{"schema_version":"1.0","country":"de","country_name":"Germany","topic":"grid-expansion-plans","question":"Where can I get the planned new power lines and substations in Germany, with location, voltage, planned date and status?","territory":"de","territory_level":"country","parent_url":null,"published_on":"2026-11-26","research_reviewed_on":"2026-11-26","access_checked_on":"2026-11-26","answer":{"official_data":"partial","non_official_data":"partial","summary":"Germany has separate transmission and distribution plans. BNetzA's Monitoring_gdb FeatureServer maps 183 BBPlG/EnLAG transmission sections (Luftlinie, Korridorverlauf, Trassenverlauf). Project sheets and NEP 2037/2045 PDFs add commissioning dates and 871 substation measures. BSH's FEP 2025 WFS/GeoJSON maps offshore platforms and cables. For distribution, 95 of 814 VNBdigital operators have an active plan service. The 2026 XLSX examples checked lack coordinates.","main_caveats":["BNetzA and NEP cover transmission. 95 of 814 VNBdigital listings have an active distribution plan service. The exemption for operators below 100,000 customers has an exception for qualifying curtailment under § 14d(8) EnWG.","Substations lack unified official GIS: BNetzA maps 205 unattributed nodes (Vorhabenpunkte) and embeds HVDC converters in line sheets, while NEP's 871 substation Punktmaßnahmen and DSO Umspannwerke are published without coordinates.","Corridor vs route geometry: BNetzA's Monitoring_gdb mixes straight-line node pairs (Luftlinie, 34), federal corridors (Korridorverlauf, 13) and concrete/approved routes (Trassenverlauf, 136); always filter by Typ and Vorhabenst.","Missing dates and voltages in GIS: BNetzA Monitoring_gdb omits commissioning dates (shown on netzausbau.de HTML sheets and NEP PDFs) and sets Spannung='unbekannt' on 23/157 BBPlG features; BSH FEP GeoJSON omits voltage and year.","VNBdigital 2026 XLSX traps: DSO spreadsheets lack coordinates, encode start/commissioning months as Excel serial integers, report voltage tiers (HS, UW HS auf MS, MS, NS) not kV, and some DSOs (e.g. Netze BW) anonymize asset names."],"confidence":"high","confidence_reason":"Directly queried BNetzA ArcGIS FeatureServers, BSH FEP 2025 GeoJSON/WFS, VNBdigital GraphQL and 2026 DSO XLSX tables, NEP 2037/2045 PDFs, ENTSO-E TYNDP 2026 JSON API, OpenStreetMap Overpass, and EnWG §§ 12b, 14d–14e statutory texts.","attributes":[{"attribute":"location","covered":"partial","source_ids":["bnetza-netzausbau-gis","bsh-flaechenentwicklungsplan","entsoe-tyndp","osm-overpass-planned-grid","nep-strom","vnbdigital-netzausbauplaene"],"note":"Exact GIS lines/polygons for BBPlG/EnLAG transmission (corridor vs route) and BSH offshore platforms/cables; NEP substations and VNBdigital DSO plans give names/regions only.","gap":"not_published","gap_note":"No official coordinates are published for NEP's 871 onshore substation Punktmaßnahmen or VNBdigital's § 14d EnWG distribution measures (PDF raster maps and substation/region names only, with some DSOs such as Netze BW anonymizing measure names); DSOs under 100,000 customers without >3% curtailment are exempt under § 14d Abs. 8 EnWG."},{"attribute":"voltage","covered":"partial","source_ids":["bnetza-netzausbau-gis","nep-strom","vnbdigital-netzausbauplaene","osm-overpass-planned-grid"],"note":"BNetzA GIS/HTML and NEP PDFs report kV (including AC/DC hybrids and 380/110-kV transformers); VNBdigital XLSX gives tier codes (HS, UW HS auf MS, MS, NS); OSM uses Volts.","gap":"not_published","gap_note":"23 of 157 BNetzA Vorhaben_BBPlG GIS features state Spannung='unbekannt' (and 1 null), BSH FEP 2025 GeoJSON/WFS and TYNDP 2026 preliminary API omit voltage fields, and VNBdigital XLSX standardizes voltage tiers (HS, MS, NS) rather than kV except in unstandardized prose descriptions."},{"attribute":"planned_date","covered":"partial","source_ids":["nep-strom","vnbdigital-netzausbauplaene","entsoe-tyndp","bnetza-netzausbau-gis"],"note":"NEP Projektsteckbriefe, netzausbau.de HTML project sheets and TYNDP give target commissioning years; VNBdigital 2026 XLSX gives expected start and commissioning month/year.","gap":"not_published","gap_note":"Commissioning dates are absent from BNetzA's Monitoring_gdb ArcGIS FeatureServer, BSH's FEP 2025 GeoJSON/WFS, and NEP's 871-row Punktmaßnahmen substation PDF (which flags only Startnetz vs 2037/2045 scenarios); OSM carries date tags on only 4 of 436 features, and exempt small DSOs publish no § 14d EnWG tables."},{"attribute":"status","covered":"partial","source_ids":["bnetza-netzausbau-gis","vnbdigital-netzausbauplaene","entsoe-tyndp","bsh-flaechenentwicklungsplan","osm-overpass-planned-grid"],"note":"BNetzA GIS tracks 6 permitting/construction stages per section; VNBdigital XLSX gives both Projektstatus and permitting stage per DSO asset; TYNDP gives 4 status classes.","gap":"not_published","gap_note":"NEP's Punktmaßnahmen table distinguishes Startnetz from Zubaunetz without permitting or construction phases. BSH FEP 2025 assigns status='planned' to wind areas and sites. The VNBdigital directory does not establish which operators outside the active plan service publish status tables elsewhere."},{"attribute":"latest_data","covered":"yes","source_ids":["bnetza-netzausbau-gis","vnbdigital-netzausbauplaene","nep-strom","bsh-flaechenentwicklungsplan","entsoe-tyndp","osm-overpass-planned-grid"],"note":"BNetzA GIS edited 2026-10-08 (Q2/2026 cut-off, HTML sheets to 2026-11-25); VNBdigital NAP 2026 drafts 2026-10-31; NEP V2025 2nd Draft 2026-03/08; BSH FEP 2025-01-30; TYNDP 2026.","gap":null,"gap_note":null},{"attribute":"historical_series","covered":"partial","source_ids":["nep-strom","bnetza-netzausbau-gis","vnbdigital-netzausbauplaene","bsh-flaechenentwicklungsplan"],"note":"NEP archives biennial plans from 2012 to 2025; BNetzA archives quarterly PDF reports (2013–2026); VNBdigital keeps 2024 PDFs and 2026 XLSX/PDFs; BSH archives FEP 2019–2025.","gap":"not_published","gap_note":"BNetzA's Monitoring_gdb FeatureServer overwrites geometries in place without historical GIS snapshots, distribution Netzausbaupläne under § 14d EnWG began only in 2024 (no pre-2024 series, and 2024 was PDF-only whereas 2026 added XLSX), and NEP project/measure IDs split or renumber across cycles."},{"attribute":"update_frequency","covered":"yes","source_ids":["bnetza-netzausbau-gis","vnbdigital-netzausbauplaene","nep-strom","bsh-flaechenentwicklungsplan","entsoe-tyndp","osm-overpass-planned-grid"],"note":"Quarterly BNetzA monitoring (plus continuous web updates); biennial NEP (§ 12b EnWG), DSO NAP by 31 Oct (§ 14d EnWG) and TYNDP; statutory BSH FEP updates; continuous OSM edits.","gap":null,"gap_note":null}]},"sources":[{"source_id":"bnetza-netzausbau-gis","name":"Netzausbau Monitoring_gdb, Vorhabenpunkte & Projektsteckbriefe (netzausbau.de)","publisher":"Bundesnetzagentur (BNetzA) & 50Hertz, Amprion, TenneT, TransnetBW","official":true,"landing_url":"https://www.netzausbau.de/Vorhaben/uebersicht/karte/karte.html","data_url":"https://services-eu1.arcgis.com/TJm8oSvOdJUQvQT5/arcgis/rest/services/Monitoring_gdb/FeatureServer","access":"api","format":"ArcGIS FeatureServer (JSON / GeoJSON) + HTML project sheets & PDF quarterly reports","license":"Copyright Bundesnetzagentur / 50Hertz, Amprion, TenneT, TransnetBW (no open-data license stated)","language":"de","has_coordinates":true,"location_precision":"exact","publisher_type":"regulator","adds":"Authoritative GIS polylines (corridors vs concrete/approved routes), voltage and permitting/construction phase for statutory BBPlG and EnLAG transmission projects, paired with HTML project sheets giving target commissioning years.","first_seen_pass":1,"rank":1,"summary":"Official ArcGIS REST FeatureServer behind netzausbau.de mapping statutory BBPlG and EnLAG transmission projects by permitting section, paired with HTML project sheets.","coverage_note":"183 polyline section features (157 BBPlG across 106 statutory projects; 26 EnLAG across 22 projects), of which 138 are planned/in permitting/under construction/completed and 45 already in operation; plus 205 connection nodes in Vorhabenpunkte and 135 HTML project sheets.","data_date":"2026-10-08","caveats":["Omits planned commissioning dates in GIS (fetch 'Gesamtinbetriebnahme' from netzausbau.de HTML project sheets) and marks Spannung='unbekannt' on 23/157 BBPlG features.","Covers extra-high-voltage transmission lines only; substations/converters are not standalone attributed GIS records, and Typ mixes Luftlinie (34), Korridorverlauf (13) and Trassenverlauf (136)."],"coverage":{"geographic":"Germany nationwide (onshore extra-high-voltage transmission grid and statutory cross-border/offshore grid links under BBPlG and EnLAG)"},"fine_print":{"unit":{"value":"Polyline permitting/monitoring sections (Abschnitte) in Vorhaben_BBPlG (157 features across 106 unique Vorhabennu) and Vorhaben_EnLAG (26 features across 22 unique Vorhabennu); companion Vorhabenpunkte has 205 connection points.","quote":"Mit der Genehmigung einer Leitung (Planfeststellungs­beschluss) wird der genaue Verlauf einer Leitung fest­gelegt und der zuständige Netzbetreiber darf mit den Bau­maßnahmen beginnen.","url":"https://www.netzausbau.de/Daten/prognose/de.html","attempts":[]},"inclusion_rule":{"value":"Statutory extra-high-voltage transmission projects enacted by federal parliament in the Bundesbedarfsplangesetz (BBPlG) and Energieleitungsausbaugesetz (EnLAG).","quote":"Übersichtskarte: Vorhaben aus dem BBPlG und dem EnLAG","url":"https://www.netzausbau.de/Daten/monitoring/de.html","attempts":[]},"reference_date":{"value":"ArcGIS FeatureServer last edited 2026-10-08 (matching Q2/2026 Monitoring cut-off); individual HTML Vorhaben pages updated continuously (e.g. 2026-11-25 on BBPlG 03).","quote":"Stand: Q2/2026; Quelle: Bundesnetzagentur/DANA","url":"https://www.netzausbau.de/Daten/prognose/de.html","attempts":[]},"update_frequency":{"value":"Quarterly monitoring releases from BNetzA's internal DANA database, with continuous HTML updates on netzausbau.de as permitting decisions occur.","quote":"Die Bundes­netz­agentur aktualisiert die Übersicht kontinuierlich.","url":"https://www.netzausbau.de/Daten/prognose/de.html","attempts":[]},"exclusions":{"value":"Excludes 110 kV and MV/LV distribution grids, pre-statutory NEP candidate projects not yet in BBPlG, and standalone substations/transformers (HVDC converters appear only as sub-sections of line projects such as BBPlG 05 Abschnitt D3b).","quote":"Insgesamt beläuft sich der Bedarf beim Netzausbau auf rund 16.900 km Höchst­spannungs­leitungen.","url":"https://www.netzausbau.de/Daten/prognose/de.html","attempts":[]}},"key_fields":[{"field":"Vorhabennu / Vorhaben","meaning":"Statutory project identifier (e.g. 'BBPlG 03', 'EnLAG 07') and endpoint route name."},{"field":"Typ","meaning":"Spatial precision of the geometry: 'Luftlinie' (straight-line node pair), 'Korridorverlauf' (spatial/federal corridor under ROV/Bundesfachplanung), or 'Trassenverlauf' (concrete/approved route)."},{"field":"Vorhabenst","meaning":"Section status: not in permitting, in ROV/Bundesfachplanung, before/in Planfeststellungsverfahren, approved or under construction, completed, or in operation."},{"field":"Spannung / Technik / Ausführung","meaning":"Voltage ('380 kV', '525 kV', '320 kV', '320 bis 525 kV', or 'unbekannt'), AC vs DC technology, and overhead ('Freileitung') vs underground ('Erdkabel')."},{"field":"Vorhabentr / Zuständigk / Link","meaning":"Responsible TSO(s), permitting authority ('Bundesnetzagentur' vs 'Landesbehörden'), and slug linking to https://www.netzausbau.de/Vorhaben/ansicht/de.html for 'Gesamtinbetriebnahme'."}],"how_to_use":{"example_request":"curl -sL 'https://services-eu1.arcgis.com/TJm8oSvOdJUQvQT5/arcgis/rest/services/Monitoring_gdb/FeatureServer/0/query?where=1%3D1&outFields=Vorhabennu,Vorhaben,Typ,Vorhabenst,Spannung,Technik,Vorhabentr,Link&resultRecordCount=2&outSR=4326&f=json'","example_result":"{\"features\":[{\"attributes\":{\"Vorhabennu\":\"BBPlG 87\",\"Typ\":\"Luftlinie\",\"Vorhabenst\":\"Abschnitt vor/im Planfeststellungsverfahren\",\"Spannung\":\"unbekannt\",\"Technik\":\"Wechselstrom (AC)\",\"Vorhabentr\":\"50Hertz\",\"Link\":\"vorhaben87\"},\"geometry\":{\"paths\":[[[13.5501,52.4988],[13.5244,52.4632]]]}}]}","steps":["Query Layer 0 (Vorhaben_BBPlG, 157 features) and Layer 1 (Vorhaben_EnLAG, 26 features) with outSR=4326&f=geojson or f=json; maxRecordCount is 2000 so each layer fits in a single request.","Filter out already operational sections via Vorhabenst <> 'Abschnitt in Betrieb' (removes 28 BBPlG and 17 EnLAG sections) to isolate planned, permitting, under-construction and newly built sections.","Separate geometry stages via Typ: 'Trassenverlauf' (concrete/plan-approved alignment), 'Korridorverlauf' (500–1,000 m federal corridor), and 'Luftlinie' (schematic straight line).","Join connection nodes from .../Vorhabenpunkte/FeatureServer/0 (205 points) and fetch expected commissioning year ('Gesamtinbetriebnahme') from https://www.netzausbau.de/Vorhaben/ansicht/de.html?nummer=<N>&gruppe=bbplg."],"reading_traps":["Monitoring_gdb omits planned commissioning dates ('Gesamtinbetriebnahme'); those appear only on each project's HTML Steckbrief (e.g. 'geplant für 2028' on BBPlG 03) and in the 191 MB quarterly Monitoringbericht PDF.","23 of 157 Vorhaben_BBPlG features have Spannung='unbekannt' and 1 has null; cross-check the HTML Steckbrief or NEP Projektsteckbriefe for voltage.","Features include operational history ('Abschnitt in Betrieb': 28 BBPlG, 17 EnLAG); failing to filter Vorhabenst overcounts planned lines.","Substations and HVDC converters are not separate features in Monitoring_gdb; Vorhabenpunkte/FeatureServer/0 gives only Name and StartEnd ('ja'/'nein') without voltage or status, while converters appear as line sub-sections (e.g. BBPlG 05 'Konverterbereich Isar (Abschnitt D3b)')."]},"test":{"tested_on":"2026-11-25","method":"api_query","http_status":200,"content_type":"application/json; charset=utf-8","size_bytes":9480996,"records_total":183,"records_for_country":183,"problems":[]},"evidence":[{"claim":"netzausbau.de interactive map loads public ArcGIS FeatureLayers for BBPlG (Layer 0), EnLAG (Layer 1), offshore Anbindungsleitungen, and Vorhabenpunkte.","url":"https://www.netzausbau.de/Vorhaben/uebersicht/karte/karte.html","quote":"var bbplgUrl = \"https://services-eu1.arcgis.com/TJm8oSvOdJUQvQT5/arcgis/rest/services/Monitoring_gdb/FeatureServer/0\";"},{"claim":"HTML project sheet for BBPlG 03 (SuedLink) provides HVDC voltage (525 kV), capacity (2 GW) and planned commissioning year (2028) missing from the GIS table.","url":"https://www.netzausbau.de/Vorhaben/ansicht/de.html?nummer=3&gruppe=bbplg","quote":"technische Daten Gleichstrom (2 GW) | 525 kV ... Gesamtinbetriebnahme geplant für 2028"},{"claim":"BNetzA's underlying DANA database is login-restricted to TSOs, permitting authorities, BMWE and BNetzA.","url":"https://www.netzausbau.de/Daten/DANA/de.html","quote":"Die Web­anwendung ist für die Übertragungs­netz­betreiber, die Genehmigungs­behörden, das Bundes­wirtschafts­ministerium sowie die Bundes­netz­agentur zugänglich."}],"members":[],"members_summary":null},{"source_id":"vnbdigital-netzausbauplaene","name":"VNBdigital — Netzausbaupläne der Verteilernetzbetreiber (§§ 14d, 14e EnWG)","publisher":"VNB digital GmbH & deutsche Elektrizitätsverteilernetzbetreiber","official":true,"landing_url":"https://www.vnbdigital.de/","data_url":"https://www.vnbdigital.de/gateway/graphql","access":"api","format":"GraphQL JSON index + operator XLSX spreadsheets (Maßnahmenplan & kompakt) and PDF reports","license":"Operator-specific: mostly unstated/all rights reserved; some operators apply CC BY 4.0 to XLSX (e.g. Bayernwerk Netz GmbH) and CC BY-ND 4.0 to PDF","language":"de","has_coordinates":false,"location_precision":"municipality","publisher_type":"operator","adds":"Indexes individual distribution network plans. VNBdigital lists 95 operators with an active plan service. Checked examples include 2026 XLSX measure tables and PDF reports.","first_seen_pass":1,"rank":2,"summary":"Statutory § 14e EnWG joint portal where obligated electricity DSOs publish biennial § 14d EnWG distribution expansion plans as standardized 2026 XLSX measure spreadsheets and 2024/2026 PDFs.","coverage_note":"Of 814 DSOs in the GraphQL directory, 95 have an active plan service ('nap'). Example XLSX downloads contained 1,205 measure rows at Bayernwerk Netz, 15,097 at Westnetz and 18,094 at Netze BW.","data_date":"2026-10-31","caveats":["No geographic coordinates are published (substation/line names or anonymized regional labels only; grid maps are static images in PDFs without existing-grid topology).","Exempts DSOs under 100,000 customers unless renewable curtailment exceeded 3% (§ 14d Abs. 8 EnWG); XLSX dates are Excel serial numbers and include completed/cancelled rows."],"coverage":{"geographic":"Germany nationwide across 6 statutory planning regions (Nord, Ost, West, Mitte, Südwest, Bayern), covering 95 activated DSOs out of 814 listed electricity DSOs"},"fine_print":{"unit":{"value":"One row per planned, ongoing, completed or cancelled distribution grid measure (line or substation) in each DSO's 'Maßnahmenplan' XLSX (e.g. 1,205 rows in Bayernwerk Netz, 15,097 in Westnetz, 18,094 in Netze BW; >33,000 nationwide).","quote":"Alle Maßnahmen die innerhalb der nächsten 5 Jahre (NS-MS) bzw. 10 Jahre (Umspannung HS/MS und HS) aus Sicht der Netzplanung begonnen werden müssten.","url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4ccdf23b8e2304a3440a7","attempts":[]},"inclusion_rule":{"value":"Mandatory under § 14d Abs. 1 & 8 EnWG for electricity DSOs with >= 100,000 directly or indirectly connected customers, or smaller DSOs that curtailed >3% of onshore wind/solar generation in each of the two preceding years.","quote":"Die Absätze 1 bis 4 sowie 6 und 7 sind nicht anzuwenden auf Betreiber von Elektrizitätsverteilernetzen, an deren Elektrizitätsverteilernetz weniger als 100 000 Kunden unmittelbar oder mittelbar angeschlossen sind.","url":"https://www.gesetze-im-internet.de/enwg_2005/__14d.html","attempts":[]},"reference_date":{"value":"Second-round NAP 2026 consultation drafts ('Entwurfsfassung' / 'DRAFT') published 2026-10-31 to 2026-11-02 alongside finalized 2024 plans ('FINAL').","quote":"Die Veröffentlichung auf der Internetseite „VNBdigital“ (https://vnbdigital.de) der deutschen Verteilnetzbetreiber erfolgte am 31. Oktober 2026.","url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4cc8c23b8e2304a344064","attempts":[]},"update_frequency":{"value":"Every two years by 31 October under § 14d Abs. 1 EnWG (initial cycle 2024; regular statutory cycle starting 31 October 2026, with post-consultation final versions).","quote":"Betreiber von Elektrizitätsverteilernetzen haben der Regulierungsbehörde alle zwei Jahre jeweils zum 31. Oktober eines Kalenderjahres, beginnend mit dem Jahr 2026, einen Plan für ihr jeweiliges Elektrizitätsverteilernetz (Netzausbauplan) vorzulegen.","url":"https://www.gesetze-im-internet.de/enwg_2005/__14d.html","attempts":[]},"exclusions":{"value":"Excludes ~719 smaller municipal/local DSOs (<100,000 customers and <=3% curtailment), omits geographic coordinates in the standardized VNBdigital Maßnahmenplan XLSX schema across tested operators, and omits existing-grid topology in PDF maps for critical-infrastructure protection.","quote":"Auf die Darstellung des Bestandnetzes wurde zum Schutz der kritischen Infrastruktur bewusst verzichtet.","url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4cc8c23b8e2304a344064","attempts":[]}},"key_fields":[{"field":"Maßnahme / kurze Projektbeschreibung","meaning":"Asset name and technical scope (e.g. 'UW Kleinschwabhausen - Neubau Umspannwerk', 'Leitung Lüdinghausen-Abzw. Lippe'; anonymized as 'HS-Maßnahme'/'NAP Maßnahme' by some DSOs)."},{"field":"Projektkategorie / Betriebsmittel [Zuordnungscodes]","meaning":"Category ('Neubau', 'Netzoptimierung und -verstärkung', 'Ersatz(neubau) mit Erhöhung der Übertragungskapazität') and asset codes (201 UW HöS/HS, 301 HS line, 401 UW HS/MS, 501 MS line, 601 UW MS/NS, 701 NS line)."},{"field":"Vorrangig betroffene Netz- oder Umspannebene","meaning":"Grid voltage tier: 'UW HöS auf HS', 'HS' (typically 110 kV), 'UW HS auf MS', 'MS', 'UW MS auf NS', or 'NS'."},{"field":"voraussichtlicher Zeitpunkt der Inbetriebnahme [MM/JJJJ]","meaning":"Expected commissioning month/year (accompanied by optimal completion date [12/JJJJ] and expected construction start [MM/JJJJ])."},{"field":"Projektstatus / Stand Genehmigungsverfahren","meaning":"Project state ('vorgesehene Maßnahme', 'konkrete Planung', 'im Bau', 'abgeschlossen', 'weggefallene Maßnahme') and permitting status."}],"how_to_use":{"example_request":"curl -sL -X POST 'https://www.vnbdigital.de/gateway/graphql' -H 'Content-Type: application/json' -d '{\"query\":\"query { vnb_gridExpansionDocumentsExternal(vnbId: \\\"1068\\\") { uploadDate url metadata { filename version } } }\"}'","example_result":"{\"data\":{\"vnb_gridExpansionDocumentsExternal\":[{\"uploadDate\":1793379551492,\"url\":\"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4ccdf23b8e2304a3440a7\",\"metadata\":{\"filename\":\"Netzausbauplan_Massnahmen_1068_2026_Entwurf.xlsx\",\"version\":\"DRAFT\"}}]}}","steps":["POST to https://www.vnbdigital.de/gateway/graphql with query { vnb_vnbs { _id name services { activated type { type } } } } (do NOT request voltageTypes, which throws a server nullability error) and filter services where type.type=='nap' and activated==true (95 DSOs).","For each vnbId, query vnb_gridExpansionDocumentsExternal(vnbId) to obtain direct GET URLs (https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=...) for 2026 'Maßnahmenplan' XLSX and PDF files.","In each 'Maßnahmenplan' sheet, read headers on row 2 or row 3 (varies by 1 row across operators; Westnetz also inserts an extra 'Kosten (geschätzt) in Euro' column S, shifting later columns by one).","Filter Projektkategorie and Projektstatus (exclude 'abgeschlossen', 'weggefallene Maßnahme', and pure 1:1 replacement 'Ersatz(neubau) ohne Erhöhung der Übertragungskapazität') and convert Excel date serials (epoch 1899-12-30) to YYYY-MM."],"reading_traps":["Do NOT include 'voltageTypes' in GraphQL vnb_vnbs queries: the gateway fails with 'Cannot return null for non-nullable field vnb_VNB.voltageTypes'.","No DSO spreadsheet contains geographic coordinates, and naming precision varies sharply: Bayernwerk and Westnetz name concrete substations/municipalities ('UW Kleinschwabhausen'), whereas Netze BW anonymizes all 18,094 rows to 'HS-Maßnahme' or 'NAP Maßnahme' with Teilnetzgebiet='Netze BW'.","Date columns store raw Excel serial numbers in XML (e.g. 46357 = 2026-12-01, 49644 = 2035-12-01, plus occasional typos like 72502 = year 2098 in Netze BW row 4).","Row counts include already completed ('abgeschlossen'), cancelled ('weggefallene Maßnahme') and pure 1:1 replacement rows alongside new build ('Neubau') and upgrades."]},"test":{"tested_on":"2026-11-25","method":"api_query","http_status":200,"content_type":"application/json; charset=utf-8","size_bytes":43868,"records_total":814,"records_for_country":814,"problems":[]},"evidence":[{"claim":"§ 14e EnWG mandates a joint internet platform operated by electricity DSOs, implemented at vnbdigital.de.","url":"https://www.gesetze-im-internet.de/enwg_2005/__14e.html","quote":"Betreiber von Elektrizitätsverteilernetzen sind verpflichtet, ab dem 1. Januar 2023 zu den in den folgenden Absätzen genannten Zwecken eine gemeinsame Internetplattform einzurichten und zu betreiben."},{"claim":"Bayernwerk's 2026 Maßnahmenplan XLSX lists concrete 110 kV line and HS/MS substation new-build rows under CC BY 4.0.","url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4ccdf23b8e2304a3440a7","quote":"UW Kleinschwabhausen - Neubau Umspannwerk | UW Oberbachern | Errichtung eines neuen Umspannwerkes und 110-kV-Anbindung über zwei 110-kV-Kabel an das UW Oberbachern"}],"members":[{"name":"Bayernwerk Netz GmbH","landing_url":"https://www.vnbdigital.de/vnb/1068","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4ccdf23b8e2304a3440a7","access":"direct_download","tested":true,"data_found":true,"note":"Downloaded 2026 Maßnahmenplan XLSX (192,184 B, 1,205 measure rows, CC BY 4.0) and PDF (16,975,347 B, CC BY-ND 4.0); names concrete substations and 110 kV lines."},{"name":"Westnetz GmbH","landing_url":"https://www.vnbdigital.de/vnb/7332","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae5a21f23b8e2304a344295","access":"direct_download","tested":true,"data_found":true,"note":"Downloaded 2026 Maßnahmenplan XLSX (1,512,160 B, 15,097 measure rows); names concrete 110 kV lines and stations ('Leitung Lüdinghausen-Abzw. Lippe', 'Station Hemsen') and includes extra estimated-cost column S."},{"name":"Netze BW GmbH","landing_url":"https://www.vnbdigital.de/vnb/7214","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae86281977b74434075c509","access":"direct_download","tested":true,"data_found":true,"note":"Downloaded 2026 Maßnahmenplan XLSX (2,249,656 B, 18,094 measure rows: 44 UW HöS/HS, 498 HS, 339 UW HS/MS, 5,093 MS, 2,026 UW MS/NS, 6,201 NS, 3,893 blank); anonymizes Maßnahme to 'HS-Maßnahme'/'NAP Maßnahme'."},{"name":"Avacon Netz GmbH","landing_url":"https://www.vnbdigital.de/vnb/7137","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae880e8d65f39cfe55146b2","access":"direct_download","tested":true,"data_found":true,"note":"Verified via GraphQL: publishes NAP_Massnahmen_10010461_2026_Entwurf.xlsx, NAP_kompakt_10010461_2026_Entwurf.xlsx and 2024/2026 PDFs."},{"name":"EWE NETZ GmbH","landing_url":"https://www.vnbdigital.de/vnb/496","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae885bed65f39cfe55146d9","access":"direct_download","tested":true,"data_found":true,"note":"Verified via GraphQL: publishes Netzausbauplan_EWE_NETZ_2026_Massnahmenplan.xlsx, Datenblatt XLSX, 2026 draft PDF and 2024 final PDF."},{"name":"Stromnetz Berlin GmbH","landing_url":"https://www.vnbdigital.de/vnb/80","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6afefea2ec6b90b9525c3c04","access":"direct_download","tested":true,"data_found":true,"note":"Verified via GraphQL: publishes 2026-11-02_Anlage_Massnahmeplan_Stromnetz_Berlin.xlsx, Datenblatt XLSX and 2024/2026 PDFs."},{"name":"E.DIS Netz GmbH","landing_url":"https://www.vnbdigital.de/vnb/1000","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4739123b8e2304a343e83","access":"direct_download","tested":true,"data_found":true,"note":"Verified via GraphQL: publishes NAP2026_1000_Massnahmenplan.xlsx, kompakt XLSX and 2024/2026 PDFs."},{"name":"LEW Verteilnetz GmbH","landing_url":"https://www.vnbdigital.de/vnb/27","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae4a3a323b8e2304a343fe1","access":"direct_download","tested":true,"data_found":true,"note":"Verified via GraphQL: publishes NAP_Massnahmen_27_2026_Entwurf.xlsx, kompakt XLSX and 2024/2026 PDFs."},{"name":"Mitteldeutsche Netzgesellschaft Strom mbH","landing_url":"https://www.vnbdigital.de/vnb/1081","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae5bebb23b8e2304a3442d7","access":"direct_download","tested":true,"data_found":true,"note":"Verified via GraphQL (MITNETZ STROM): publishes NAP_Massnahmen_1081_2026_Entwurf.xlsx, kompakt XLSX and 2026 PDF."},{"name":"Schleswig-Holstein Netz GmbH","landing_url":"https://www.vnbdigital.de/vnb/535","data_url":"https://www.vnbdigital.de/gateway/files?serviceName=vnb&fileId=6ae5c44e23b8e2304a3442f8","access":"direct_download","tested":true,"data_found":true,"note":"Verified via GraphQL: publishes Netzausbauplan_Massnahmen_535_2026_Entwurf.xlsx, kompakt XLSX and 2026 PDF."}],"members_summary":{"total":95,"listed":10,"tested":10,"data_found":10,"scope_note":"95 of 814 listed electricity DSOs have an active Netzausbauplan ('nap') service on VNBdigital. Ten major regional or urban DSOs across all six planning regions were tested directly. The active count does not establish that every operator made an XLSX file available.","pattern":"Query vnb_gridExpansionDocumentsExternal(vnbId) on https://www.vnbdigital.de/gateway/graphql or open https://www.vnbdigital.de/vnb/<vnbId> to download NAP_<id>_2026_Entwurf.pdf and NAP_Massnahmen_<id>_2026_Entwurf.xlsx."},"member_scope":{"total":95,"note":"95 of 814 listed electricity DSOs have an active Netzausbauplan ('nap') service on VNBdigital. Ten major regional or urban DSOs across all six planning regions were tested directly. The active count does not establish that every operator made an XLSX file available.","pattern":"Query vnb_gridExpansionDocumentsExternal(vnbId) on https://www.vnbdigital.de/gateway/graphql or open https://www.vnbdigital.de/vnb/<vnbId> to download NAP_<id>_2026_Entwurf.pdf and NAP_Massnahmen_<id>_2026_Entwurf.xlsx."}},{"source_id":"nep-strom","name":"Netzentwicklungsplan Strom (NEP 2037/2045) — Digitale Projektbibliothek, Projektsteckbriefe & Punktmaßnahmen","publisher":"50Hertz Transmission GmbH, Amprion GmbH, TenneT TSO GmbH, TransnetBW GmbH","official":true,"landing_url":"https://www.netzentwicklungsplan.de/projektbibliothek","data_url":"https://www.netzentwicklungsplan.de/sites/default/files/2026-03/NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf","access":"pdf","format":"PDF reports/Steckbriefe + paginated HTML Digitale Projektbibliothek (static PNG maps; no GIS or XLSX measure list)","license":"All rights reserved (prior written consent of the TSOs required per Impressum)","language":"de","has_coordinates":false,"location_precision":"municipality","publisher_type":"operator","adds":"Covers pre-statutory candidate transmission projects (Zubaunetz to 2045), expected commissioning windows per measure, archived plan editions since 2012, and 871 substation/transformer/switchgear point measures (Punktmaßnahmen) absent from BNetzA GIS.","first_seen_pass":1,"rank":3,"summary":"Joint TSO statutory transmission plan (§ 12b EnWG) publishing candidate and confirmed projects through 2037/2045 as PDF Steckbriefe and a 40-page substation Punktmaßnahmen report.","coverage_note":"871 unique substation/transformer/switchgear M-code point measures in the downloaded Punktmaßnahmen PDF, plus 272 onshore and offshore transmission projects in the NEP 2037/2045 (2025) 2nd Draft Digitale Projektbibliothek (and archived editions 2012–2023).","data_date":"2026-08-11","caveats":["Published as PDFs and HTML pages with static PNG maps only (no CSV/XLSX measure list or GIS routes); copyright reserved by the 4 TSOs.","Punktmaßnahmen substation tables give scenario flags (Startnetz vs 2037/2045) rather than exact commissioning dates or coordinates."],"coverage":{"geographic":"Germany nationwide (onshore 220/380 kV AC and HVDC transmission plus offshore grid connection systems in North and Baltic Seas)"},"fine_print":{"unit":{"value":"272 transmission projects (composed of individual line/station Maßnahmen M...) in the NEP 2037/2045 (2025) 2nd Draft Digitale Projektbibliothek, plus 871 unique M-code point measures in the 40-page Punktmaßnahmen companion PDF.","quote":"Neben Leitungsbaumaßnahmen sind im Netzentwicklungsplan Strom (NEP) auch Punktmaßnahmen für ein bedarfsgerechtes Stromnetz erforderlich.","url":"https://www.netzentwicklungsplan.de/sites/default/files/2026-03/NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf","attempts":[]},"inclusion_rule":{"value":"All effective measures for demand-driven optimization, reinforcement and expansion of the German transmission network required through 2037/2045 under § 12b EnWG (both already confirmed Startnetz and proposed Zubaunetz).","quote":"Der gemeinsame nationale Netzentwicklungsplan muss alle wirksamen Maßnahmen zur bedarfsgerechten Optimierung, Verstärkung und zum Ausbau des Netzes enthalten","url":"https://www.gesetze-im-internet.de/enwg_2005/__12b.html","attempts":[]},"reference_date":{"value":"NEP 2037/2045 Version 2025, 2nd Draft (Punktmaßnahmen PDF published 2026-03-16; Sonderveröffentlichung Steckbriefe 2026-05-19; combined Steckbriefe PDF 2026-08-11), following BNetzA confirmation of NEP 2037/2045 (2023) in March 2024.","quote":"Begleitdokument zum Netzentwicklungsplan Strom 2037 mit Ausblick 2045, Version 2025, zweiter Entwurf","url":"https://www.netzentwicklungsplan.de/sites/default/files/2026-03/NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf","attempts":[]},"update_frequency":{"value":"Biennial statutory cycle (1st draft, 2nd draft, BNetzA confirmation under §§ 12b–12c EnWG); next cycle NEP 2040/2045 (2027) scenario framework already initiated.","quote":"Die Betreiber von Übertragungsnetzen mit Regelzonenverantwortung legen der Regulierungsbehörde auf der Grundlage des Szenariorahmens einen gemeinsamen nationalen Netzentwicklungsplan zur Bestätigung vor.","url":"https://www.gesetze-im-internet.de/enwg_2005/__12b.html","attempts":[]},"exclusions":{"value":"Excludes distribution grids (<=110 kV except vertical 380/110-kV or 220/110-kV coupling transformers and 110-kV switchgear bays at transmission nodes); provides static PNG/PDF schematic maps rather than route coordinates.","quote":"Vertikale Punktmaßnahmen stellen eine Verbindung zwischen Übertragungs- (380 kV, 220 kV) und Verteilnetz (110 kV) her.","url":"https://www.netzentwicklungsplan.de/sites/default/files/2026-03/NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf","attempts":[]}},"key_fields":[{"field":"Projektnummer / BBP-Nr / Maßnahmennummer","meaning":"NEP project code (e.g. 'TTG-P53', 'DC43', '50HzT-P364'), corresponding BBPlG statutory number ('BBP-Nr: 41'), and measure ID ('M54', 'M30TR_b', 'M748SA')."},{"field":"Basisdaten (Startnetz / Zubaunetz, Onshore / Offshore, AC / DC)","meaning":"Distinguishes already confirmed baseline projects ('Startnetz') from scenario-dependent new proposals ('Zubaunetz' across scenarios A/B/C 2037 and 2045)."},{"field":"Art der Maßnahme / Ausführung","meaning":"Classifies 'Leitung' vs 'Anlage' (reactive compensation/booster) or Punktmaßnahme ('380-kV-AC-Schaltanlage', '380/110-kV-Transformator', '380-kV-Einschleifung', 'Kundenanschluss')."},{"field":"Geplante Inbetriebnahme","meaning":"Planned commissioning year or multi-year window per measure in Projektsteckbriefe (e.g. '2029 - 2032', '2032 - 2034', '2045')."}],"how_to_use":{"example_request":"curl -sL 'https://www.netzentwicklungsplan.de/sites/default/files/2026-03/NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf' -o /tmp/nep_punkt.pdf && pdftotext -layout -f 4 -l 4 /tmp/nep_punkt.pdf - | head -n 20","example_result":"Tabelle 1: Übersicht über die Punktmaßnahmen im Startnetz des NEP 2037/2045 (2025)\n50HzT-P215  M748SA   Gnewitz: 380-kV-AC-Schaltanlage\n50HzT-P364  M30TR_b  Malchow: 380/110-kV-Transformator (1x)","steps":["Browse or scrape https://www.netzentwicklungsplan.de/projektbibliothek?page=0 through ?page=27 (272 projects) or download the combined 41.9 MB Projektsteckbriefe PDF from /nep-aktuell/netzentwicklungsplan-20372045-2025.","Extract line measures, voltage, km, 'BBP-Nr' and 'Geplante Inbetriebnahme' from individual Projektsteckbriefe PDFs with pdftotext -layout.","Download NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf (40 pages) to obtain Tabelle 1 (Startnetz) and Tabelle 2 (Zubaunetz with A/B/C 2037 & 2045 scenario flags) covering 871 substation, switchgear, transformer and customer-connection point measures."],"reading_traps":["Horizontal point measures confirmed under § 12c EnWG (e.g. STATCOM, MSCDN, compensators) sit in Projektsteckbriefe, whereas vertical 380/110-kV transformers, switchgear bays and loop-ins not subject to § 12c confirmation sit only in the separate Punktmaßnahmen PDF.","Maps in the Digitale Projektbibliothek are static raster PNGs (/sites/default/files/project_library/maps/.../*.png), not downloadable GeoJSON.","Tabelle 1 in Punktmaßnahmen uses a two-column side-by-side page layout (pages 4–27); parse left and right column blocks separately when running pdftotext -layout.","Some Zubaunetz projects (e.g. DC43, DC44) carry an explicit economic-optimum caveat ('negatives Kosten-Nutzen-Verhältnis') and are not yet confirmed by BNetzA."]},"test":{"tested_on":"2026-11-25","method":"download","http_status":200,"content_type":"application/pdf","size_bytes":290164,"records_total":871,"records_for_country":871,"problems":[]},"evidence":[{"claim":"Unconfirmed vertical/horizontal substation, transformer and switchgear measures are published in the companion Punktmaßnahmen document rather than main NEP Steckbriefe.","url":"https://www.netzentwicklungsplan.de/sites/default/files/2026-03/NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf","quote":"Da die Bundesnetzagentur vertikale Punktmaßnahmen und zum Teil horizontale Punktmaßnahmen (Transformatoren, Schaltanlagen, Einschleifungen und Kundenanschlüsse) jedoch nicht nach § 12c EnWG bestätigt, sind diese im NEP 2037/2045 (2025) nicht als eigenständige Maßnahmen enthalten. ... Daher veröffentlichen die Übertragungsnetzbetreiber diese Maßnahmen dennoch in diesem Begleitdokument."},{"claim":"Individual NEP Projektsteckbrief TTG-P53 (BBP-Nr 41) documents both a 380 kV replacement line (M54, commissioning 2032–2034) and new 380 kV switchgear/380-110 kV transformers.","url":"https://www.netzentwicklungsplan.de/projektbibliothek/download/58082/TTG-P53%20Netzverst%C3%A4rkung%20und%20-ausbau%20zwischen%20Raitersaich_West%20und%20Altheim.pdf","quote":"M54 Raitersaich/West - Suchraum Ludersheim/West ... Geplante Inbetriebnahme: 2032 - 2034 ... Hierzu ist eine 380-kV-Schaltanlage mit anfänglich zwei und langfristig vier 380/110-kV-Transformatoren in Suchraum Ludersheim/West (Suchraum Gemeinden Altdorf bei Nürnberg/ Winkelhaid) an Stelle der bestehenden 220-kV-Schaltanlage neu zu errichten (Netzausbau)."}],"members":[],"members_summary":null},{"source_id":"bsh-flaechenentwicklungsplan","name":"Flächenentwicklungsplan für deutsche Seegebiete (FEP 2025) — GeoSeaPortal GeoJSON, GPKG & WFS","publisher":"Bundesamt für Seeschifffahrt und Hydrographie (BSH)","official":true,"landing_url":"https://www.geoportal.de/?search=6156b1d2-c44c-421c-9855-b2e77e4b21e5","data_url":"https://gdi.bsh.de/data/SpatialData/Main/Site_Development_Plan/Site_Development_Plan_2025.json","access":"direct_download","format":"GeoJSON, GeoPackage (.gpkg) and OGC WFS 2.0.0 / WMS","license":"GeoNutzV — Nutzungsbestimmungen für die Bereitstellung von Geodaten des Bundes (Quelle: © BSH 2025)","language":"en, de","has_coordinates":true,"location_precision":"exact","publisher_type":"national_government","adds":"Provides open GIS polygons and WFS 2.0.0 vectors for 17 planned offshore converter platforms, 3 transformer platforms, 36 subsea cable/interconnector corridors and 28 crossing gates in Germany's EEZ.","first_seen_pass":1,"rank":4,"summary":"Federal maritime spatial plan (FEP 2025) serving open GeoJSON, GeoPackage and WFS 2.0.0 geometries for planned offshore grid infrastructure in Germany's EEZ.","coverage_note":"153 spatial features in Germany's EEZ across 9 layers, including 17 offshore converter platform buffers, 3 transformer platform buffers, 36 subsea export/interconnector cable corridors and 28 gates (plus 25 areas, 30 sites, 7 centerlines, 6 zones, 1 other energy area).","data_date":"2025-01-30","caveats":["Covers offshore EEZ designations only (1:400,000 scale) and omits voltage and commissioning year fields (join by name_fep with NEP Offshore sheets).","Root JSON file nests 9 separate FeatureCollections by layer key rather than a single top-level features array."],"coverage":{"geographic":"German Exclusive Economic Zone (EEZ / AWZ) of the North Sea and Baltic Sea (3.35–14.75° E, 53.52–55.92° N)"},"fine_print":{"unit":{"value":"153 spatial designation features across 9 layers in Site_Development_Plan_2025.json, including 17 converter_buffer polygons, 3 transformer_buffer polygons, 36 subseacable_buffer corridors and 28 gate lines.","quote":"Der Datensatz enthält den veröffentlichten Stand der räumlichen Festlegungen des Flächenentwicklungsplans als zusätzliches Informationsangebot. Der Planungsmaßstab des Plans beträgt 1:400.000.","url":"https://gdi.bsh.de/mapservice_gs/Site_Development_Plan_2025/wfs?request=GetCapabilities&service=WFS","attempts":[]},"inclusion_rule":{"value":"Spatial designations of the statutory Site Development Plan (Flächenentwicklungsplan — FEP 2025) for offshore wind areas, converter/transformer platforms, subsea grid connection cables and interconnectors.","quote":"Flächenentwicklungsplan für deutsche Seegebiete 2025 - WFS","url":"https://gdi.bsh.de/mapservice_gs/Site_Development_Plan_2025/wfs?request=GetCapabilities&service=WFS","attempts":[]},"reference_date":{"value":"Published 2025-01-30 ('publishing': '20250130' in all feature properties).","quote":"\"publishing\": \"20250130\"","url":"https://gdi.bsh.de/data/SpatialData/Main/Site_Development_Plan/Site_Development_Plan_2025.json","attempts":[]},"update_frequency":{"value":"Statutory periodic plan revisions (FEP editions published in 2019, 2020, 2023 and 2025 on GovData/GDI-BSH).","quote":"designation in a previous SDP with update","url":"https://gdi.bsh.de/data/SpatialData/Main/Site_Development_Plan/Site_Development_Plan_2025.json","attempts":[]},"exclusions":{"value":"Covers the offshore EEZ only (coastal territorial-sea and onshore landfall routes belong to state spatial planning / BBPlG); GIS attributes omit voltage and expected commissioning year.","quote":"Maßgeblich sind die bekanntgegebenen Dokumente.","url":"https://gdi.bsh.de/mapservice_gs/Site_Development_Plan_2025/wfs?request=GetCapabilities&service=WFS","attempts":[]}},"key_fields":[{"field":"name_fep","meaning":"Official FEP designation code of the converter platform, cable system or gate (e.g. 'NOR-3-2', 'I-OST-9', 'N-III')."},{"field":"type / designation_type","meaning":"Infrastructure class ('Converter Platform', 'Transformer Platform', 'Interconnector' or export cable) and legal designation state ('designated')."},{"field":"status / information_designation_and_updates","meaning":"Planning state ('planned' on area/site layers) and provenance across FEP editions ('publishing': '20250130')."}],"how_to_use":{"example_request":"curl -sL 'https://gdi.bsh.de/mapservice_gs/Site_Development_Plan_2025/wfs?service=WFS&version=2.0.0&request=GetFeature&typeNames=Site_Development_Plan_2025:Converter_Buffer&count=1&srsName=EPSG:4326&outputFormat=application/json'","example_result":"{\"type\":\"FeatureCollection\",\"features\":[{\"id\":\"Converter_Buffer.9166da05-70c4-4b9a-b76f-1fdce9cda326\",\"geometry\":{\"type\":\"Polygon\",\"coordinates\":[[[6.80651243,54.04218511],[6.80661498,54.04083873]]]},\"properties\":{\"name_fep\":\"NOR-3-2\",\"type\":\"Converter Platform\",\"publishing\":\"20250130\"}}]}","steps":["Download the complete multi-layer JSON file (Site_Development_Plan_2025.json, 3.16 MB) or GeoPackage, or query individual layers via WFS 2.0.0 with srsName=EPSG:4326&outputFormat=application/json.","When parsing Site_Development_Plan_2025.json, iterate over the top-level dictionary keys ('converter_buffer', 'transformer_buffer', 'subseacable_buffer', 'gate') — each key holds its own GeoJSON FeatureCollection.","Cross-reference name_fep (e.g. 'NOR-3-2') with NEP Offshore Projektsteckbriefe or the FEP 2025 report text to attach DC voltage (typically 320 or 525 kV) and target commissioning year."],"reading_traps":["Site_Development_Plan_2025.json is NOT a single FeatureCollection: its root JSON object has 9 named keys, each containing a FeatureCollection (reading root['features'] returns nothing).","Bare root URL https://gdi.bsh.de/ returns HTTP 403 Forbidden; access the direct data/WFS endpoints or Geoportal.de metadata record.","Geometries represent buffer zones at 1:400,000 planning scale rather than exact engineering footprints, and omit voltage and commissioning year attributes."]},"test":{"tested_on":"2026-11-25","method":"download","http_status":200,"content_type":"application/json","size_bytes":3159758,"records_total":153,"records_for_country":153,"problems":[]},"evidence":[{"claim":"BSH WFS GetCapabilities authorizes reuse under Federal GeoNutzV with attribution '© BSH 2025' at 1:400,000 planning scale.","url":"https://gdi.bsh.de/mapservice_gs/Site_Development_Plan_2025/wfs?request=GetCapabilities&service=WFS","quote":"Dieser Datensatz kann gemäß der \"Nutzungsbestimmungen für die Bereitstellung von Geodaten des Bundes\" (http://www.gesetze-im-internet.de/geonutzv/GeoNutzV.pdf) genutzt werden."}],"members":[],"members_summary":null},{"source_id":"osm-overpass-planned-grid","name":"OpenStreetMap (Overpass API) — Planned and Under-Construction Power Lines & Substations","publisher":"OpenStreetMap Contributors","official":false,"landing_url":"https://overpass-turbo.eu/","data_url":"https://maps.mail.ru/osm/tools/overpass/api/interpreter","access":"api","format":"Overpass JSON / XML","license":"Open Database License (ODbL 1.0)","language":"de, en","has_coordinates":true,"location_precision":"exact","publisher_type":"community","adds":"Openly licensed (ODbL) exact coordinates for both extra-high-voltage and 110 kV lines, cables and substations currently under construction or proposed in Germany.","first_seen_pass":1,"rank":5,"summary":"Crowd-sourced ODbL vector dataset via Overpass API mapping under-construction and proposed power lines, cables and substations with exact coordinates.","coverage_note":"436 OSM elements in Germany (401 construction=line, 21 construction=cable, 7 construction=substation, 4 proposed=line, 2 proposed=cable, 1 proposed=substation); individual ways represent segments/busbars rather than whole projects.","data_date":"2026-11-25","caveats":["Captures mainly active construction sites (only 7 proposed elements and 8 substations nationwide) and lacks commissioning dates on 432 of 436 elements.","Voltages are in Volts ('220000' = 220 kV); overpass-api.de returned HTTP 406 to bare CLI clients, so use the maps.mail.ru Overpass mirror or set Accept headers."],"coverage":{"geographic":"Germany nationwide (crowd-sourced, concentrated on active construction sites)"},"fine_print":{"unit":{"value":"Individual OSM nodes, ways and relations (436 elements in Germany: 401 construction=line, 21 construction=cable, 7 construction=substation, 4 proposed=line, 2 proposed=cable, 1 proposed=substation); a single line project may be split into dozens of ways/busbars.","quote":null,"url":null,"attempts":[{"url":"https://maps.mail.ru/osm/tools/overpass/api/interpreter","note":"Counted live from Overpass response (436 OSM elements across DE admin_level=2); OSM elements represent mapped geometry segments rather than administrative projects."},{"url":"https://overpass-turbo.eu/","note":"Checked Overpass Turbo frontend; unit semantics follow standard OSM power=construction / power=proposed tagging."}]},"inclusion_rule":{"value":"Voluntarily mapped power infrastructure tagged power=proposed or power=construction with proposed/construction in (line, cable, minor_line, substation, converter).","quote":null,"url":null,"attempts":[{"url":"https://maps.mail.ru/osm/tools/overpass/api/interpreter","note":"Verified empirically via Overpass tag filter across ISO3166-1=DE."},{"url":"https://overpass-turbo.eu/","note":"No statutory inclusion rule applies to crowd-sourced OSM mapping."}]},"reference_date":{"value":"Live OpenStreetMap database queried on 2026-11-25.","quote":null,"url":null,"attempts":[{"url":"https://maps.mail.ru/osm/tools/overpass/api/interpreter","note":"Returned live OSM snapshot on 2026-11-25 (138,044 bytes)."},{"url":"https://overpass-turbo.eu/","note":"Overpass serves near-real-time OSM diffs."}]},"update_frequency":{"value":"Continuous crowd-sourced edits.","quote":null,"url":null,"attempts":[{"url":"https://maps.mail.ru/osm/tools/overpass/api/interpreter","note":"Continuous minutely/hourly OSM replication."},{"url":"https://overpass-turbo.eu/","note":"Verified continuous community update model."}]},"exclusions":{"value":"Severely under-represents pre-construction planned lines and substations (only 7 proposed elements and 8 substations total across Germany) and omits commissioning dates on 432 of 436 elements.","quote":null,"url":null,"attempts":[{"url":"https://maps.mail.ru/osm/tools/overpass/api/interpreter","note":"Verified by auditing all 436 returned DE elements: 429 construction vs 7 proposed; 406 carry voltage; only 4 carry start_date/opening_date/check_date."},{"url":"https://overpass-api.de/api/interpreter","note":"Main overpass-api.de nginx returned HTTP 406 to default CLI requests without Accept/UA negotiation, while maps.mail.ru mirror succeeded with HTTP 200."}]}},"key_fields":[{"field":"power + proposed / construction","meaning":"Lifecycle prefix ('proposed' vs 'construction') and asset type ('line', 'cable', 'substation', 'converter')."},{"field":"voltage","meaning":"Nominal voltage in Volts (e.g. '380000', '220000', '110000'; semicolon-delimited for multi-voltage lines), populated on 406 of 436 DE elements."},{"field":"operator / name / ref / start_date","meaning":"TSO/DSO name, line/substation name or code, and expected completion date (present on only 4 of 436 DE elements)."}],"how_to_use":{"example_request":"curl -sL --data-urlencode 'data=[out:json][timeout:60];area[\"ISO3166-1\"=\"DE\"][admin_level=2]->.de;(nwr[\"power\"=\"proposed\"][\"proposed\"~\"^(line|cable|minor_line|substation|converter)$\"](area.de);nwr[\"power\"=\"construction\"][\"construction\"~\"^(line|cable|minor_line|substation|converter)$\"](area.de););out tags center;' 'https://maps.mail.ru/osm/tools/overpass/api/interpreter'","example_result":"{\"elements\":[{\"type\":\"way\",\"id\":160711985,\"center\":{\"lat\":52.8588048,\"lon\":8.0813431},\"tags\":{\"cables\":\"3\",\"construction\":\"line\",\"power\":\"construction\",\"voltage\":\"220000\"}}]}","steps":["POST the Overpass QL query to https://maps.mail.ru/osm/tools/overpass/api/interpreter (note: overpass-api.de returned HTTP 406 Not Acceptable to default bare curl/urllib requests).","Divide numeric voltage values by 1,000 to convert Volts to kV and split semicolon-separated multi-voltage strings (e.g. '380000;110000').","Exclude substation internal busbars (tags.line=='busbar') if counting inter-substation transmission/distribution circuits."],"reading_traps":["OSM stores voltage in Volts ('220000' = 220 kV), not kV.","Many construction=line ways represent short substation busbars (line=busbar) or individual span segments rather than whole projects.","Coverage is heavily skewed toward visible physical construction (429 construction vs 7 proposed; only 8 substations total) and 99% lack planned commissioning dates."]},"test":{"tested_on":"2026-11-25","method":"api_query","http_status":200,"content_type":"application/json","size_bytes":138044,"records_total":436,"records_for_country":436,"problems":["Primary instance https://overpass-api.de/api/interpreter returned HTTP 406 Not Acceptable to default CLI headers; public mirror https://maps.mail.ru/osm/tools/overpass/api/interpreter served HTTP 200."]},"evidence":[{"claim":"Overpass returns 436 proposed or under-construction power line, cable and substation elements in Germany.","url":"https://maps.mail.ru/osm/tools/overpass/api/interpreter","quote":"\"tags\": {\"cables\": \"3\", \"construction\": \"line\", \"power\": \"construction\", \"voltage\": \"220000\"}"}],"members":[],"members_summary":null},{"source_id":"entsoe-tyndp","name":"ENTSO-E Ten-Year Network Development Plan (TYNDP 2026) — Public Projects JSON API","publisher":"European Network of Transmission System Operators for Electricity (ENTSO-E)","official":true,"landing_url":"https://tyndp2026.entsoe.eu/projects-map","data_url":"https://tyndp2026.entsoe.eu/api/Public/Projects/Transmission","access":"api","format":"REST JSON API (with embedded GeoJSON strings)","license":"ENTSO-E public transparency mode (no open license stated)","language":"en","has_coordinates":true,"location_precision":"exact","publisher_type":"supranational","adds":"Single European JSON API combining GeoJSON schematic/corridor lines, target commissioning year, permitting status and cross-border investment links for 38 German transmission projects.","first_seen_pass":1,"rank":6,"summary":"Official ENTSO-E TYNDP 2026 REST JSON endpoint providing GeoJSON routes, commissioning years and status for 38 German transmission projects.","coverage_note":"199 European transmission projects total, of which 38 involve Germany (8 internal corridors, 30 cross-border interconnectors).","data_date":"2026-11-13","caveats":["Covers only major corridors/interconnectors; structured voltageLevelKv is null in preliminary 2026 JSON (read description), and investments[].geometry swaps latitude/longitude keys."],"coverage":{"geographic":"Pan-European ENTSO-E grid, including 38 projects in Germany (8 internal German corridors and 30 cross-border interconnectors)"},"fine_print":{"unit":{"value":"199 European transmission projects (38 with country isoCode 'DE'), each expandable via /api/Public/Projects/Transmission/{id} into constituent investment items.","quote":"\"title\": \"TYNDP 2026 Project Collection\"","url":"https://tyndp2026.entsoe.eu/projects-map","attempts":[]},"inclusion_rule":{"value":"Transmission projects of European/cross-border significance submitted by TSOs for the ENTSO-E TYNDP 2026 portfolio.","quote":"pciSubmissionWindowStart: \"2026-09-14T09:00:00\", pciSubmissionWindowEnd: \"2026-11-13T23:59:59\"","url":"https://tyndp2026.entsoe.eu/projects-map","attempts":[]},"reference_date":{"value":"Preliminary TYNDP 2026 project collection following the Autumn 2026 submission window ('isPreliminary: true', 'pciSubmissionWindowEnd: 2026-11-13T23:59:59').","quote":"isPreliminary: true","url":"https://tyndp2026.entsoe.eu/projects-map","attempts":[]},"update_frequency":{"value":"Biennial European TYNDP cycle (TYNDP 2012 through TYNDP 2026).","quote":"The TYNDP tested how 141 transmission and 23 storage projects respond to the 2030 and 2040 scenarios.","url":"https://tyndp.entsoe.eu/","attempts":[]},"exclusions":{"value":"Covers only major cross-border interconnectors and flagship internal corridors (38 DE projects vs 272 in Germany's national NEP); in the preliminary 2026 JSON, structured investment fields voltageLevelKv and substationFrom/To are null (written in description text), while the TYNDP 2024 portal (tyndp2024.entsoe.eu) now redirects to Microsoft OAuth login.","quote":"\"voltageLevelKv\": null","url":"https://tyndp2026.entsoe.eu/api/Public/Projects/Transmission/47","attempts":[]}},"key_fields":[{"field":"id / name / countries","meaning":"TYNDP project ID, title and array of country objects ({'isoCode': 'DE', 'name': 'Germany'})."},{"field":"commissioningYear / statusName","meaning":"Promoter expected commissioning year (or MM-YYYY in investments) and status ('Under Consideration', 'Planned But Not Yet Permitting', 'In Permitting', 'Under Construction')."},{"field":"geoJson / description","meaning":"Serialized RFC 7946 GeoJSON FeatureCollection string for the project corridor and prose description specifying kV and substations."}],"how_to_use":{"example_request":"curl -sL 'https://tyndp2026.entsoe.eu/api/Public/Projects/Transmission'","example_result":"[{\"id\":47,\"name\":\"Westtirol (AT) - Vöhringen (DE)\",\"commissioningYear\":\"2030\",\"statusName\":\"Planned But Not Yet Permitting\",\"countries\":[{\"isoCode\":\"AT\",\"name\":\"Austria\"},{\"isoCode\":\"DE\",\"name\":\"Germany\"}]}]","steps":["GET https://tyndp2026.entsoe.eu/api/Public/Projects/Transmission and filter items where any c['isoCode']=='DE' in countries (38 projects).","Parse each project's stringified geoJson field with json.loads() for standard [lon, lat] route coordinates.","Fetch https://tyndp2026.entsoe.eu/api/Public/Projects/Transmission/{id} for investment-level commissioning months ('12-2030'), CAPEX and prose voltage/substation details."],"reading_traps":["CRITICAL COORDINATE TRAP: inside /api/Public/Projects/Transmission/{id}, investments[].geometry.coordinates[] swaps field names — 'latitude' holds longitude (e.g. 10.6898° E) and 'longitude' holds latitude (e.g. 47.5411° N)! Use the top-level project geoJson string ([lon, lat]) instead.","In the preliminary TYNDP 2026 API, investments[].voltageLevelKv, substationFrom and substationTo are null; parse kV from description (or consult the archived TYNDP 2024 export in Open-TYNDP).","https://tyndp2024.entsoe.eu/ now redirects to Microsoft Entra login (login.microsoftonline.com), whereas https://tyndp2026.entsoe.eu/api/Public/Projects/Transmission is open without login."]},"test":{"tested_on":"2026-11-25","method":"api_query","http_status":200,"content_type":"application/json; charset=utf-8","size_bytes":281246,"records_total":199,"records_for_country":38,"problems":["Prior-cycle portal https://tyndp2024.entsoe.eu/ redirects to Microsoft login; preliminary 2026 API leaves structured voltageLevelKv null and swaps latitude/longitude labels inside investments[].geometry."]},"evidence":[{"claim":"TYNDP 2026 public JSON API serves 38 German projects with commissioningYear, statusName and embedded GeoJSON.","url":"https://tyndp2026.entsoe.eu/api/Public/Projects/Transmission","quote":"\"id\": 47, \"name\": \"Westtirol (AT) - Vöhringen (DE)\", ... \"commissioningYear\": \"2030\", ... \"statusName\": \"Planned But Not Yet Permitting\""}],"members":[],"members_summary":null}],"sector":{"regulator":{"name":"Bundesnetzagentur für Elektrizität, Gas, Telekommunikation, Post und Eisenbahnen (BNetzA)","url":"https://www.bundesnetzagentur.de/DE/Home/home_node.html"},"operators":{"structure":"many","note":"Four transmission system operators with control-area responsibility (50Hertz Transmission, Amprion, TenneT TSO, TransnetBW) operate the 220/380 kV AC and HVDC grid. VNBdigital lists 814 electricity DSOs, including 95 with an active plan service.","census_url":"https://www.vnbdigital.de/"},"publication_obligation":{"exists":"yes","norm":"§§ 12b, 12c, 14d, 14e EnWG; BBPlG; EnLAG; § 17d EnWG / WindSeeG","url":"https://www.gesetze-im-internet.de/enwg_2005/__14d.html","what_must_be_published":"4 TSOs must submit a joint national Netzentwicklungsplan Strom (all effective optimization, reinforcement and expansion measures) for BNetzA confirmation (§§ 12b–12c EnWG); BSH publishes the offshore Flächenentwicklungsplan; DSOs >=100,000 customers (or >3% curtailment) must submit and publish Netzausbaupläne covering 5-year, 10-year and 2045 horizons with HV/MV grid maps, congestion regions, planned measures, permitting status and expected timeline on a joint platform (§§ 14d–14e EnWG).","frequency":"Every 2 years for NEP Strom (§ 12b EnWG) and every 2 years by 31 October for DSO Netzausbaupläne (§ 14d Abs. 1 EnWG); quarterly BNetzA BBPlG/EnLAG progress monitoring."},"consolidated_republication":{"found":"partial","note":"BNetzA consolidates transmission BBPlG/EnLAG line sections on netzausbau.de, the four TSOs list NEP measures on netzentwicklungsplan.de and BSH publishes offshore designations on gdi.bsh.de. VNBdigital links to distribution plans by operator and lists 95 active plan services.","checked_pages":[{"organization":"Bundesnetzagentur (Netzausbau / DANA)","url":"https://www.netzausbau.de/Daten/DANA/de.html","saw":"Confirmed BNetzA collects TSO and permitting-authority transmission data in DANA (login-restricted at dana.netzausbau.de) and republishes BBPlG/EnLAG maps and quarterly Monitoringberichte, excluding distribution grids."},{"organization":"Bundesnetzagentur (SMARD)","url":"https://www.smard.de/home","saw":"Confirmed SMARD provides market time series and editorial summaries on grid expansion, not a downloadable project/substation inventory."},{"organization":"VNB digital GmbH (Gemeinsame Internetplattform nach § 14e EnWG)","url":"https://www.vnbdigital.de/","saw":"Verified GraphQL catalog of 814 DSOs (95 with active NAP service) serving per-operator 2024 PDFs and 2026 XLSX/PDF files without a merged national file or coordinates."},{"organization":"Bundesministerium für Wirtschaft und Energie (BMWE/BMWK)","url":"https://www.bundeswirtschaftsministerium.de/Redaktion/DE/Dossier/netze-und-netzausbau.html","saw":"Ministry policy dossier refers to BNetzA's netzausbau.de, NEP and BBPlG; hosts no separate consolidated GIS or distribution dataset."}]}},"national_registry":{"exists":"partial","note":"No single national registry covers planned lines and substations across transmission and distribution. Transmission is split between BNetzA's netzausbau.de, the TSOs' NEP project library and BSH's offshore FEP 2025. VNBdigital lists 95 active distribution plan services and provides links by operator.","checked_pages":[{"organization":"Bundesnetzagentur (Netzausbau Monitoring & DANA)","url":"https://www.netzausbau.de/Daten/monitoring/de.html","saw":"Found quarterly BBPlG/EnLAG monitoring PDFs (2013–2026) and interactive ArcGIS FeatureServer map for statutory transmission lines only."},{"organization":"4 German TSOs (Netzentwicklungsplan Strom)","url":"https://www.netzentwicklungsplan.de/projektbibliothek","saw":"Found 272 transmission projects in the NEP 2037/2045 (2025) Digitale Projektbibliothek and companion Punktmaßnahmen PDF, without GIS exports or distribution assets."},{"organization":"VNB digital GmbH","url":"https://www.vnbdigital.de/","saw":"Found the central § 14e EnWG portal, with 95 active plan services and individual PDF/XLSX examples. There is no merged national table or GIS layer."},{"organization":"GovData — Das Datenportal für Deutschland","url":"https://www.govdata.de/ckan/api/3/action/package_search?q=Netzausbau%20Strom&rows=5","saw":"CKAN search returned 34 BSH Flächenentwicklungsplan records, 0 records for Netzentwicklungsplan or Bundesbedarfsplan, and no national planned grid inventory."},{"organization":"Bundesnetzagentur (Marktstammdatenregister — MaStR)","url":"https://www.marktstammdatenregister.de/MaStR","saw":"Registers generation, storage and grid operators, not individual planned power lines or transformer substations."}]},"if_unstructured":{"summary":"To obtain planned onshore substations (missing from BNetzA GIS), exact commissioning windows for transmission sections, or 110 kV line/substation locations missing from VNBdigital XLSX tables, extract NEP Steckbriefe and Punktmaßnahmen PDFs, netzausbau.de project sheets, DSO Netzausbauplan PDFs, and state permitting dossiers on UVP-Verbund.","recipe":["Start with BNetzA Monitoring_gdb (transmission lines) and VNBdigital 2026 Maßnahmenplan XLSX files (distribution lines and substations) to build the structured backbone.","Attach missing transmission commissioning years and HVDC converter status by fetching https://www.netzausbau.de/Vorhaben/ansicht/de.html?nummer=<N>&gruppe=bbplg (table 'Steckbrief' -> 'Gesamtinbetriebnahme' and section accordions) and matching 'BBP-Nr' against NEP 2037/2045 Projektsteckbriefe ('Geplante Inbetriebnahme').","Extract all 871 planned transmission substation, switchgear and 380/110-kV transformer upgrades from NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf (pages 4–40) with pdftotext -layout, splitting the two side-by-side column blocks in Tabelle 1 (Startnetz, pp. 4–27) and reading single-width scenario rows in Tabelle 2 (Zubaunetz, pp. 28–40).","For 110 kV lines and HS/MS substations listed without coordinates in VNBdigital XLSX tables, inspect Anhang 1/2 schematic Netzkarten in the DSO's NAP 2026 PDF (e.g. Bayernwerk Netz GmbH pp. 7–8) and search uvp-verbund.de or state Planfeststellungsbehörden portals once 'Stand Genehmigungsverfahren' enters 'im Verfahren'."],"location_method":"Existing substations upgraded in NEP Punktmaßnahmen or VNBdigital tables (e.g. 'UW Oberbachern', 'Gnewitz', 'Malchow') can be matched by substation name against OpenStreetMap power=substation polygons or BNetzA Vorhabenpunkte; greenfield substations ('Suchraum Ludersheim/West', 'UW Kleinschwabhausen') and 110 kV routes only gain exact parcel/route plans in Planfeststellung application packages published on netzausbau.de, uvp-verbund.de, or state authority portals.","cross_with":["BNetzA Vorhabenpunkte FeatureServer (205 transmission grid connection nodes) and OpenStreetMap power=substation / power=line (existing 110–380 kV topology)","UVP-Verbund (uvp-verbund.de) and Bezirksregierungen / Regierungspräsidien / Landesämter Planfeststellung portals for 110 kV and Landesbehörden-led 380 kV alignments","NEP Offshore Projektsteckbriefe to attach voltage (320/525 kV DC) and commissioning year to BSH FEP 2025 converter_buffer and subseacable_buffer polygons"],"where_published":[{"name":"Netzentwicklungsplan Strom — Digitale Projektbibliothek & Punktmaßnahmen PDFs","url":"https://www.netzentwicklungsplan.de/nep-aktuell/netzentwicklungsplan-20372045-2025","what":"Individual transmission project PDFs (Projektsteckbriefe) and the 40-page Punktmaßnahmen PDF detailing all 871 planned substation switchgear, 380/110-kV transformer and loop-in measures.","how_to_search_inside":"Filter /projektbibliothek by Bundesland, 'Leitung' vs 'Anlage', 'Startnetz' vs 'Zubaunetz', or search project/substation names in NEP_2037_2045_V2025_2E_inkl-SB_Projektsteckbriefe_0.pdf and NEP_2037_2045_V2025_2_Entwurf_Punktmassnahmen.pdf.","example_document":{"url":"https://www.netzentwicklungsplan.de/projektbibliothek/download/58082/TTG-P53%20Netzverst%C3%A4rkung%20und%20-ausbau%20zwischen%20Raitersaich_West%20und%20Altheim.pdf","what_it_gives":"Pages 1–3 give BBP-Nr ('41'), Startnetz Onshore AC status, line measure 'M54 Raitersaich/West - Suchraum Ludersheim/West' ('45 km', '380-kV-Doppelleitung', 'Geplante Inbetriebnahme: 2032 - 2034') AND embedded new substation '380-kV-Schaltanlage mit anfänglich zwei und langfristig vier 380/110-kV-Transformatoren in Suchraum Ludersheim/West (Suchraum Gemeinden Altdorf bei Nürnberg/ Winkelhaid)' plus replacement '380-kV-Schaltanlage Raitersaich/West'."}},{"name":"BNetzA Netzausbau — Vorhaben-Steckbriefe & Quartals-Monitoringbericht","url":"https://www.netzausbau.de/Vorhaben/uebersicht/liste/liste.html","what":"135 statutory BBPlG/EnLAG/offshore HTML project sheets with project-level commissioning year ('Gesamtinbetriebnahme'), section-by-section permitting dates, and HVDC converter sections, plus the 190.6 MB quarterly Monitoringbericht PDF.","how_to_search_inside":"Browse Vorhaben/uebersicht/liste/liste.html by BBPlG/EnLAG number or follow the {Link} attribute from Monitoring_gdb features to Vorhaben/ansicht/de.html?nummer=<N>&gruppe=bbplg.","example_document":{"url":"https://www.netzausbau.de/Vorhaben/ansicht/de.html?nummer=5&gruppe=bbplg","what_it_gives":"Top Steckbrief table gives 'Wolmirstedt – Isar (SuedOstLink)', '50Hertz TenneT', 'Gleichstrom (2 GW) | 525 kV', 'Länge 543 km', 'Gesamtinbetriebnahme geplant für 2027', 'Stand: 5. November 2026', and dedicated converter permitting section 'Konverterbereich Isar (Abschnitt D3b) | 2 km | Bayern | TenneT' ('Bau seit Q4 2023')."}},{"name":"UVP-Verbund (Joint EIA & Planfeststellung Portal of the 16 Länder) & VNBdigital DSO PDFs","url":"https://www.uvp-verbund.de/freitextsuche?rstart=0&currentSelectorPage=1&q=110-kV","what":"State-level Planfeststellung and EIA notices/dossiers for 110 kV distribution lines and substations (with affected municipalities, route maps and parcel schedules), complementing the schematic Anhang 1/2 Netzkarten inside VNBdigital DSO PDF reports.","how_to_search_inside":"Query uvp-verbund.de full-text search with '110-kV' or 'Umspannwerk' and filter by Zulassungsverfahren / Bundesland; cross-match the DSO and line/UW name against the DSO's VNBdigital Maßnahmenplan.","example_document":{"url":"https://www.uvp-verbund.de/trefferanzeige?docuuid=0682c3aa-1285-4541-8087-0a3b679e175a","what_it_gives":"Dossier '110-kV-Ersatzneubau Perleberg-Wittstock' ('Zuletzt geändert 12.03.2026'): applicant 'E.DIS Netz GmbH', authority 'Landesamt für Bergbau, Geologie und Rohstoffe (LBGR)', scope '110-kV-Freileitung Perleberg-Wittstock (HT-1130) mit einer Gesamtlänge von 43,73 km' plus branches 'Pritzwalk (HT-1131)' (0.8 km) and 'Falkenhagen (HT-1132)' (6.38 km) across 'Perleberg, Pritzwalk und Wittstock (Dosse) sowie der Gemeinden Groß Pankow und Heiligengrabe'."}}]},"related_not_answering":[{"name":"gridAhead (Reiner Lemoine Institute & Goal100)","url":"https://github.com/gridAhead/gridAhead","why":"Community open-source initiative launched November 2026 to extract and geocode VNBdigital § 14d EnWG DSO plans, but its public repository currently publishes only the 'nap-tool' extraction code ('We currently publish only the pipelines, not data') with 0 public dataset releases on GitHub or Zenodo."},{"name":"Marktstammdatenregister (MaStR)","url":"https://www.marktstammdatenregister.de/MaStR","why":"Official federal register of electricity/gas generation units, storage systems, large consumers and market actors (including grid operator master data), but it does not list planned power lines or substations."},{"name":"SMARD — Strommarktdaten der Bundesnetzagentur","url":"https://www.smard.de/home","why":"Publishes generation, load, market and congestion/redispatch time series plus articles summarizing grid expansion progress, without project-level lists of planned lines or substations."}],"open_questions":["When will BNetzA publish a consolidated evaluation or machine-readable national dataset of the 2026 § 14d EnWG distribution Netzausbaupläne, and will it require uniform measure naming (preventing full anonymization such as Netze BW's 'HS-Maßnahme' rows) or coordinates in the 2028 cycle?","When will gridAhead (RLI & Goal100) resolve licensing clearance on DSO spreadsheets/maps to release its geocoded 2024/2026 distribution expansion dataset publicly?"],"history":[{"pass":1,"date":"2026-11-26","role":"research","model":"Gemini 4 Carbon","rules_version":"2026-11-25-de-red-y-tramitacion","note":"Initial research in session f843b96e-b516-44f8-8831-ee71816fec53: tested BNetzA Monitoring_gdb GIS, VNBdigital GraphQL & 2026 DSO XLSX plans, NEP 2037/2045 PDFs, BSH FEP 2025 WFS/GeoJSON, ENTSO-E TYNDP 2026 API and OSM.","headline":{"official_data":"partial","non_official_data":"partial","national_registry":"partial"},"sources":{"total":6,"new":6,"dropped":0},"negatives":{"overturned":0,"confirmed":0},"effort":{"pages":64,"minutes":28}},{"pass":2,"date":"2026-11-26","role":"revision","model":"GPT-6 (Codex)","note":"Editorial review: distinguished active VNBdigital plan services from inspected XLSX samples.","headline":{},"sources":{},"negatives":{},"effort":{}}],"local_terms":[{"term":"Netzentwicklungsplan Strom (NEP)","language":"de","meaning":"Biennial joint transmission grid development plan (§ 12b EnWG) drafted by Germany's 4 TSOs and confirmed by BNetzA."},{"term":"Netzausbauplan (§ 14d EnWG)","language":"de","meaning":"Biennial distribution grid expansion plan published by larger electricity DSOs on VNBdigital."},{"term":"Bundesbedarfsplangesetz (BBPlG)","language":"de","meaning":"Federal statute enacting priority transmission expansion projects monitored by BNetzA on netzausbau.de."},{"term":"Punktmaßnahmen","language":"de","meaning":"NEP companion category for planned substation switchgear bays, 380/110-kV transformers, loop-ins and reactive compensation."},{"term":"Bundesfachplanung / Trassenkorridor","language":"de","meaning":"Federal corridor planning stage under NABEG determining a 500–1,000 m route corridor ('Korridorverlauf') prior to exact route approval."},{"term":"Planfeststellungsbeschluss","language":"de","meaning":"Final route/site approval decision fixing the binding alignment ('Trassenverlauf') and authorizing construction."},{"term":"Umspannwerk (UW) / Konverter","language":"de","meaning":"AC transformer substation ('UW') and HVDC AC/DC converter station ('Konverter' / 'Konverterplattform')."},{"term":"Flächenentwicklungsplan (FEP)","language":"de","meaning":"BSH federal maritime spatial plan designating offshore converter platforms and subsea export cable corridors in Germany's EEZ."}],"provenance":{"pass_count":2,"models":["Gemini 4 Carbon","GPT-6 (Codex)"],"minutes_estimate":null,"pages_opened":null,"passes":[{"pass":1,"date":"2026-11-26","model":"Gemini 4 Carbon"},{"pass":2,"date":"2026-11-26","model":"GPT-6 (Codex)"}],"note":"Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed."},"card_url":"https://georutter.org/v1/de/grid-expansion-plans.json","detail_url":"https://georutter.org/v1/de/grid-expansion-plans/detail.json","html_url":"https://georutter.org/de/grid-expansion-plans/","country_url":"https://georutter.org/v1/countries/de.json"}