\"","url":"https://openelectricity.org.au/facility/KWINANA_ESR2","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://openelectricity.org.au/facilities","note":"No stated update frequency for facility metadata."},{"url":"https://platform.openelectricity.org.au/license","note":"Not stated."}]},"exclusions":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://openelectricity.org.au/facilities","note":"No exclusion text; no NT or off-grid facilities found among 505 facilities."},{"url":"https://openelectricity.org.au/facility/KWINANA_ESR2","note":"Facility page footer credits 'AEMO' and 'APVI' only."}]}},"key_fields":[{"field":"network_id / network_region","meaning":"'NEM' + region (e.g. SA1) or 'WEM'."},{"field":"location.lat / location.lng","meaning":"Facility point (WGS84); facility pages also link an OSM way."},{"field":"units[].fueltech_id","meaning":"'battery' = bidirectional battery unit; 'battery_charging'/'battery_discharging' = legacy split units."},{"field":"units[].status_id","meaning":"'operating' or 'commissioning' (68 and 7 battery units on 2026-11-26)."},{"field":"units[].capacity_registered / capacity_maximum / capacity_storage","meaning":"MW registered, MW maximum, MWh storage."},{"field":"units[].commencement_date (+ _specificity)","meaning":"Start date with precision flag (day/month/year); definition not documented."},{"field":"owners[].name","meaning":"Owner shown on facility pages (e.g. Synergy); not present in the list embed."}],"how_to_use":{"example_request":"curl -sL -o facilities.html 'https://openelectricity.org.au/facilities'  # parse embedded objects {code:...,network_id:...,location:{lat,lng},units:[{fueltech_id:\"battery\",status_id,capacity_maximum,capacity_storage,commencement_date}]}","example_result":"Kwinana Battery 2 | WEM | lat -32.202465 lng 115.778452 | KWINANA_ESR2 battery operating | capacity_registered 225 | capacity_storage 900 | commencement_date 2024-09-26 | owner Synergy","steps":["Download the facilities page; the data is a JavaScript object literal (unquoted keys), not JSON - extract with regular expressions or a JS-literal parser.","Split facility objects at '{code:\"...\",code_display:\"...\",name:\"'; read network_id, network_region and location.","Keep units with fueltech_id == 'battery' and status_id == 'operating' (68 units: 62 NEM, 6 WEM on 2026-11-26).","For owner and description open /facility/<code> per facility.","The documented API (api.openelectricity.org.au/v4/facilities/) returns 401 without an API key (sign-up required)."],"reading_traps":["Non-official: MW/MWh can differ from AEMO (e.g. ADPBA1 12.6 MWh here vs MMS MAXSTORAGECAPACITY 6).","commencement_date is not AEMO's FCUD: ADPBA1 commencement 2021-05-18 vs GI July 2024 FCUD 2022-05-01.","Licence CC BY-NC 4.0 excludes commercial use and AI training/grounding under the standard licence.","Legacy facilities may hold only battery_charging/battery_discharging units (e.g. Kennedy Energy Park)."]},"test":{"tested_on":"2026-11-26","method":"download","http_status":200,"content_type":"text/html","size_bytes":5241713,"records_total":505,"records_for_country":68,"problems":["Data embedded as a JavaScript literal in the page; API requires a key (HTTP 401 without one)."]},"evidence":[{"claim":"Facility page gives MW, MWh, status and owner.","url":"https://openelectricity.org.au/facility/KWINANA_ESR2","quote":"Kwinana Battery 2 operating WA Western Australia 2024 ... Total Capacity 225 MW Storage 900 MWh ... Owner Synergy"},{"claim":"Unit carries commencement date and coordinates.","url":"https://openelectricity.org.au/facility/KWINANA_ESR2","quote":"capacity_storage:900,data_first_seen:\"2025-09-02T08:00:00+08:00\",...,commencement_date:\"2024-09-26T00:00:00+08:00\",commencement_date_specificity:\"day\""},{"claim":"Licence terms.","url":"https://platform.openelectricity.org.au/license","quote":"Data and content published through the Service are licensed under the Creative Commons Attribution-NonCommercial 4.0 International (CC BY-NC 4.0) licence."}],"members":[],"members_summary":null},{"source_id":"osm_battery_plants","name":"OpenStreetMap power=plant + plant:source=battery","publisher":"OpenStreetMap contributors","official":false,"landing_url":"https://www.openstreetmap.org/","data_url":"https://api.openstreetmap.org/api/0.6/way/1315308558.json","access":"api","format":"JSON (OSM API 0.6); Overpass QL for bulk queries","license":"ODbL 1.0","language":"en","has_coordinates":true,"location_precision":"exact","publisher_type":"community","adds":"Mapped footprints with operator, plant:output:electricity, plant:storage and start_date tags per element; Open Electricity links facilities to OSM ways.","first_seen_pass":1,"rank":6,"coverage":{"geographic":"Worldwide; Australian completeness not measured (Overpass unavailable during this pass)."},"fine_print":{"unit":{"value":"Free-text tag values with units (e.g. '200 MW', '800 MWh').","quote":"'plant:output:electricity': '200 MW', 'plant:storage': '800 MWh'","url":"https://api.openstreetmap.org/api/0.6/way/1315308558.json","attempts":[]},"inclusion_rule":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://overpass-api.de/api/interpreter","note":"Overpass count query rejected (HTTP 406); kumi.systems 502/busy; private.coffee timed out."},{"url":"https://taginfo.openstreetmap.org/api/4/tag/stats?key=plant:source&value=battery","note":"Taginfo gives 1365 objects worldwide with plant:source=battery, no per-country split."}]},"reference_date":{"value":"Element timestamp (way 1315308558: 2025-02-28).","quote":"\"timestamp\":\"2025-02-28T04:59:29Z\"","url":"https://api.openstreetmap.org/api/0.6/way/1315308558.json","attempts":[]},"update_frequency":{"value":"Continuous (crowd edits); taginfo data until 2026-11-26.","quote":"\"data_until\":\"2026-11-26T00:59:56Z\"","url":"https://taginfo.openstreetmap.org/api/4/tag/stats?key=plant:source&value=battery","attempts":[]},"exclusions":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://overpass-api.de/api/interpreter","note":"Not measurable without Overpass."},{"url":"https://taginfo.openstreetmap.org/api/4/tag/stats?key=plant:source&value=battery","note":"No coverage statement."}]}},"key_fields":[{"field":"plant:source=battery","meaning":"Battery plant tag (generator:source=battery for units)."},{"field":"plant:output:electricity / plant:storage","meaning":"Power and energy as text with units."},{"field":"operator / start_date","meaning":"Operator name and start year as mapped."}],"how_to_use":{"example_request":"curl -s 'https://api.openstreetmap.org/api/0.6/way/1315308558.json'","example_result":"way 1315308558: name 'Kwinana BESS 2', operator 'Synergy', plant:output:electricity '200 MW', plant:storage '800 MWh', start_date '2024', power 'plant'","steps":["Bulk: Overpass QL nwr[\"power\"=\"plant\"][\"plant:source\"=\"battery\"] within the Australia area (not completed in this pass: instances returned 406/502/timeouts).","Per facility: take osm_way_id from Open Electricity and read the way via the OSM API."],"reading_traps":["Tag values can be outdated: Kwinana BESS 2 tagged 200 MW/800 MWh while Open Electricity gives 225/900 and WEM SCADA peaks ~225 MW.","Values are text with units; parse before comparing."]},"test":{"tested_on":"2026-11-26","method":"api_query","http_status":200,"content_type":"application/json; charset=utf-8","size_bytes":809,"records_total":null,"records_for_country":null,"problems":["overpass-api.de answered HTTP 406 to the default curl client; other public instances were overloaded or timed out."]},"evidence":[{"claim":"Tags available on a mapped battery.","url":"https://api.openstreetmap.org/api/0.6/way/1315308558.json","quote":"'name': 'Kwinana BESS 2', 'operator': 'Synergy', 'plant:output:electricity': '200 MW', 'plant:source': 'battery', 'plant:storage': '800 MWh', 'power': 'plant', 'start_date': '2024'"}],"members":[],"members_summary":null},{"source_id":"aemo_nem_registration_list","name":"NEM Registration and Exemption List","publisher":"Australian Energy Market Operator (AEMO)","official":true,"landing_url":"https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","data_url":"https://www.aemo.com.au/-/media/files/electricity/nem/participant_information/nem-registration-and-exemption-list.xlsx?rev=2a09052d2f1d448fb33582038a290bd6&sc_lang=en","access":"direct_download","format":"XLSX","license":"unknown","language":"en","has_coordinates":null,"location_precision":null,"publisher_type":"operator","adds":"Human-readable list of registered participants, generators/scheduled loads and registration exemptions (the exemption part is the only place exempt small units may appear).","first_seen_pass":1,"rank":7,"coverage":{"geographic":"NEM."},"fine_print":{"unit":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.aemo.com.au/-/media/files/electricity/nem/participant_information/nem-registration-and-exemption-list.xlsx?rev=2a09052d2f1d448fb33582038a290bd6&sc_lang=en","note":"HTTP 403 to automated client."},{"url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","note":"Archived landing page describes content but not units."}]},"inclusion_rule":{"value":"Registered participants, applicants, ceasing/suspended registrations, generators and scheduled loads, ancillary services and exemptions (landing page).","quote":"You can view the current registration and exemption list containing all registered participants in the NEM, registration applicants, registrations that are ceasing or suspended, information about generators and scheduled loads, ancillary services, and registration exemptions.","url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","attempts":[]},"reference_date":{"value":"2026-11-10 per archived landing page (copy of 2026-11-16).","quote":"10/11/2026 NEM Registration and Exemption List 765.57 KB","url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","note":"No frequency stated."},{"url":"https://www.aemo.com.au/-/media/files/electricity/nem/participant_information/nem-registration-and-exemption-list.xlsx?rev=2a09052d2f1d448fb33582038a290bd6&sc_lang=en","note":"File blocked (403)."}]},"exclusions":{"value":null,"quote":null,"url":null,"attempts":[{"url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","note":"Not stated."},{"url":"https://www.aemo.com.au/-/media/files/electricity/nem/participant_information/nem-registration-and-exemption-list.xlsx?rev=2a09052d2f1d448fb33582038a290bd6&sc_lang=en","note":"File blocked (403)."}]}},"key_fields":[],"how_to_use":{"example_request":"","example_result":"","steps":["Not tested: the xlsx returned HTTP 403; the same registration data was tested through NEMWEB MMS (nemweb_mms_registration)."],"reading_traps":[]},"test":{"tested_on":"2026-11-26","method":"blocked","http_status":403,"content_type":"text/html","size_bytes":null,"records_total":null,"records_for_country":null,"problems":["Rejects automated clients (HTTP 403, Cloudflare) on the landing page and the xlsx URL."]},"evidence":[{"claim":"Content per landing page (archived copy 2026-11-16).","url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","quote":"You can view the current registration and exemption list containing all registered participants in the NEM, registration applicants, registrations that are ceasing or suspended, information about generators and scheduled loads, ancillary services, and registration exemptions."}],"members":[],"members_summary":null},{"source_id":"offgrid_system_publications","name":"Publications on systems outside the NEM and WEM (Northern Territory, regional and Pilbara WA)","publisher":"NT Utilities Commission; Territory Generation; Horizon Power; WA Government (Energy Policy WA)","official":true,"landing_url":null,"data_url":null,"access":"pdf","format":"PDF reports and web pages","license":"unknown","language":"en","has_coordinates":null,"location_precision":null,"publisher_type":"regional_government","adds":"Where information on off-grid/isolated systems would be published; no per-installation list found and the NT and Horizon Power sites reject automated clients.","first_seen_pass":1,"rank":8,"coverage":{"geographic":"Northern Territory (Darwin-Katherine, Alice Springs, Tennant Creek per search snippets, not verified), regional WA microgrids, Pilbara NWIS."},"fine_print":{"unit":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://utilicom.nt.gov.au/__data/assets/pdf_file/0005/1619636/2025-northern-territory-electricity-outlook-report-update.pdf","note":"HTTP 403 (curl and WebFetch)."},{"url":"https://web.horizonpower.com.au/our-community/news-events/news/horizon-power-expanding-its-battery-storage-capabilities","note":"HTTP 403."}]},"inclusion_rule":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://utilicom.nt.gov.au/__data/assets/pdf_file/0005/1619636/2025-northern-territory-electricity-outlook-report-update.pdf","note":"HTTP 403 (curl and WebFetch)."},{"url":"https://web.horizonpower.com.au/our-community/news-events/news/horizon-power-expanding-its-battery-storage-capabilities","note":"HTTP 403."}]},"reference_date":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://utilicom.nt.gov.au/__data/assets/pdf_file/0005/1619636/2025-northern-territory-electricity-outlook-report-update.pdf","note":"HTTP 403 (curl and WebFetch)."},{"url":"https://web.horizonpower.com.au/our-community/news-events/news/horizon-power-expanding-its-battery-storage-capabilities","note":"HTTP 403."}]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://utilicom.nt.gov.au/__data/assets/pdf_file/0005/1619636/2025-northern-territory-electricity-outlook-report-update.pdf","note":"HTTP 403 (curl and WebFetch)."},{"url":"https://web.horizonpower.com.au/our-community/news-events/news/horizon-power-expanding-its-battery-storage-capabilities","note":"HTTP 403."}]},"exclusions":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://utilicom.nt.gov.au/__data/assets/pdf_file/0005/1619636/2025-northern-territory-electricity-outlook-report-update.pdf","note":"HTTP 403 (curl and WebFetch)."},{"url":"https://web.horizonpower.com.au/our-community/news-events/news/horizon-power-expanding-its-battery-storage-capabilities","note":"HTTP 403."}]}},"key_fields":[],"how_to_use":{"example_request":"","example_result":"","steps":["Not tested: NT Utilities Commission, Territory Generation (NT Parliament) and Horizon Power documents returned HTTP 403; open them with a browser session."],"reading_traps":["NWIS is several loosely connected networks with different owners; no single operator list was found."]},"test":{"tested_on":"2026-11-26","method":"blocked","http_status":403,"content_type":"text/html","size_bytes":null,"records_total":null,"records_for_country":null,"problems":["NT Government (utilicom.nt.gov.au, parliament.nt.gov.au) and Horizon Power sites reject automated clients (HTTP 403)."]},"evidence":[{"claim":"NWIS structure.","url":"https://stateofenergy.wa.gov.au/wa-energy-system/north-west-interconnected-system","quote":"Unlike the South West Interconnected System, the NWIS is not truly interconnected. Instead, it is made up of several loosely connected networks owned and operated by different parties, rather than a single, centrally managed system."}],"members":[{"name":"NT Utilities Commission - Northern Territory Electricity Outlook Report (2025 Update)","landing_url":"https://utilicom.nt.gov.au/electricity/reporting/electricity-outlook-report","data_url":"https://utilicom.nt.gov.au/__data/assets/pdf_file/0005/1619636/2025-northern-territory-electricity-outlook-report-update.pdf","access":"pdf","tested":false,"data_found":null,"note":"Landing page and PDF HTTP 403 (curl and WebFetch)."},{"name":"Territory Generation - 2026-27 Statement of Corporate Intent (NT Parliament)","landing_url":"https://parliament.nt.gov.au/__data/assets/pdf_file/0003/1618203/Territory-Generation-2026-27-Statement-of-Corporate-Intent.pdf","data_url":"https://parliament.nt.gov.au/__data/assets/pdf_file/0003/1618203/Territory-Generation-2026-27-Statement-of-Corporate-Intent.pdf","access":"pdf","tested":false,"data_found":null,"note":"HTTP 403."},{"name":"Horizon Power (regional WA microgrids) news pages","landing_url":"https://web.horizonpower.com.au/our-community/news-events/news/horizon-power-expanding-its-battery-storage-capabilities","data_url":null,"access":"web_viewer_only","tested":false,"data_found":null,"note":"HTTP 403 (curl and WebFetch)."},{"name":"WA State of Energy - North West Interconnected System","landing_url":"https://stateofenergy.wa.gov.au/wa-energy-system/north-west-interconnected-system","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"Describes NWIS structure; no list of batteries."},{"name":"WA Government media statements (Horizon Power Kununurra vanadium battery)","landing_url":"https://www.wa.gov.au/government/media-statements/Cook-Labor-Government/Vanadium-battery-to-power-regional-WA--20230731","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"78 kW/220 kWh battery purchase announced 2023; no operation date."}],"members_summary":{"total":null,"listed":5,"tested":2,"data_found":0,"scope_note":"Off-grid systems: NT regulated systems, Horizon Power microgrids, Pilbara NWIS and others (Mount Isa, island grids) not enumerated; 5 publications tried, 2 opened, none with a list.","pattern":"Look for the system's utility regulator outlook report, the state-owned generator's annual report or Statement of Corporate Intent, and state media statements naming the battery."},"member_scope":{"total":null,"note":"Off-grid systems: NT regulated systems, Horizon Power microgrids, Pilbara NWIS and others (Mount Isa, island grids) not enumerated; 5 publications tried, 2 opened, none with a list.","pattern":"Look for the system's utility regulator outlook report, the state-owned generator's annual report or Statement of Corporate Intent, and state media statements naming the battery."}}],"sector":{"regulator":{"name":"Australian Energy Regulator (AER) for the NEM; in WA the ESM Rules are made by the WA Government (Energy Policy WA)","url":"https://www.aer.gov.au/"},"operators":{"structure":"many","note":"Batteries belong to many owners (often project SPVs); AEMO registers units and operates the NEM and WEM; the Pilbara NWIS is several networks with different owners; NT systems are outside both markets.","census_url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23PARTICIPANT%23FILE01%23202610010000.zip"},"publication_obligation":{"exists":"yes","norm":"NEM: National Electricity Rules clauses 3.7F, 3.13.3A, 2.1B.3, 2.10.1 and 3.13.3(a)(2A) (cited in GI); WEM: ESM Rules clause 2.34B.1(e)","url":"https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en","what_must_be_published":"NEM: technical and operational parameters of existing, committed and proposed generation or storage projects submitted to AEMO; WEM: names and System Sizes of Registered Facilities.","frequency":"NEM: every three months or as required; WEM: daily (06:30 AWST)"},"consolidated_republication":{"found":"partial","note":"AEMO republishes participant submissions per market (NEM GI and MMS; WEM facilities). No file joins NEM, WEM and off-grid systems; GA's layer copies GI July 2024.","checked_pages":[{"organization":"AEMO (NEM)","url":"http://web.archive.org/web/20261114233107/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-planning-data/generation-information","saw":"Generation information page (archived 2026-11-14): consolidated 'NEM' data file, quarterly; live page 403."},{"organization":"AEMO (NEM)","url":"https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/","saw":"MMSDM monthly registration tables incl. 70 bidirectional DUIDs with MAXSTORAGECAPACITY."},{"organization":"AEMO (WEM)","url":"https://data.wa.aemo.com.au/datasets/definitions/facilities-definition.yaml","saw":"Facilities dataset: names and System Size of all Registered Facilities, daily."},{"organization":"Geoscience Australia","url":"https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer?f=json","saw":"Battery layer compiled from AEMO GI July 2024, NEM only."}]}},"national_registry":{"exists":"partial","note":"No single official national register of operating batteries. AEMO's NEM registration data and Generation Information cover the NEM only; the WEM facilities list covers WA's SWIS; NT and other off-grid systems are outside both.","checked_pages":[{"organization":"AEMO","url":"http://web.archive.org/web/20261114233107/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-planning-data/generation-information","saw":"NEM Generation Information page (archived copy): NEM-only consolidated file."},{"organization":"AEMO","url":"http://web.archive.org/web/20261116083129/https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/participate-in-the-market/registration","saw":"NEM Registration and Exemption List described; xlsx blocked (403)."},{"organization":"AEMO (WA)","url":"https://data.wa.aemo.com.au/","saw":"WEM Market Data portal: Registration > Facilities (SWIS only)."},{"organization":"Geoscience Australia","url":"https://ecat.ga.gov.au/geonetwork/srv/api/records/747fc5c7-efcc-4df4-99d2-7d314d29ce57","saw":"Battery Storage Facilities: NEM-connected in-service batteries only."},{"organization":"data.gov.au","url":"https://data.gov.au/data/api/3/action/package_search?q=battery%20storage&rows=30","saw":"395 hits for 'battery storage'; only GA battery layers are installation lists."},{"organization":"Clean Energy Regulator","url":"https://cer.gov.au/markets/reports-and-data/small-scale-installation-postcode-data","saw":"Small-scale battery counts and kWh by postcode only."},{"organization":"AER","url":"https://www.aer.gov.au/","saw":"Site unreachable (HTTP/2 error to curl; WebFetch timeouts on AER pages)."},{"organization":"NT Utilities Commission","url":"https://utilicom.nt.gov.au/electricity/reporting/electricity-outlook-report","saw":"HTTP 403 to automated clients."}]},"if_unstructured":{"summary":"Official structured data cover the NEM (no coordinates, few commissioning dates) and WA's SWIS (no MWh, location or dates). Missing pieces come from AEMO's release archive and Change Log and from WA government pages and reports; NT/off-grid documents could not be opened.","recipe":["NEM list: take GI 'Generator Information' rows with Technology Type 'Battery Storage' and Commitment Status 'In Service' (+ 'In Commissioning'); join DUID to MMS DUDETAIL (latest version), DUDETAILSUMMARY, STATION and PARTICIPANT (64 of 70 bidirectional DUIDs match GI).","NEM in-service date: in the GI 'Change Log' find 'Unit Status Updated From In Commissioning To In Service' (e.g. LDBESS1 in the 2026-10-30 release); for units in service before 2025 read FCUD in older releases (July 2024: 19 of 24 in-service battery rows filled).","Evidence case NESBESS1 (New England Solar Farm BESS): Change Log 2026-01-30 'From Anticipated to Committed*'; MMS registration 2026-02-18 (START_DATE, station 'COMMISSIONED'); first SCADA output 2026-02-18 05:50 (1.76 MW); 2026-04-30 'Committed* To In Commissioning' (hold point >=30%); Oct 2026 SCADA +/-100 MW but still 'In Commissioning' with FCUD moved to 2026-07-31.","NEM location: STATION address/locality (road or lot + locality + postcode), KCI 'Site Location Description' via AEMO KCI ID (29 of 58 rows), GA points for the 25 units in service in July 2024.","WEM: select '_ESR'/'_BESS' codes in facilities.csv; MW = System Size / 2 or max(Average MWh) x 12 from FacilitySCADA; status and dates from WA State of Energy pages; MWh only aggregated officially (WATC) for Synergy's three batteries."],"location_method":"Use the MMS STATION street/lot address (not PO boxes) or the KCI free-text description for NEM units, GA coordinates for the 2024 fleet; for newer NEM and all WEM units only non-official points (Open Electricity, OSM) were found.","cross_with":["GI DUID <-> MMS DUID (registration, participant, address, SCADA).","GI 'AEMO KCI ID' <-> KCI datafile 'Site Location Description'.","WEM Facility Code <-> Facility SCADA (actual MW) and Open Electricity unit code.","Open Electricity osm_way_id <-> OSM API element tags.","GA Site_Name/legacy DUID <-> current GI site name."],"where_published":[{"name":"WA State of Energy (Energy Policy WA) system pages","url":"https://stateofenergy.wa.gov.au/wa-energy-system/collie-battery","what":"Government pages on WA energy-system assets (batteries, NWIS) with status and dates in prose.","how_to_search_inside":"Browse the 'WA energy system' section by asset name; no search or data download tested.","example_document":{"url":"https://stateofenergy.wa.gov.au/wa-energy-system/collie-battery","what_it_gives":"Neoen Collie Battery: 'The project is fully operational. Stage 1 commenced operations in October 2024, with Stage 2 coming online a year later.'; 'Just 13km northeast of Collie'."}},{"name":"WA Treasury Corporation Sustainable Bond Program Allocation and Impact Report","url":"https://www.watc.wa.gov.au/media/4hijzqvs/sustainable-bond-program-allocation-and-impact-report-may-2026.pdf","what":"Status, rated MW and MWh of state-funded projects, incl. Synergy's large-scale batteries.","how_to_search_inside":"PDF (17.5 MB); search text 'Large-Scale Batteries' (pp. 29-30).","example_document":{"url":"https://www.watc.wa.gov.au/media/4hijzqvs/sustainable-bond-program-allocation-and-impact-report-may-2026.pdf","what_it_gives":"KBESS Stage 1, KBESS Stage 2 and CBESS: 'Status / Key dates Fully operational December 2025.'; 'Peak Power Output: 825 MW (rated capacity)'; 'Energy Storage: 3,500 MWh (rated energy capacity)' (combined)."}},{"name":"WA Government media statements","url":"https://www.wa.gov.au/government/media-statements/Cook-Labor-Government/Vanadium-battery-to-power-regional-WA--20230731","what":"Announcements on state-owned batteries (purchase, construction, switch-on).","how_to_search_inside":"Web search restricted to wa.gov.au with the battery name; announcements are not status records.","example_document":{"url":"https://www.wa.gov.au/government/media-statements/Cook-Labor-Government/Vanadium-battery-to-power-regional-WA--20230731","what_it_gives":"'The 78-kilowatt/220kWh battery will enable Horizon Power to test the capabilities of providing long periods of 100% renewable energy' (Kununurra; purchase, no operation date)."}}]},"related_not_answering":[{"name":"CER small-scale installation postcode data (SGU-Battery)","url":"https://cer.gov.au/markets/reports-and-data/small-scale-installation-postcode-data","why":"Counts and kWh of home batteries by postcode since 1 July 2025; totals per postcode, not a list of installations."},{"name":"Geoscience Australia Major Power Stations layer","url":"https://services.ga.gov.au/gis/rest/services/Electricity_Infrastructure/MapServer/1","why":"430 power stations with coordinates but no battery installations (only pumped hydro)."},{"name":"WEM Facility/Component Certified Reserve Capacity","url":"https://data.wa.aemo.com.au/datasets/definitions/facility-certified-reserve-capacity-definition.yaml","why":"Capacity credits in MW per facility; not installed power, energy or status."},{"name":"ARENA Community Batteries Data Summary (June 2026)","url":"https://arena.gov.au/assets/2026/06/Community-Batteries-Data-Summary-1.pdf","why":"Programme portfolio statistics and state maps ('Currently, 23 batteries have been installed'); no per-battery list."},{"name":"WA Treasury Corporation bond report - Large-Scale Batteries","url":"https://www.watc.wa.gov.au/media/4hijzqvs/sustainable-bond-program-allocation-and-impact-report-may-2026.pdf","why":"Rated MW/MWh and status aggregated for three Synergy batteries; not per installation (used only in the recipe)."}],"open_questions":["Waratah Super Battery (WTAHB1): GI Oct 2026 says 'Committed' (FCUD 2026-09-01) but MMS SCADA shows +556.8/-569.4 MW in Oct 2026; only AEMO can state its commissioning status.","MWh basis: GI nameplate MWh and MMS MAXSTORAGECAPACITY differ by >10% for 10 units (e.g. LIMBESS1 400 vs 536; ADPBA1 12.6 vs 6); the definitions behind each figure are not published in the files.","Kwinana Battery 2 (KWINANA_ESR2): Open Electricity 225 MW/900 MWh vs OSM 200 MW/800 MWh; SCADA supports ~225 MW, but no opened official source gives its MWh (Synergy pages 403)."],"history":[{"pass":1,"date":"2026-11-26","role":"research","model":"claude-sonnet-5-5","rules_version":"2026-11-26-de-fr-baterias","note":"First pass: NEM (GI, MMS), WEM facilities/SCADA, GA and Open Electricity tested; registration vs first output vs in-service case documented (NESBESS1); NT/off-grid sites blocked (403).","headline":{"official_data":"partial","non_official_data":"usable","national_registry":"partial"},"sources":{"total":8,"new":8,"dropped":0},"negatives":{"overturned":0,"confirmed":0},"effort":{"pages":64,"minutes":40}}],"local_terms":[{"term":"NEM Generation Information","language":"en","meaning":"AEMO's quarterly xlsx of existing and proposed NEM generating/storage units; filter Technology Type 'Battery Storage'."},{"term":"DUID (Dispatchable Unit Identifier)","language":"en","meaning":"Unit code that joins GI, MMS tables, SCADA and Open Electricity."},{"term":"Bidirectional unit (BIDIRECTIONAL)","language":"en","meaning":"MMS DISPATCHTYPE for batteries registered under the IESS rules (from mid-2024)."},{"term":"Electric Storage Resource (ESR)","language":"en","meaning":"WEM term for storage; battery facility codes contain '_ESR' (or '_BESS')."},{"term":"System Size","language":"en","meaning":"WEM facility capacity in MW; for storage it adds withdrawal to sent-out capacity."},{"term":"Full Commercial Use Date (FCUD)","language":"en","meaning":"GI field: date units are expected to become operationally available after NER 5.7.3 tests."},{"term":"In Commissioning / In Service","language":"en","meaning":"GI statuses: hold point >=30% capacity passed / commissioning signed off by AEMO."},{"term":"BESS","language":"en","meaning":"Battery energy storage system; common in AEMO site names (e.g. 'Orana BESS')."}],"provenance":{"pass_count":1,"models":["claude-sonnet-5-5"],"minutes_estimate":40,"pages_opened":64,"passes":[{"pass":1,"date":"2026-11-26","model":"claude-sonnet-5-5"}],"note":"Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed."},"card_url":"https://georutter.org/v1/au/battery-storage.json","detail_url":"https://georutter.org/v1/au/battery-storage/detail.json","html_url":"https://georutter.org/au/battery-storage/","country_url":"https://georutter.org/v1/countries/au.json"}