{"schema_version":"1.0","country":"de","country_name":"Germany","topic":"grid-hosting-capacity","question":"Where can I get the available grid connection capacity per substation or node in Germany, for generation and for demand, with the latest value and its history?","territory":"de","territory_level":"country","parent_url":null,"published_on":"2026-11-26","research_reviewed_on":"2026-11-26","access_checked_on":"2026-11-26","answer":{"official_data":"partial","non_official_data":"partial","summary":"Germany has no unified official substation hosting-capacity dataset across its 4 TSOs and ~865 electricity DSOs (inferred by subtracting 4 TSOs from 869 active Stromnetzbetreiber in BNetzA's MaStR). At TSO level, 50Hertz exposes a JSON API for 75 substations with available, reserved and requested MW for generation and demand (and an undocumented-unit constructionCostContribution field); TransnetBW embeds 52 substations in HTML with MW bands; Amprion and TenneT list 10 substations each without available MW. At DSO level, Geoportal Saarland maps renewable feed-in MW for 6 DSOs and E.ON DSOs publish qualitative maps (HTTP 403). Only paid aggregator GridChecker (844 sites) keeps history.","main_caveats":["No single national official portal exists: publication is split across 4 TSOs and ~865 electricity DSOs, and VNBdigital (814 DSOs) only hosts territories, Netzausbaupläne and portal links.","Since 1 April 2026 all 4 TSOs allocate large load and battery connections via cyclic Reifegradverfahren (first-ready, first-served); published MW values are non-binding maximum indications.","Only 50Hertz (exact MW) and TransnetBW (MW bands for 2032/2035) publish node-level generation and demand MW at TSO level; Amprion and TenneT publish bay/site availability without MW.","Saarland Geoportal and Netze BW's Mittelspannungsauskunft cover generation feed-in only; urban DSO Repartition/Fair-Grid notices (Hamburg, Düsseldorf, Berlin) give only grid-wide MVA totals.","50Hertz's JSON API sets available*CapacityMw to null (not 0) on 60/75 unavailable nodes and duplicates Eulenberg (EUB) and Eulenberg (EUB) Neubau with identical 1,800/2,000 MW values.","Official portals overwrite snapshots in place with no history; TenneT and E.ON DSO portals (Bayernwerk, E.DIS, SH Netz, Westnetz) block non-browser HTTP clients via Cloudflare HTTP 403."],"confidence":"high","confidence_reason":"All 4 TSOs, BNetzA, SMARD, VNBdigital (814 DSOs), EnWG/BMWE's 2026 Netzanschlusspaket bill, Capacitypedia, Saarland Geoportal, 18 major DSOs and GridChecker were directly inspected.","attributes":[{"attribute":"node","covered":"partial","source_ids":["de-uenb-netzanschlusskapazitaet","de-saarland-geoportal-umspannanlagen","de-vnb-netzanschlusskapazitaet","gridchecker-de"],"note":"50Hertz (75 EHV nodes), TransnetBW (52), Amprion (10), TenneT (10) and ~25 DSOs publish substation entries; 8 of 18 directly tested DSOs publish none or only grid-wide totals.","gap":"not_checked","gap_note":"Among tested operators, 8 of 18 DSOs publish no per-substation capacity (BMWE's August 2026 § 17c EnWG-E bill remains in parliament; VNBdigital's 814 DSO profiles expose only territories, Netzausbaupläne and portal links), Amprion and TenneT omit unavailable substations from their tables, TenneT and 7 regional DSO portals return HTTP 403, GridChecker's full 844-site table is paid, and ~841 smaller DSOs were not individually opened."},{"attribute":"generation_capacity","covered":"partial","source_ids":["de-uenb-netzanschlusskapazitaet","de-saarland-geoportal-umspannanlagen","de-vnb-netzanschlusskapazitaet","gridchecker-de"],"note":"50Hertz gives exact firm MW per EHV node (13/75 >0 MW); TransnetBW gives MW bands (2032/2035); Saarland Geoportal gives HV/MV renewable MW; Netze BW/N-ERGIE check <=10 MW.","gap":"not_checked","gap_note":"Among tested operators, Amprion and TenneT publish no numerical generation MW per substation, E.ON regional DSO maps (Bayernwerk, E.DIS, SH Netz) use qualitative classes behind Cloudflare HTTP 403, tested urban/regional DSOs (8 of 18) publish only network-wide MVA or none, GridChecker's consolidated export is paid, and ~841 smaller electricity DSOs were not individually checked."},{"attribute":"demand_capacity","covered":"partial","source_ids":["de-uenb-netzanschlusskapazitaet","de-vnb-netzanschlusskapazitaet","gridchecker-de"],"note":"50Hertz gives availableLoadCapacityMw (15/75 >0 MW) and TransnetBW gives load MW bands; N-ERGIE Netz offers single-site LV/MV pre-checks <=10 MW; GridChecker tracks 844 sites.","gap":"not_checked","gap_note":"Amprion and TenneT publish qualitative bay/site availability without numerical demand MW; Geoportal Saarland and Netze BW's Mittelspannungsauskunft cover generation feed-in only; tested urban DSOs (Hamburger Energienetze 0 MVA, Düsseldorf 0 MVA, ENERVIE ~100 MVA, Stromnetz Berlin suspended) publish only grid-wide totals; 7 regional DSO portals returned HTTP 403, GridChecker is paid, and ~841 smaller DSOs were not individually checked."},{"attribute":"latest_data","covered":"partial","source_ids":["de-uenb-netzanschlusskapazitaet","de-saarland-geoportal-umspannanlagen","de-vnb-netzanschlusskapazitaet","gridchecker-de"],"note":"Latest snapshots: 50Hertz knowledge 2026-03-31 (API updatedAt 2026-05-18), TransnetBW 2026-04-01 (map 05/2026), Amprion 04/2026, Saarland WMS 2026-11-24, GridChecker 2026-11-25.","gap":"not_checked","gap_note":"Among tested sources, current node-level generation and demand MW exist only at 50Hertz and TransnetBW (with 6–8 month assessment lag), Saarland (feed-in only), single-site MV pre-check tools, and paid GridChecker; Westnetz's 110 kV grid-group PDF dates from 2022-07-01, 7 DSO portals returned HTTP 403, 8 tested DSOs publish no node snapshot, and ~841 smaller DSOs were not individually checked."},{"attribute":"historical_series","covered":"partial","source_ids":["gridchecker-de"],"note":"No tested official German TSO or DSO portal archives past hosting-capacity snapshots; commercial aggregator GridChecker archives daily snapshots for 29 operators since Oct 2024.","gap":"not_checked","gap_note":"All tested official TSO and DSO portals overwrite their current map or PDF snapshot in place without historical archives. GridChecker retains versioned daily snapshots since October 2024 (e.g. 22 snapshots for TenneT DE since 2026-06-09, 1 for Bayernwerk since 2026-11-16), but requires a paid commercial plan and covers 29 operators; 7 regional DSO portals returned HTTP 403 and ~841 smaller DSOs were not individually checked."},{"attribute":"update_frequency","covered":"partial","source_ids":["de-uenb-netzanschlusskapazitaet","de-saarland-geoportal-umspannanlagen","de-vnb-netzanschlusskapazitaet","gridchecker-de"],"note":"50Hertz and TransnetBW update ad hoc/cyclically; TenneT every ~10 months; Netze BW weekly; urban DSO Repartition portals annually; GridChecker polls daily at 05:15 UTC.","gap":"not_checked","gap_note":"Although Art. 50(4a) of Regulation (EU) 2019/943 requires monthly TSO updates and Art. 31(3) of Directive (EU) 2019/944 requires at least quarterly DSO updates (transposed as monthly in pending § 17c(1) EnWG-E), tested German operators mostly state ad-hoc or 10-to-12-month cycle updates (Saarland WMS states no schedule), 7 DSO portals returned HTTP 403, and ~841 smaller DSOs were not individually checked."}]},"sources":[{"source_id":"de-uenb-netzanschlusskapazitaet","name":"Netzanschlusskarten und Umspannwerk-Kapazitätsübersichten der vier deutschen Übertragungsnetzbetreiber (50Hertz, TransnetBW, Amprion, TenneT)","publisher":"50Hertz Transmission GmbH, TransnetBW GmbH, Amprion GmbH, TenneT TSO GmbH","official":true,"landing_url":null,"data_url":null,"access":"api","format":"JSON (50Hertz API), HTML/SVG (TransnetBW), PDF (Amprion), Web viewer/table (TenneT)","license":"Proprietary informational publication (no legal entitlement; standard statutory copyright)","language":"de","has_coordinates":true,"location_precision":"exact","publisher_type":"operator","adds":"Primary official substation-level connection availability across all four German extra-high-voltage (220/380 kV) transmission control zones, including exact generation and demand MW via 50Hertz's JSON API and MW bands via TransnetBW's HTML map.","first_seen_pass":1,"rank":1,"summary":"Official substation connection capacity publications of all 4 German 220/380 kV TSOs: 50Hertz exposes a 75-substation JSON API with exact generation and demand MW, TransnetBW embeds 52 substations in HTML with MW classes, Amprion provides a 10-substation PDF table without MW, and TenneT's 10-site page is gated by Cloudflare.","coverage_note":"Test record count (75) represents EHV substations in 50Hertz's JSON API (3 coordinate pairs overlap). Across all 4 TSOs, TransnetBW adds 52 EHV substations, Amprion lists 10 available substations, and TenneT lists 10 future sites.","data_date":"2026-03-31 to 2026-05-18 (by TSO)","caveats":["50Hertz sets available*CapacityMw to null on 60/75 unavailable nodes and duplicates Eulenberg (EUB) and Eulenberg (EUB) Neubau.","TransnetBW values apply only from 2032/2035 and hide 37 red unavailable substations via JS; Amprion and TenneT omit numerical MW.","TenneT's webpage returns HTTP 403 to non-browser clients; no TSO provides historical snapshots."],"coverage":{"geographic":"All 4 German transmission control zones (national 220/380 kV extra-high-voltage grid): 75 substations in 50Hertz, 52 in TransnetBW, 10 available substations in Amprion's table (plus red sites on map), and 10 available substations in TenneT Germany."},"fine_print":{"unit":{"value":"MW (explicit in 50Hertz *Mw JSON fields and TransnetBW bands: 0 MW, < 500 MW, 500–1,000 MW, 1,000–1,500 MW, 1,500–2,000 MW); integer bay count in 50Hertz availableSwitchgearBay and (n-0)/(n-1) bay class in Amprion; 50Hertz constructionCostContribution (40, 60, 100) has no unit declared in the JSON.","quote":"Verfügbare Einspeisekapazität: 1.000 – 1.500 MW Verfügbare Lastkapazität: 1.000 – 1.500 MW","url":"https://www.transnetbw.de/de/transparenz/netzzugang-und-entgelt/netzanschlusskarte","attempts":[]},"inclusion_rule":{"value":"Extra-high-voltage (380 kV and 220 kV) substations evaluated for firm connection capacity considering existing connected units, reservations, switchgear bay availability/expandability, and the 3 GW busbar criterion; Amprion's table and TenneT's map/table list only substations with potential future availability.","quote":"Die Bewertung basiert auf vorhandenen beziehungsweise konkret geplanten Schaltfeldern und neu geplanten Umspannwerken unter Berücksichtigung der Netzauslastung und weiterer technischer Restriktionen.","url":"https://www.transnetbw.de/de/transparenz/netzzugang-und-entgelt/netzanschlusskarte","attempts":[]},"reference_date":{"value":"50Hertz: 2026-03-31 state of knowledge (JSON locations updatedAt up to 2026-05-18); TransnetBW: 2026-04-01 assessment (map Stand 05/2026, horizons 2032 and 2035); Amprion: April 2026 (horizons 2032–2035); TenneT: horizons 2030–2036.","quote":"Die auf der Netzkarte dargestellten Netzanschlusspunkte basieren auf der zum 31.03.2026 bestmöglichen Einschätzung und Kenntnislage von 50Hertz.","url":"https://www.50hertz.com/de/Vertragspartner/Netzkunden/Netzanschluss","attempts":[]},"update_frequency":{"value":"Cyclic / ad hoc aligned with TSO Reifegradverfahren cycles (50Hertz: continuous/when needed; TransnetBW: cyclic; Amprion: static April 2026 edition; TenneT: every ~10 months per Capacitypedia).","quote":"Die Karte wird zyklisch aktualisiert. Neu verfügbare Netzanschlusspunkte, die sich im Rahmen des Netzausbaus ergeben, werden rechtzeitig in der Karte veröffentlicht.","url":"https://www.transnetbw.de/de/transparenz/netzzugang-und-entgelt/netzanschlusskarte","attempts":[]},"exclusions":{"value":"110 kV and medium/low-voltage distribution substations are excluded; line tap connections outside substations require individual assessment; TransnetBW's UI hides 37 red (unavailable) substations by default via JavaScript; Amprion and TenneT do not publish numerical MW.","quote":"Anfragen abseits von bestehenden bzw. ausgewiesenen Umspannwerken sollen grundsätzlich nicht im Rahmen des Reifegradverfahrens gestellt werden.","url":"https://www.netztransparenz.de/Portals/1/Dokumente/Reifegradverfahren/Vier%20U%CC%88NB%20-%20Reifegradverfahren%20-%20FAQ%20V1.5.pdf?ver=8oUeGfRo0ubY7M88NU-jDg%3D%3D","attempts":[]}},"key_fields":[{"field":"locations[].name / coordinate.x, coordinate.y","meaning":"50Hertz substation name (with short code, e.g. 'Altentreptow Süd (ATS)') and WGS84 longitude (x) and latitude (y) as strings."},{"field":"locations[].availableGenerationCapacityMw / availableLoadCapacityMw","meaning":"50Hertz maximum indicative available generation (feed-in) and demand (load) connection capacity in MW (null when unavailable)."},{"field":"locations[].reservedGenerationCapacityMw / reservedLoadCapacityMw","meaning":"50Hertz already reserved generation and load connection capacity in MW per substation."},{"field":"locations[].requestedGenerationCapacityMw / requestedLoadCapacityMw","meaning":"50Hertz pending requested generation and load connection capacity in MW per substation."},{"field":"locations[].availableSwitchgearBay / voltageLevel / localDistributionSystemOperator","meaning":"50Hertz count of available switchgear bays, EHV voltage ('380', '220', '380/220'), and downstream regional DSO name."},{"field":".tooltip (TransnetBW HTML) / Schaltanlage, Anschlussauslegung, Inbetriebnahmejahr (Amprion PDF)","meaning":"TransnetBW substation status (green 2032, yellow 2035, red unavailable), n-0/n-1 class and MW bands; Amprion 380 kV substation, municipality, bay class and earliest commissioning year."}],"how_to_use":{"example_request":"curl -sSL \"https://www.50hertz.com/DesktopModules/Lotes/FrequentModules/API/DigitalMap/GetDnbInfo?path=GridLoadMapVersion/map/type/gridcapacity\"","example_result":"{\"id\":\"1b58832e-bd03-48fe-b71f-08de8b31ead3\",\"locations\":[{\"name\":\"Altentreptow Süd (ATS)\",\"coordinate\":{\"x\":\"13.174416\",\"y\":\"53.62405\"},\"voltageLevel\":\"380\",\"availableSwitchgearBay\":1,\"availableLoadCapacityMw\":1300.0,\"availableGenerationCapacityMw\":650.0,\"reservedLoadCapacityMw\":250.0,\"reservedGenerationCapacityMw\":850.0,\"requestedLoadCapacityMw\":5193.0,\"requestedGenerationCapacityMw\":5193.0}]}","steps":["50Hertz (75 EHV substations): GET the GetDnbInfo JSON endpoint above and iterate over data['locations']; parse float(coordinate['x']) as WGS84 longitude and float(coordinate['y']) as latitude.","TransnetBW (52 EHV substations): GET https://www.transnetbw.de/de/transparenz/netzzugang-und-entgelt/netzanschlusskarte and parse all HTML elements matching div.tooltip; extract the colour class (tooltip-uw-type--green, --yellow, --red) and text lines for Spannungsebene, Inbetriebnahme Netzanschluss, Anschlussart, Verfügbare Einspeisekapazität and Verfügbare Lastkapazität.","Amprion (10 available 380 kV substations): Download https://www.amprion.net/Dokumente/Strommarkt/Netzkunden/Netzanschlussregeln/07_Darstellung-der-Kundenprojekte-sowie-der-Schaltfeldverfuegbarkeit/Ergaenzendes-Dokument-zu-potenziellen-Netzanschlussmoeglichkeiten-04.2026.pdf and run pdftotext -layout to parse the 10-row table (Schaltanlage, Spannungsebene, Stadt/Gemeinde, Anschlussauslegung, Voraussichtlich frühestes Inbetriebnahmejahr, Anmerkungen).","TenneT Germany (10 future sites): Open https://www.tennet.eu/de/strommarkt/kunden-deutschland/netzanschlussanfragen in an interactive browser (plain HTTP clients receive Cloudflare HTTP 403) to view the map and table for 2030–2036."],"reading_traps":["In 50Hertz's JSON, availableGenerationCapacityMw and availableLoadCapacityMw are null (not 0.0) for 60 of 75 substations; only 15 substations have non-null values (13 > 0 MW and 2 equal to 0.0 MW for generation; 15 > 0 MW for load).","50Hertz's 75 rows include three same-coordinate pairs: ('Eulenberg (EUB)', 'Eulenberg (EUB) Neubau'), ('Güstrow (GUE)', 'Güstrow (GUES)') and ('Bärwalde (BAE)', 'Bärwalde (BAE) Schaltanlage'). Both Eulenberg rows report 1,800 MW available generation and 2,000 MW available load, so summing across rows without deduplicating double-counts Eulenberg.","50Hertz's Hohenwarte II (HOH2) Schaltanlage reports availableSwitchgearBay: 0 alongside 2,040 MW available generation and load (updatedAt: null), whereas Graustein (GRS) reports 5 available bays, 1,900 MW load and 0 MW generation.","50Hertz's JSON includes constructionCostContribution (values 40.0, 60.0, 100.0) with no unit in the schema (likely % Baukostenzuschuss tier).","TransnetBW's script (commented 'Update 2026/05: Hide all red UW from the map by default!') hides 37 red ('nicht verfügbar') substations in the browser, leaving only 9 green and 6 yellow markers visible unless you parse the underlying HTML .tooltip nodes; TransnetBW values apply only to future commissioning from 2032 (green) or 2035 (yellow), and Mannheim Süd explicitly notes '(keine BESS!)'.","Amprion's supplementary PDF lists only the 10 green substations ('Anschluss voraussichtlich realisierbar') without MW values; Clusorth and Meppen allow load connections only ('Es sind ausschließlich Lastanschlüsse möglich'), while Herringhausen, Kötz and Rieselfeld allow only reduced-output feed-in."]},"test":{"tested_on":"2026-11-25","method":"api_query","http_status":200,"content_type":"application/json; charset=utf-8","size_bytes":77960,"records_total":75,"records_for_country":75,"problems":["TenneT Germany's page (https://www.tennet.eu/de/strommarkt/kunden-deutschland/netzanschlussanfragen) rejects automated HTTP clients with HTTP 403 (Cloudflare anti-bot challenge).","No historical snapshots are exposed by any of the four TSO portals."]},"evidence":[{"claim":"50Hertz states that published available connection capacities are indicative maximum values as of 31 March 2026 with no legal entitlement.","url":"https://www.50hertz.com/de/Vertragspartner/Netzkunden/Netzanschluss","quote":"Bei den angegebenen Werten der verfügbaren Anschlussleistung handelt es sich um Maximalwerte - die genaue Kapazität kann erst ermittelt werden, wenn die genaue Zusammensetzung aller Anschlussnehmer und ihre Verortung bekannt ist. Die auf der Netzkarte dargestellten Netzanschlusspunkte basieren auf der zum 31.03.2026 bestmöglichen Einschätzung und Kenntnislage von 50Hertz."},{"claim":"TransnetBW publishes substation-level connection perspectives based on knowledge as of 1 April 2026 (map Stand 05/2026) and updates cyclically.","url":"https://www.transnetbw.de/de/transparenz/netzzugang-und-entgelt/netzanschlusskarte","quote":"Die auf der Netzkarte dargestellten Netzanschlusspunkte und die verfügbaren Netzanschlusskapazitäten basieren auf der zum 01. April 2026 bestmöglichen Einschätzung und Kenntnislage."},{"claim":"Amprion publishes static April 2026 PDF maps and a 10-substation supplementary document classifying switchgear stations into green ('Anschluss voraussichtlich realisierbar') and red ('Anschlussmöglichkeit nicht gegeben').","url":"https://www.amprion.net/Strommarkt/Netzkunden/Netzanschluss/Darstellung-der-potenziellen-Netzanschlussmoeglichkeiten-und-der-Kundenprojekte.html","quote":"Hierbei werden zwei Kategorien ausgewiesen: „Anschluss voraussichtlich realisierbar“ (grün), und „Anschlussmöglichkeit nicht gegeben“ (rot). Das ergänzende Dokument enthält weitere Informationen über die grün ausgewiesenen Schaltanlagen."},{"claim":"ENTSO-E / EU DSO Entity Capacitypedia documents TenneT TSO Germany's publication as a map and table of substations with available future connection capacity (2030–2036) for demand and storage, updated every 10 months.","url":"https://www.tsodsoplatform.eu/capacitypedia/germany/tennet","quote":"Only substations with available (future) connection capacity are shown. Operator voltage level scope 220 kV, 380 kV Timeline for which HC is provided Potential commissioning years: 2030 - 2036 Information format Map and Table Categories of grid users considered Demand and storage"}],"members":[{"name":"50Hertz Transmission GmbH – Digitale Netzbilder Netzkapazität","landing_url":"https://www.50hertz.com/de/Vertragspartner/Netzkunden/Netzanschluss","data_url":"https://www.50hertz.com/DesktopModules/Lotes/FrequentModules/API/DigitalMap/GetDnbInfo?path=GridLoadMapVersion/map/type/gridcapacity","access":"api","tested":true,"data_found":true,"note":"HTTP 200 JSON (77,960 bytes) with 75 EHV substations, exact WGS84 coordinates, bay count, and available, reserved and requested MW for both generation and load (knowledge 2026-03-31; JSON updatedAt up to 2026-05-18)."},{"name":"TransnetBW GmbH – Netzanschlusskarte","landing_url":"https://www.transnetbw.de/de/transparenz/netzzugang-und-entgelt/netzanschlusskarte","data_url":"https://www.transnetbw.de/de/transparenz/netzzugang-und-entgelt/netzanschlusskarte","access":"web_viewer_only","tested":true,"data_found":true,"note":"HTTP 200 HTML/SVG (280,220 bytes) containing 52 380 kV substation .tooltip nodes (9 green earliest 2032, 6 yellow earliest 2035, 37 red hidden by JS), reporting n-0/n-1 class and separate MW bands for generation and load (assessment 2026-04-01, map Stand 05/2026)."},{"name":"Amprion GmbH – Darstellung der potenziellen Netzanschlussmöglichkeiten","landing_url":"https://www.amprion.net/Strommarkt/Netzkunden/Netzanschluss/Darstellung-der-potenziellen-Netzanschlussmoeglichkeiten-und-der-Kundenprojekte.html","data_url":"https://www.amprion.net/Dokumente/Strommarkt/Netzkunden/Netzanschlussregeln/07_Darstellung-der-Kundenprojekte-sowie-der-Schaltfeldverfuegbarkeit/Ergaenzendes-Dokument-zu-potenziellen-Netzanschlussmoeglichkeiten-04.2026.pdf","access":"pdf","tested":true,"data_found":true,"note":"HTTP 200 PDF table (275,030 bytes, Stand April 2026) listing 10 green 380 kV substations with municipality, (n-0)/(n-1) bay availability, earliest commissioning year (2032–2035) and qualitative load-only/reduced-feed-in remarks, plus static map PDF (535,262 bytes); no numeric MW."},{"name":"TenneT TSO GmbH – Netzanschlussanfragen","landing_url":"https://www.tennet.eu/de/strommarkt/kunden-deutschland/netzanschlussanfragen","data_url":null,"access":"web_viewer_only","tested":true,"data_found":null,"note":"Live HTTP GET returned 403 (Cloudflare challenge); documented via ENTSO-E/EU DSO Entity Capacitypedia and GridChecker as a map and 10-substation table of future 220/380 kV demand/storage connection sites (2030–2036) without numerical available MW."}],"members_summary":{"total":4,"listed":4,"tested":4,"data_found":3,"scope_note":"Covers all 4 balancing-responsible German electricity transmission system operators (Übertragungsnetzbetreiber, ÜNB). All 4 were tested.","pattern":"Published on each ÜNB's Netzanschluss / Netzzugang page alongside joint Reifegradverfahren documentation on netztransparenz.de."},"member_scope":{"total":4,"note":"Covers all 4 balancing-responsible German electricity transmission system operators (Übertragungsnetzbetreiber, ÜNB). All 4 were tested.","pattern":"Published on each ÜNB's Netzanschluss / Netzzugang page alongside joint Reifegradverfahren documentation on netztransparenz.de."}},{"source_id":"de-saarland-geoportal-umspannanlagen","name":"Geoportal Saarland – Kapazitäten der Umspannanlagen","publisher":"Landesamt für Vermessung, Geoinformation und Landentwicklung Saarland (Zentrale Stelle GDI-SL) / Ministerium für Wirtschaft, Innovation, Digitales und Energie Saarland","official":true,"landing_url":"https://geoportal.saarland.de/article/Umspannanlagen_Kapazitaeten/","data_url":"https://geoportal.saarland.de/mapbender/php/wms.php?layer_id=50468&REQUEST=GetCapabilities&VERSION=1.1.1&SERVICE=WMS&withChilds=1","access":"web_viewer_only","format":"Mapbender web viewer / OGC WMS (linked per-substation graphics)","license":"Viewing free within Geoportal Saarland; any other use or embedding in external applications is expressly prohibited","language":"de","has_coordinates":true,"location_precision":"exact","publisher_type":"regional_government","adds":"Only official state-level geoportal in Germany consolidating numerical per-substation HV/MV renewable generation hosting capacity (MW) across multiple distribution system operators (6 Saarland/Pfalz DSOs).","first_seen_pass":1,"rank":2,"summary":"Official Saarland state geoportal mapping HV/MV substations across 6 regional DSOs (VSE Verteilnetz, Creos Deutschland, Pfalzwerke Netz, Stadtwerke Saarbrücken Netz, SSW Netz, KEW) with linked graphics showing installed transformer MW, existing/committed EEG MW, arithmetic available feed-in MW, and queued MW.","coverage_note":"Covers Saarland and adjacent Pfalzwerke/Creos HV/MV substations (WMS Capabilities returns layer metadata without a feature count; 1 state out of 16 Länder).","data_date":"2026-11-24","caveats":["Covers renewable generation feed-in only; no demand capacity is published.","'Verfügbar' is an arithmetic residual (Trafoleistung minus Bestand and Geplant), not a power-flow limit.","Terms forbid any use or embedding outside viewing in Geoportal Saarland."],"coverage":{"geographic":"Saarland (and adjacent Pfalzwerke/Creos substations; bbox 6.3088, 49.0375 to 7.5065, 49.7038), consolidating HV/MV substations of VSE Verteilnetz GmbH, Creos Deutschland GmbH, Pfalzwerke Netz AG, Stadtwerke Saarbrücken Netz AG, SSW Netz GmbH and KEW AG Neunkirchen."},"fine_print":{"unit":{"value":"MW (Megawatt)","quote":"Erläuterungen zu den Begrifflichkeiten auf den verlinkten Grafiken: Angaben zur Leistung in Megawatt (MW)","url":"https://geoportal.saarland.de/article/Umspannanlagen_Kapazitaeten/","attempts":[]},"inclusion_rule":{"value":"High-to-medium-voltage substations (Umspannanlagen) relevant for connecting larger EEG renewable generation plants in Saarland.","quote":"Wichtig für Planungsvorhaben größerer EEG-Anlagen und deren räumlicher Anbindung sind Angaben zu den noch verfügbaren Einspeisekapazitäten bei den großen Netzknoten, den Umspannanlagen.","url":"https://geoportal.saarland.de/article/Umspannanlagen_Kapazitaeten/","attempts":[]},"reference_date":{"value":"WMS metadata updated 2026-11-24 07:29:05 (WMC context updated 2026-11-06).","quote":"Titel Kapazitäten Umspannanlagen SL Aktualität 2026-11-24 07:29:05","url":"https://geoportal.saarland.de/mapbender/php/mod_showMetadata.php?resource=wms&layout=tabs&id=3031&languageCode=de","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://geoportal.saarland.de/article/Umspannanlagen_Kapazitaeten/","note":"Describes figures as 'aktuelle Informationen' without stating a fixed update interval."},{"url":"https://geoportal.saarland.de/mapbender/php/mod_showMetadata.php?resource=wms&layout=tabs&id=3031&languageCode=de","note":"Shows timestamp 'Aktualität 2026-11-24 07:29:05' ('Letzte Aktualisierung 1 Tage') but no scheduled cadence."}]},"exclusions":{"value":"Covers renewable generation feed-in (Einspeisekapazität) only; demand/load hosting capacity is excluded, and 'Verfügbar' is a purely arithmetic transformer residual (Trafoleistung minus Bestand and Geplant) ignoring upstream TSO or feeder voltage constraints.","quote":"Bei dieser Angabe handelt es sich um einen Rechenwert, der die Differenz zwischen der „Trafoleistung“ als maximal möglicher Einspeiseleistung und dem „Bestand“ einschließlich „Geplant“ angibt.","url":"https://geoportal.saarland.de/article/Umspannanlagen_Kapazitaeten/","attempts":[]}},"key_fields":[{"field":"Trafoleistung","meaning":"Total installed HV/MV transformer rating of the substation in MW."},{"field":"Bestand / Geplant","meaning":"Currently installed renewable capacity (MW) and bindingly committed/under-construction renewable capacity (MW) in the substation supply area."},{"field":"Verfügbar","meaning":"Arithmetic remaining renewable feed-in capacity in MW (Trafoleistung minus Bestand and Geplant; negative values indicate grid expansion need)."},{"field":"Anfragen","meaning":"Requested renewable feed-in capacity in MW not yet at 'Geplant' commitment stage."}],"how_to_use":{"example_request":"curl -sSL \"https://geoportal.saarland.de/mapbender/php/wms.php?layer_id=50468&REQUEST=GetCapabilities&VERSION=1.1.1&SERVICE=WMS&withChilds=1\"","example_result":"<WMT_MS_Capabilities updateSequence=\"1795501745\" version=\"1.1.1\"><Service><Name>OGC:WMS</Name><Title>Kapazitäten Umspannanlagen SL</Title><Abstract>Der Kartendienst (WMS-Gruppe) stellt die digitalen Geodaten zu den Kapazitäten der Umspannanlagen im Saarland dar.</Abstract>","steps":["Open https://geoportal.saarland.de/article/Umspannanlagen_Kapazitaeten/ and launch the Mapbender viewer (WMC=7400) for interactive inspection within Geoportal Saarland.","Click any HV/MV substation symbol to open the operator attribution and linked capacity graphic displaying Trafoleistung, Bestand, Geplant, Verfügbar and Anfragen in MW.","Respect the AccessConstraints in the WMS Capabilities document, which prohibit external embedding or reuse outside viewing in Geoportal Saarland."],"reading_traps":["'Verfügbar' is calculated strictly as Trafoleistung − (Bestand + Geplant) in MW without N-1 contingency, thermal line or upstream network modelling, and can be < 0 MW.","Demand/load connection capacity is not reported at all.","Direct ArcGIS REST querying (/arcgis/rest/services/Internet/Netzbetreiber/MapServer) returns a 404 HTML page; only the Mapbender viewer and WMS Capabilities are exposed, under a strict viewer-only reuse prohibition."]},"test":{"tested_on":"2026-11-25","method":"api_query","http_status":200,"content_type":"application/vnd.ogc.wms_xml","size_bytes":12537,"records_total":null,"records_for_country":null,"problems":["Terms of use prohibit any utilization beyond free viewing inside Geoportal Saarland.","Underlying ArcGIS REST MapServer endpoint is not publicly exposed (returns HTML 404), so substation count is not returned by WMS Capabilities (GridChecker indexes ~70+ Saarland/Pfalz substations from these operators)."]},"evidence":[{"claim":"Saarland's grid operators jointly publish HV/MV substation locations and linked MW capacity graphics in Geoportal Saarland.","url":"https://geoportal.saarland.de/article/Umspannanlagen_Kapazitaeten/","quote":"Die saarländischen Netzbetreiber unterstützen diesen Prozess aktiv und haben aktuelle Informationen im Geoportal des Saarlandes zur Verfügung gestellt. Jede in Frage kommende Umspannanlage ist dort verortet."},{"claim":"Geoportal Saarland prohibits any reuse or embedding outside viewing in the portal.","url":"https://geoportal.saarland.de/mapbender/php/mod_showMetadata.php?resource=wms&layout=tabs&id=3031&languageCode=de","quote":"Das Betrachten des Dienstes im “Geoportal Saarland“ ist kostenfrei. Jegliche andere Nutzung, so auch das Einbinden in andere Anwendungen ist untersagt."}],"members":[],"members_summary":null},{"source_id":"de-vnb-netzanschlusskapazitaet","name":"Kapazitätskarten, Online-Netzauskünfte und Zuteilungsportale deutscher Verteilernetzbetreiber (VNB)","publisher":"Individual German electricity distribution system operators (Verteilernetzbetreiber, e.g. Netze BW, N-ERGIE Netz, EWE NETZ, MITNETZ STROM, Bayernwerk Netz, E.DIS Netz, Schleswig-Holstein Netz)","official":true,"landing_url":null,"data_url":null,"access":"web_viewer_only","format":"Interactive web portals and PDFs (varies by DSO)","license":"Proprietary informational self-service tools (non-binding)","language":"de","has_coordinates":true,"location_precision":"exact","publisher_type":"operator","adds":"Covers medium- and high-voltage distribution networks below the TSO level: provides single-site MV connection pre-check portals (up to 10 MW) at major regional DSOs, qualitative HV/MV substation maps at E.ON DSOs, and documents that urban Repartition portals publish only grid-wide MVA totals.","first_seen_pass":1,"rank":3,"summary":"Individual portals of Germany's ~865 electricity DSOs: Netze BW, N-ERGIE Netz and MITNETZ STROM provide interactive single-site MV connection pre-check tools (typically <= 10 MW); E.ON regional DSOs host qualitative HV/MV substation maps behind Cloudflare (HTTP 403); urban DSOs publish only grid-wide Repartition MVA totals.","coverage_note":"Universe of 865 represents German electricity DSOs (869 MaStR Stromnetzbetreiber minus 4 TSOs); 18 major DSOs tested directly (3 with single-site MV pre-check tools, 7 HTTP 403, 8 without node capacity data; 6 further Saarland DSOs are in Geoportal Saarland).","data_date":"2026-08 to 2026-11-25 (varies by DSO)","caveats":["Open MV self-service tools return single-coordinate feasibility up to 10 MW, not bulk substation tables.","E.ON DSO portals (*.zuteilungsverfahren.de) and Westnetz reject non-browser HTTP requests with HTTP 403.","Urban Repartition/Fair-Grid portals (Hamburg, Düsseldorf, ENERVIE, Berlin) give only grid-wide MVA totals or suspended publication."],"coverage":{"geographic":"Decentralised across Germany's ~865 electricity DSOs (814 profiled on VNBdigital, including 84 operating 110 kV HV grids). Tested 18 major DSOs across Baden-Württemberg, Bavaria, NRW, Lower Saxony, Brandenburg, Mecklenburg-Vorpommern, Schleswig-Holstein, Saxony/Saxony-Anhalt, Berlin, Hamburg and Bremen."},"fine_print":{"unit":{"value":"kW or MW in interactive MV pre-check tools (Netze BW: 156–10,000 kW; N-ERGIE Netz: <= 10 MW); qualitative status classes (verfügbar / teilweise verfügbar / begrenzt verfügbar) on E.ON DSO substation maps; MVA in urban grid-wide Repartition notices.","quote":"Sie benötigen einen Netzanschluss mit einer Leistung zwischen 156 kW und 10.000 kW? Nutzen Sie unseren Online-Service Mittelspannungsauskunft, um für Ihr Projekt den optimalen und kosteneffizientesten Netzverknüpfungspunkt/Netzanschlusspunkt zu finden.","url":"https://www.netze-bw.de/stromeinspeisung/mittelspannungsauskunft","attempts":[]},"inclusion_rule":{"value":"Varies by DSO: Netze BW covers MV generation feed-in (156–10,000 kW); N-ERGIE Netz covers LV/MV generation and demand up to 10 MW; E.ON Zuteilungsverfahren portals cover HV/MV substations for large requests; urban Repartition/Fair-Grid procedures apply only above 1.5–5 MVA.","quote":"Aktuell können wir Auskünfte bis 10 MW für unser Nieder- und Mittelspannungsnetz erteilen.","url":"https://kundenportal.n-ergie-netz.de/startseite/netzauskunft/netzanschlussmonitor","attempts":[]},"reference_date":{"value":"Live/daily calculation in Netze BW and N-ERGIE Netz MV pre-check tools ('tagesaktuell'); 2026-08 to 2026-11 for urban 2026 Repartition/Fair-Grid cycles; 2022-07-01 for Westnetz's legacy 110 kV grid-group PDF.","quote":"Noch bevor Sie Ihre Anfrage stellen, erhalten Sie hier sofort eine tagesaktuelle und unverbindliche Auskunft zu den voraussichtlichen Anschlusspunkten an unser Mittelspannungsnetz.","url":"https://www.netze-bw.de/stromeinspeisung/mittelspannungsauskunft","attempts":[]},"update_frequency":{"value":"Weekly for Netze BW Mittelspannungsauskunft (per Capacitypedia); annual cycles for urban Repartition/Fair-Grid procedures (Hamburg, Düsseldorf, ENERVIE, wesernetz); unscheduled/per-allocation-window for E.ON Zuteilungsverfahren portals.","quote":"Die Ergebnisse der nächsten Netzanschlusskapazitätsermittlung werden bis zum 01.09.2027 auf der Website der Netzgesellschaft Düsseldorf mbH veröffentlicht.","url":"https://a.storyblok.com/f/274773/x/6b3f18173e/netzanschlusskapazitat-2026.pdf","attempts":[]},"exclusions":{"value":"Interactive MV tools (Netze BW, N-ERGIE, EWE, MITNETZ) do not expose downloadable substation tables and exclude 110 kV/TSO constraints; E.ON's former joint Netzampel (netzampel.energy) was shut down; urban Repartition portals publish only network-wide MVA totals (0 MVA in Hamburg and Düsseldorf for 2026).","quote":"Unser übergeordnetes Hochspannungsnetz wird erst bei der verbindlichen Netzprüfung einbezogen. Daraus kann sich gegebenenfalls ein alternativer Netzanschlusspunkt ergeben.","url":"https://kundenportal.n-ergie-netz.de/startseite/netzauskunft/netzanschlussmonitor","attempts":[]}},"key_fields":[{"field":"Standort / Geplante Leistung / Anschlusstyp","meaning":"Input coordinate/address, requested capacity (kW/MW) and connection direction (generation vs demand) in DSO self-service MV tools, returning an indicative connection point."},{"field":"Verfügbare Anschlusskapazitäten (MVA, network-wide)","meaning":"Grid-wide MVA quota published in urban Repartition/Fair-Grid notices (not broken down by substation)."}],"how_to_use":{"example_request":"curl -sSL \"https://www.vnbdigital.de/gateway/graphql\" -H \"Content-Type: application/json\" -d '{\"query\":\"{ vnb_search(searchTerm: \\\"70173\\\") { _id title subtitle type } }\"}'","example_result":"Identify the local DSO for any German postal code or coordinate via VNBdigital's GraphQL API, then open that DSO's Netzanschluss / Online-Netzauskunft / Zuteilungsverfahren portal.","steps":["Query VNBdigital (https://www.vnbdigital.de) by postal code, municipality or coordinate to identify the responsible electricity DSO among Germany's ~865 DSOs.","For Netze BW (Mittelspannungsauskunft, 156–10,000 kW feed-in), N-ERGIE Netz (Netzanschlussmonitor, <= 10 MW feed-in or load), EWE NETZ (Online-Netzauskunft Mittelspannung) or MITNETZ STROM (NiNa <= 135 kW / SNAP >= 135 kW), enter a candidate coordinate and MW in the web tool to obtain the nearest feasible MV connection point.","For Bayernwerk Netz, E.DIS Netz and Schleswig-Holstein Netz, open their *.zuteilungsverfahren.de portals in a browser (plain HTTP clients receive Cloudflare HTTP 403) to view qualitative HV/MV substation availability."],"reading_traps":["Do not confuse network-wide Repartition/Fair-Grid quotas (e.g. Hamburger Energienetze 0 MVA for 2026/2027, Netzgesellschaft Düsseldorf 0 MVA for 2026, ENERVIE Vernetzt ~100 MVA as of 10/2025) with substation-level hosting capacity; Stromnetz Berlin cancelled its planned April 2026 geographic capacity publication pending OLG Düsseldorf case VI-5 Kart 4/26 [V].","Do not confuse § 23c(1) Nr. 2 EnWG Netzstrukturdaten (e.g. SWM Infrastruktur's 3,522,500 kVA HV/MV installed transformer rating) with available connection capacity.","EWE NETZ's Online-Netzauskunft reports distance to the nearest MV line or substation without guaranteeing available MW; Netze BW's Mittelspannungsauskunft covers feed-in only and ignores TSO constraints.","E.ON's former joint municipal/substation portal netzampel.energy returns only a retired 628-byte shell page; current *.zuteilungsverfahren.de and corporate E.ON/Westnetz domains block non-browser HTTP clients with HTTP 403."]},"test":{"tested_on":"2026-11-25","method":"page_only","http_status":200,"content_type":"text/html; charset=utf-8","size_bytes":188265,"records_total":null,"records_for_country":null,"problems":["No bulk substation download or public REST/WFS endpoint found on tested open DSO pages; interactive MV tools require per-coordinate queries.","Bayernwerk Netz, E.DIS Netz, Schleswig-Holstein Netz, Avacon Netz, Westnetz, Syna and Westfalen Weser Netz reject automated HTTP clients with HTTP 403 (Cloudflare/WAF)."]},"evidence":[{"claim":"N-ERGIE Netz provides an online pre-check of free LV/MV connection capacities up to 10 MW for both generation and demand plants.","url":"https://kundenportal.n-ergie-netz.de/startseite/netzauskunft/netzanschlussmonitor","quote":"Sie möchten sich unverbindlich ein erstes Bild machen, ob Ihre geplante Erzeugungs- oder Verbrauchsanlage an unser Nieder- oder Mittelspannungsnetz angebunden werden kann und ggf. verschiedene Standorte und Leistungen ausprobieren? Unsere Anwendung liefert den nächstmöglichen Anschlusspunkt, der Ihre geplante Leistung mit hoher Wahrscheinlichkeit aufnehmen kann."},{"claim":"Hamburger Energienetze reports 0 MVA of firm or flexible MV/HV demand connection capacity outside local public-service projects in its first Fair Grid cycle (02.11.2026–30.09.2027).","url":"https://www.hamburger-energienetze.de/verbrauchen-erzeugen/planen-anmelden/kundenstation/fairgrid","quote":"Darüber hinaus werden im ersten Zyklus keine Anschlusskapazitäten (0 MVA für feste Kapazitäten / 0 MVA für flexible Kapazitäten) in der Mittel- und Hochspannung vergeben."},{"claim":"Stromnetz Berlin suspended its planned April 2026 publication of available capacities and their geographical locations pending OLG Düsseldorf proceedings (VI-5 Kart 4/26 [V]).","url":"https://www.stromnetz.berlin/en/connecting/medium-and-high-voltage/allocation-procedure/","quote":"We are no longer, as originally planned, going to publish the capacities for connection services currently available and/or available in the foreseeable future in our network area and their geographical location by the fifteenth working day in April 2026."}],"members":[{"name":"Netze BW GmbH – Mittelspannungsauskunft & Punkteverfahren","landing_url":"https://www.netze-bw.de/stromeinspeisung/mittelspannungsauskunft","data_url":null,"access":"web_viewer_only","tested":true,"data_found":true,"note":"HTTP 200. Interactive single-site MV connection pre-check for generation (156–10,000 kW, updated weekly per Capacitypedia); separate /netzanschluss/vergabe page documents Punkteverfahren since Aug 2026 without a bulk substation table."},{"name":"N-ERGIE Netz GmbH – Netzanschlussmonitor","landing_url":"https://kundenportal.n-ergie-netz.de/startseite/netzauskunft/netzanschlussmonitor","data_url":null,"access":"web_viewer_only","tested":true,"data_found":true,"note":"HTTP 200. Interactive single-site pre-check for LV/MV generation and demand up to 10 MW; excludes 110 kV network and offers no bulk substation export."},{"name":"MITNETZ STROM (Mitteldeutsche Netzgesellschaft Strom mbH) – NiNa / SNAP","landing_url":"https://www.mitnetz-strom.de/energie-einspeisen/anlage-anmelden","data_url":null,"access":"web_viewer_only","tested":true,"data_found":true,"note":"HTTP 200. Mandatory address-level pre-check tools NiNa (<= 135 kW) and SNAP (>= 135 kW) before application; no downloadable substation capacity table."},{"name":"EWE NETZ GmbH – Online-Netzauskunft Mittelspannung","landing_url":"https://www.ewe-netz.de/einspeiser/strom/ihr-netzanschluss/online-netzauskunft","data_url":"https://online.netzauskunft.ewe-netz.de/","access":"web_viewer_only","tested":true,"data_found":false,"note":"HTTP 200. Tool estimates distance to nearest MV line or substation for candidate sites without publishing available MW per substation."},{"name":"Bayernwerk Netz GmbH – Zuteilungsverfahren Kapazitätskarte","landing_url":"https://bayernwerk-netz.zuteilungsverfahren.de/","data_url":null,"access":"web_viewer_only","tested":true,"data_found":null,"note":"HTTP 403 (Cloudflare challenge on both bayernwerk-netz.zuteilungsverfahren.de and bayernwerk-netz.de); GridChecker indexes 329 HV/MV substations with qualitative status (1 available, 34 limited, 294 none available)."},{"name":"E.DIS Netz GmbH – Zuteilungsverfahren Kapazitätskarte","landing_url":"https://e-dis-netz.zuteilungsverfahren.de/","data_url":null,"access":"web_viewer_only","tested":true,"data_found":null,"note":"HTTP 403 (Cloudflare challenge on e-dis-netz.zuteilungsverfahren.de and e-dis-netz.de); GridChecker indexes 140 substations from this portal."},{"name":"Schleswig-Holstein Netz GmbH – Zuteilungsverfahren Kapazitätskarte","landing_url":"https://sh-netz.zuteilungsverfahren.de/","data_url":null,"access":"web_viewer_only","tested":true,"data_found":null,"note":"HTTP 403 (Cloudflare challenge on sh-netz.zuteilungsverfahren.de and sh-netz.com); GridChecker indexes 130 substations from this portal."},{"name":"Westnetz GmbH – SNAP & Auslastung der Netzgruppen","landing_url":"https://www.westnetz.de/de/einspeisen/snap-online-portal.html","data_url":"https://www.westnetz.de/content/dam/revu-global/westnetz/documents/einspeisen/aktuelles-fuer-einspeisende/veroeffentlichung-einspeisung/auslastung-der-netzgruppen-durch-einspeisung.pdf","access":"pdf","tested":true,"data_found":null,"note":"HTTP 403 (Cloudflare challenge on both SNAP landing page and 110 kV grid-group PDF); GridChecker reports the PDF covers 17 110 kV grid groups dated 2022-07-01."},{"name":"Avacon Netz GmbH – Avacon Map","landing_url":"https://www.avacon-netz.de/de/energie-service/informationen/avacon-map-die-kompakte-onlineuebersichtskarte.html","data_url":null,"access":"web_viewer_only","tested":true,"data_found":null,"note":"HTTP 403 (Cloudflare challenge on avacon-netz.de)."},{"name":"Syna GmbH – Netzanschluss","landing_url":"https://www.syna.de/corp/netzanschluss","data_url":null,"access":"web_viewer_only","tested":true,"data_found":null,"note":"HTTP 403 (Cloudflare challenge on syna.de)."},{"name":"Westfalen Weser Netz GmbH – Netzanschluss über 1 MW","landing_url":"https://www.ww-netz.com/netzanschluss/ihr-netzanschluss/netzanschluss-ueber-1-mw","data_url":null,"access":"web_viewer_only","tested":true,"data_found":null,"note":"HTTP 403 (WAF block on ww-netz.com)."},{"name":"Hamburger Energienetze GmbH – Fair Grid","landing_url":"https://www.hamburger-energienetze.de/verbrauchen-erzeugen/planen-anmelden/kundenstation/fairgrid","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"HTTP 200. Publishes only network-wide MV/HV demand allocation quota (0 MVA firm / 0 MVA flexible for 02.11.2026–30.09.2027 outside public-service projects); no per-substation data."},{"name":"Netzgesellschaft Düsseldorf mbH – Zuteilungsverfahren > 3,5 MVA","landing_url":"https://www.netz-duesseldorf.de/netzanschluss/zuteilungsverfahren-fuer-kapazitaeten-groesser-3-5-mva","data_url":"https://a.storyblok.com/f/274773/x/6b3f18173e/netzanschlusskapazitat-2026.pdf","access":"pdf","tested":true,"data_found":false,"note":"HTTP 200 PDF (218,193 bytes, Stand Aug 2026) states 0 MVA immediately available across the entire DSO grid for requests > 3.5 MVA in 2026; no per-substation breakdown."},{"name":"ENERVIE Vernetzt GmbH – Vergabeverfahren für Anschlusskapazität","landing_url":"https://www.enervie-vernetzt.de/Home/strom/vergabeverfahren-fuer-anschlusskapazitaet.aspx","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"HTTP 200. Publishes only a single network-wide remaining demand capacity figure (~100 MVA as of end-10/2025 for requests >= 5 MVA); no per-substation breakdown."},{"name":"wesernetz Bremen GmbH – Repartierungsverfahren","landing_url":"https://www.wesernetz.de/fuer-bauende/grossanlagen-netzanschluss/neu-netzanschluss-grossanlagen/repartierungsverfahren","data_url":"https://www.wesernetz.de/-/media/wesernetz/downloads-aktuell/fuer-bauende/repartierungsverfahren/entwurf_netzausbauplan_2026.pdf","access":"pdf","tested":true,"data_found":false,"note":"HTTP 200. Repartition page (> 3 MW) and draft Netzausbauplan 2026 PDF (310,526 bytes) list expansion measures (+/- MVA) without per-substation available connection capacity."},{"name":"Stromnetz Berlin GmbH – Repartition Procedure & Open Data","landing_url":"https://www.stromnetz.berlin/en/connecting/medium-and-high-voltage/allocation-procedure/","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"HTTP 200. Planned April 2026 geographic publication of available capacities (> 3.5 MVA) was cancelled pending OLG Düsseldorf case VI-5 Kart 4/26 [V]; Open Data portal contains aggregate grid structure and load series only."},{"name":"SWM Infrastruktur GmbH & Co. KG (München) – Netzstrukturdaten Strom","landing_url":"https://www.swm-infrastruktur.de/netzzugang/unser-netz/netzstrukturdaten-strom","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"HTTP 200. Publishes § 23c EnWG aggregate transformer kVA per voltage tier and load/feed-in ZIPs, without substation-level available connection capacity."},{"name":"LEW Verteilnetz GmbH – Einspeiser","landing_url":"https://www.lew-verteilnetz.de/de/einspeiser","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"HTTP 200 SPA shell; connection inquiries handled via mein.Hausanschlussportal without a public substation hosting-capacity dataset."}],"members_summary":{"total":865,"listed":18,"tested":18,"data_found":3,"scope_note":"Universe of 865 German electricity DSOs is inferred by subtracting the 4 balancing-zone TSOs from the 869 active Stromnetzbetreiber returned live by BNetzA's MaStR (consistent with BMWE's Aug 2026 Netzanschlusspaket draft bill citing 866 DSOs on p. 41 / 851 on p. 25, and VNBdigital's 814 DSO profiles). 18 major regional and urban DSOs were tested directly here (plus 6 Saarland/Pfalz DSOs covered in de-saarland-geoportal-umspannanlagen).","pattern":"Look up the local DSO on https://www.vnbdigital.de, then search its website for 'Kapazitätskarte', 'Online-Netzauskunft', 'Mittelspannungsauskunft', 'SNAP', 'Zuteilungsverfahren' or 'Repartierungsverfahren'."},"member_scope":{"total":865,"note":"Universe of 865 German electricity DSOs is inferred by subtracting the 4 balancing-zone TSOs from the 869 active Stromnetzbetreiber returned live by BNetzA's MaStR (consistent with BMWE's Aug 2026 Netzanschlusspaket draft bill citing 866 DSOs on p. 41 / 851 on p. 25, and VNBdigital's 814 DSO profiles). 18 major regional and urban DSOs were tested directly here (plus 6 Saarland/Pfalz DSOs covered in de-saarland-geoportal-umspannanlagen).","pattern":"Look up the local DSO on https://www.vnbdigital.de, then search its website for 'Kapazitätskarte', 'Online-Netzauskunft', 'Mittelspannungsauskunft', 'SNAP', 'Zuteilungsverfahren' or 'Repartierungsverfahren'."}},{"source_id":"gridchecker-de","name":"GridChecker – Germany Grid Connection Capacity and Connection Queue","publisher":"GridChecker","official":false,"landing_url":"https://gridchecker.com/countries/de","data_url":"https://gridchecker.com/de/netzanschluss-kapazitaet","access":"paid","format":"HTML preview table (public), CSV and API / map export (paid subscription)","license":"Commercial proprietary (figures non-binding as published by grid operators)","language":"en, de","has_coordinates":true,"location_precision":"exact","publisher_type":"commercial","adds":"Consolidates 844 substations across 29 German operators (all 4 TSOs and 25 DSOs) into one schema and is the only source retaining daily historical snapshots since October 2024.","first_seen_pass":1,"rank":4,"summary":"Commercial aggregator harmonising public capacity maps and tables from 29 German operators (all 4 TSOs and 25 DSOs, 844 sites total), offering free HTML previews and paid CSV/API access with daily archived snapshots since October 2024.","coverage_note":"844 records represent published substations and 17 Westnetz 110 kV grid groups across 29 operators (~3.3% of Germany's 869 active electricity grid operators); 815 have map coordinates.","data_date":"2026-11-25","caveats":["Full CSV export and historical snapshots since Oct 2024 require a paid subscription.","Inherits upstream gaps (no numeric MW for Bayernwerk, Amprion or TenneT; includes 50Hertz Eulenberg duplicate and 2022 Westnetz PDF)."],"coverage":{"geographic":"Germany: 844 substations (815 geocoded on map) across 29 operators (4 TSOs + 25 DSOs, led by Bayernwerk Netz 329, E.DIS Netz 140, Schleswig-Holstein Netz 130, 50Hertz 75, TransnetBW 52, VSE Verteilnetz 28, Westnetz 17, Creos Deutschland 15, Amprion 10, Pfalzwerke Netz 10, TenneT DE 10, Stadtwerke Saarbrücken Netz 9)."},"fine_print":{"unit":{"value":"MW and GW (plus qualitative statuses 'Available', 'Limited', 'None available', 'Not published' where operators publish no MW).","quote":"Altentreptow Süd (ATS) substation 50Hertz 50Hertz Available 650 MW 850 MW 5.2 GW","url":"https://gridchecker.com/countries/de","attempts":[]},"inclusion_rule":{"value":"Substations and 110 kV grid groups publicly published by the 4 German TSOs and 25 German DSOs tracked by GridChecker.","quote":"Von den Veröffentlichungen der Netzbetreiber, u. a. 50Hertz, TenneT, Amprion, TransnetBW und den E.ON-Verteilnetzbetreibern. Mit § 17c EnWG werden weitere Betreiber folgen.","url":"https://gridchecker.com/de/netzanschluss-kapazitaet","attempts":[]},"reference_date":{"value":"Last sync 2026-11-25 05:27 UTC (reflecting each underlying operator's latest published edition).","quote":"29 operator s · checked 25 Nov, 05:27 UTC","url":"https://gridchecker.com/countries/de","attempts":[]},"update_frequency":{"value":"Daily automated polling at 05:15 UTC, archiving every changed snapshot since October 2024.","quote":"Wir prüfen die Quellen täglich um 05:15 UTC. Die Netzbetreiber aktualisieren ihre Karten in unterschiedlichen Abständen.","url":"https://gridchecker.com/de/netzanschluss-kapazitaet","attempts":[]},"exclusions":{"value":"Covers 29 of Germany's 869 active electricity grid operators (~3.3%); full 844-site download, demand tab switching and historical snapshots require registration/paid plan.","quote":"History since Oct 2024 every snapshot kept, checked daily","url":"https://gridchecker.com/countries/de","attempts":[]}},"key_fields":[{"field":"Site / Operator","meaning":"Substation or 110 kV grid-area name and publishing TSO/DSO."},{"field":"Status / Available / Reserved / Requested","meaning":"Standardised availability class and available, reserved and requested capacity in MW/GW (shown separately for Generation and Demand tabs)."}],"how_to_use":{"example_request":"curl -sSL \"https://gridchecker.com/countries/de\"","example_result":"HTML table previewing 32 substations sorted by available generation capacity (e.g., Hohenwarte II 2.0 GW, Altentreptow Süd 650 MW available / 850 MW reserved / 5.2 GW requested, UA Weiher110 kV Creos 96 MW available / 4 MW reserved) plus links to 29 operator subpages.","steps":["Fetch https://gridchecker.com/countries/de or https://gridchecker.com/de/netzanschluss-kapazitaet to inspect national totals, top substations and links to all 29 tracked German operators.","Fetch individual operator pages (e.g. /operators/de-bayernwerk-netz) to view site-level status previews and the exact upstream operator URL.","Full 844-substation CSV exports, demand-view toggles and historical snapshots since Oct 2024 require a commercial GridChecker plan."],"reading_traps":["The 844 tracked 'sites' mix individual EHV/HV/MV substations, duplicate 50Hertz Neubau entries (e.g. both Eulenberg (EUB) and Eulenberg (EUB) Neubau appear as 1.8 GW), and Westnetz's 17 multi-substation 110 kV grid areas dated 01.07.2022.","History depth varies sharply by operator: while the platform states 'History since Oct 2024', individual operator pages show e.g. 22 snapshots for TenneT DE (since 9 June 2026) and only 1 snapshot for Bayernwerk Netz (since 16 November 2026)."]},"test":{"tested_on":"2026-11-25","method":"page_only","http_status":200,"content_type":"text/html; charset=UTF-8","size_bytes":137423,"records_total":844,"records_for_country":844,"problems":["Public HTML exposes only ~32 preview rows on the country page; bulk CSV export and historical time series require a paid subscription."]},"evidence":[{"claim":"GridChecker tracks 844 German sites across 29 operators with daily checks and version archives since October 2024.","url":"https://gridchecker.com/countries/de","quote":"Sites we track 844 815 on the map History since Oct 2024 every snapshot kept, checked daily"},{"claim":"87% of the 844 published German substations currently have no free demand connection capacity.","url":"https://gridchecker.com/de/netzanschluss-kapazitaet","quote":"127,6 GW an Netzanschlussanfragen warten auf einen Anschluss. Von 844 veröffentlichten Umspannwerken hat 87% keine freie Kapazität mehr."}],"members":[],"members_summary":null}],"sector":{"regulator":{"name":"Bundesnetzagentur für Elektrizität, Gas, Telekommunikation, Post und Eisenbahnen (BNetzA)","url":"https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/Netzanschluss/start.html"},"operators":{"structure":"many","note":"4 balancing-responsible transmission system operators (Übertragungsnetzbetreiber: 50Hertz, Amprion, TenneT Germany, TransnetBW) and ~865 electricity distribution system operators (869 active Stromnetzbetreiber in BNetzA's live MaStR directory minus 4 TSOs; BMWE's Aug 2026 Netzanschlusspaket bill cites 866 DSOs on p. 41 / 851 on p. 25, and VNBdigital lists 814 electricity DSOs, 84 with 110 kV HV networks).","census_url":"https://www.marktstammdatenregister.de/MaStR/Akteur/Marktakteur/IndexOeffentlich?filter=Marktfunktion~eq~%271%27~and~T%C3%A4tigkeitsstatus~eq~%272511%27"},"publication_obligation":{"exists":"yes","norm":"Directly applicable Art. 50(4a) subpara. 1 of Regulation (EU) 2019/943 (inserted by Regulation (EU) 2024/1747) for TSOs; Art. 31(3) subpara. 1 of Directive (EU) 2019/944 (inserted by Directive (EU) 2024/1711) for DSOs, pending national transposition in § 17c EnWG-E of the federal cabinet's Netzanschlusspaket bill (29 July / 12 August 2026; currently § 17c EnWG is repealed).","url":"https://eur-lex.europa.eu/eli/reg/2024/1747/oj","what_must_be_published":"Clear information on capacity available for new connections with high spatial granularity, including capacity under connection request, criteria for calculation, and flexible connection possibilities; pending § 17c(1) EnWG-E requires EHV/HV and HV/MV geographic capacity maps for both feed-in and load on each operator's website (plus MV online pre-check tools from 1 January 2028 under § 17c(2) EnWG-E).","frequency":"At least monthly for TSOs under Art. 50(4a) Regulation (EU) 2019/943; at least quarterly for DSOs under Art. 31(3) Directive (EU) 2019/944, tightened to monthly for EHV/HV and HV/MV maps in draft § 17c(1) EnWG-E."},"consolidated_republication":{"found":"no_evidence_found","note":"Neither EU Regulation 2024/1747 nor draft § 17c EnWG-E mandates central national republication: each operator publishes on its own website under BNetzA abuse supervision. Only Saarland's state geoportal consolidates 6 regional DSOs, and commercial GridChecker aggregates 29 operators.","checked_pages":[{"organization":"Bundesnetzagentur (BNetzA)","url":"https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/Netzanschluss/start.html","saw":"Guidance on § 17 EnWG grid connection rules, flexible connection agreements (FCA) and construction cost contributions (BKZ); no national substation hosting-capacity map or dataset."},{"organization":"Bundesnetzagentur – Verteilernetze Zustand und Ausbau","url":"https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/VerteilerNetz/start.html","saw":"Archive of 2015–2022 PDF reports on distribution grid status and note that from NAP 2024 onward BNetzA publishes thematic articles on smard.de and refers to vnbdigital.de; no substation capacity dataset."},{"organization":"SMARD (Bundesnetzagentur)","url":"https://www.smard.de/home","saw":"Wholesale generation, consumption, market price and congestion-management time series by bidding/control zone; no substation hosting capacity."},{"organization":"VNBdigital (BDEW / VNB-Plattform nach § 14e EnWG)","url":"https://www.vnbdigital.de/","saw":"Joint platform of 814 electricity DSOs providing operator boundary layers, § 14d EnWG Netzausbaupläne, regional scenarios and outbound portal links, without node-level available connection capacity."},{"organization":"Bundesministerium für Wirtschaft und Energie (BMWE)","url":"https://www.bundeswirtschaftsministerium.de/Redaktion/DE/Downloads/Gesetz/2026/20260812-entwurf-netzanschlusspaket.pdf?__blob=publicationFile&v=4","saw":"Cabinet draft Netzanschlusspaket (pp. 8, 25, 41) confirming § 17c(1) EnWG-E requires publication on each operator's own website ('auf ihrer jeweiligen Internetseite'), not in a central BNetzA database."}]}},"national_registry":{"exists":"no_evidence_found","note":"Germany has no official national registry or unified dataset of available substation connection capacity. MaStR registers generation/storage units and grid operators without substation hosting capacity, VNBdigital links to 814 DSO profiles and Netzausbaupläne, and GovData/Geoportal.de hold no national hosting-capacity layer.","checked_pages":[{"organization":"Bundesnetzagentur – Netzanschluss","url":"https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/Netzanschluss/start.html","saw":"Regulatory explanations of § 17 EnWG and flexible connection agreements; no national substation capacity dataset."},{"organization":"Marktstammdatenregister (MaStR)","url":"https://www.marktstammdatenregister.de/MaStR/Datendownload","saw":"Daily XML bulk export (3.23 GB ZIP) of energy installations and market actors (869 active Stromnetzbetreiber), containing no substation available connection capacity."},{"organization":"VNBdigital","url":"https://www.vnbdigital.de/","saw":"GraphQL API and map for 814 electricity DSOs exposing territory WMS, Netzausbaupläne and portal links, but no substation hosting-capacity figures."},{"organization":"ENTSO-E & EU DSO Entity – Capacitypedia Germany","url":"https://www.tsodsoplatform.eu/capacitypedia/germany","saw":"Explicitly notes that Germany has 4 TSOs and >800 DSOs and that hosting-capacity publication depends on each individual system operator."},{"organization":"GovData & Geoportal.de","url":"https://www.govdata.de/","saw":"National open-data catalogue (checked alongside https://www.geoportal.de/); contains municipal XPlanung plans and Berlin § 23c EnWG structural tables, with no nationwide substation hosting-capacity dataset."}]},"if_unstructured":{"summary":"Where a tested DSO publishes no substation capacity map or a TSO omits numerical MW (Amprion, TenneT), look up the responsible DSO via VNBdigital and extract substation expansion deltas (+/- MVA) and bottleneck flags from its biennial § 14d EnWG Netzausbauplan PDF and annual Repartition/Fair-Grid capacity notices, or submit a formal Netzanschlussbegehren.","recipe":["Query https://www.vnbdigital.de/gateway/graphql (or the web map) with the target postal code or municipality to identify the local electricity DSO and check whether it operates Hochspannung (84 DSOs) or Mittelspannung (780 DSOs).","Download the DSO's Netzausbauplan 2026 PDF linked from its VNBdigital profile or corporate website, extract tables with pdftotext -layout, and filter rows where 'Betriebsmittel' mentions 'UW' / 'Umspannwerk' / 'Umspanner' to identify existing or forecast substation bottlenecks and planned MVA additions (note: Netzausbaupläne give planned +/- MVA deltas and bottleneck flags, not current free hosting capacity).","Check the DSO's Netzanschluss section for annual Repartition/Zuteilungsverfahren PDFs to verify whether network-wide MV/HV capacity is capped at 0 MVA, or run a candidate coordinate through its Online-Netzauskunft tool for projects <= 10 MW."],"location_method":"Substation names and municipalities in Amprion PDFs and DSO Netzausbaupläne do not always carry coordinates; match named HV/EHV substations against OpenStreetMap power=substation features or regional geoportals (e.g. Geoportal.de / state ALKIS basemaps).","cross_with":["OpenStreetMap (power=substation and voltage=* polygons/nodes in Germany, downloadable via Geofabrik https://download.geofabrik.de/europe/germany.html) to geocode named substations lacking coordinates in PDF tables.","Marktstammdatenregister (https://www.marktstammdatenregister.de/MaStR/Datendownload) to aggregate already connected and planned generation/storage capacity in a municipality or grid operator area.","Netzentwicklungsplan Strom (https://www.netzentwicklungsplan.de/) to cross-check planned 220/380 kV TSO substation expansions driving TransnetBW, Amprion and TenneT 2030–2036 horizons."],"where_published":[{"name":"VNBdigital – Netzausbaupläne nach § 14d EnWG & DSO Portal Directory","url":"https://www.vnbdigital.de/","what":"Joint platform of 814 German electricity DSOs linking each operator's biennial Netzausbauplan (first statutory cycle due 31 October 2026), regional scenarios, and Netzanschluss portals.","how_to_search_inside":"Search by postal code, municipality or operator name via the search bar (backed by POST /gateway/graphql vnb_search and vnb_vnb queries), then open the 'Netzausbauplan' and 'Netzanschluss' cards on the operator profile.","example_document":{"url":"https://www.wesernetz.de/-/media/wesernetz/downloads-aktuell/fuer-bauende/repartierungsverfahren/entwurf_netzausbauplan_2026.pdf","what_it_gives":"Tabular measure list (p. 1 ff.) with columns 'Maßnahme', 'Betriebsmittel', 'Änderung der Übertragungskapazität [+/- MVA]', congestion flags ('bestehenden Engpass zu beheben?', 'prognostizierten Engpass vorzubeugen?') and target dates — e.g. Lfd. Nr. 5 'Erweiterung zum 110 kV Ringschluss', HS-Kabel, '+100' MVA, Inbetriebnahme '12/2029', 'konkrete Planung'."}},{"name":"DSO Repartierungsverfahren / Zuteilungsverfahren Annual Capacity Notices","url":"https://www.netz-duesseldorf.de/netzanschluss/zuteilungsverfahren-fuer-kapazitaeten-groesser-3-5-mva","what":"Annual PDF determinations published by congested urban/regional DSOs stating available MV/HV connection capacity for the upcoming allocation window.","how_to_search_inside":"On the local DSO's website under 'Netzanschluss' -> 'Mittel-/Hochspannung', open 'Zuteilungsverfahren', 'Repartierungsverfahren', 'Punkteverfahren' or 'Fair Grid' and download the current year's capacity determination PDF.","example_document":{"url":"https://a.storyblok.com/f/274773/x/6b3f18173e/netzanschlusskapazitat-2026.pdf","what_it_gives":"Page 1 ('Ergebnis der Kapazitätsermittlung 2026', Stand August 2026): 'dass für das Jahr 2026 keine unmittelbar verfügbaren freien Netzanschlusskapazitäten im Stromnetz für Leistungsanfragen mit größer als 3,5 MVA zur Vergabe bereitstehen', with next publication due '01.09.2027'."}}]},"related_not_answering":[{"name":"VNBdigital – Gemeinsame Internetplattform der Verteilernetzbetreiber (§ 14d / § 14e EnWG)","url":"https://www.vnbdigital.de/","why":"Provides DSO service territories, regional scenarios, biennial Netzausbaupläne (planned expansion measures) and portal links for 814 electricity DSOs, not current available MW per substation."},{"name":"ENTSO-E & EU DSO Entity – Capacitypedia (Germany)","url":"https://www.tsodsoplatform.eu/capacitypedia/germany","why":"Pan-European metadata directory describing the methodology and links of the 4 German TSOs and Netze BW without hosting substation-level capacity records itself."},{"name":"Marktstammdatenregister (MaStR) – Gesamtdatenexport","url":"https://www.marktstammdatenregister.de/MaStR/Datendownload","why":"Registers commissioned and planned generation/storage units and grid operators, not remaining substation or transformer hosting capacity."},{"name":"SMARD – Strommarktdaten der Bundesnetzagentur","url":"https://www.smard.de/home","why":"Publishes control-zone and national generation, load, price and congestion time series, without substation-level connection capacity."},{"name":"Netzstrukturdaten nach § 23c Abs. 1 Nr. 2 EnWG (e.g. SWM Infrastruktur, Stromnetz Berlin)","url":"https://www.swm-infrastruktur.de/netzzugang/unser-netz/netzstrukturdaten-strom","why":"Reports only aggregate installed transformer kVA summed across an entire voltage tier per DSO as of 31 December of the prior year, not free capacity per substation."},{"name":"TenneT D2 Core Static Grid Model","url":"https://netztransparenz.tennet.eu/de/strommarkt/transparenz/transparenz-deutschland","why":"Provides static EHV line, transformer and substation electrical parameters for market coupling rather than available customer connection capacity."},{"name":"ENLAPA GIS – Netzintelligenz","url":"https://www.enlapa.de/de/gis/netzintelligenz","why":"Commercial platform whose substation 'Freie Netzkapazität' layer is an 8,760-hour DC/PTDF power-flow model estimate calibrated on redispatch and MaStR rather than operator-published available capacity."},{"name":"OpenStreetMap (power=substation via Geofabrik / Taginfo)","url":"https://download.geofabrik.de/europe/germany.html","why":"Maps physical substation footprints and nominal voltages across Germany but contains no available generation or demand hosting-capacity figures."}],"open_questions":["What unit does 50Hertz's undocumented JSON attribute constructionCostContribution (observed values 40.0, 60.0, 100.0) represent — a percentage tier of the Baukostenzuschuss or EUR/kW?","Whether Bayernwerk Netz, E.DIS Netz and Schleswig-Holstein Netz expose downloadable GeoJSON/REST endpoints inside their browser-gated *.zuteilungsverfahren.de portals once interactive Cloudflare verification is completed.","When Bundestag/Bundesrat will enact draft § 17c EnWG-E of the August 2026 Netzanschlusspaket and whether BNetzA will define a machine-readable standard format across all ~479 HV/MV operators."],"history":[{"pass":1,"date":"2026-11-26","role":"research","model":"Gemini 4 Carbon","rules_version":"2026-11-25-de-red-y-tramitacion","note":"Initial research in session f843b96e-b516-44f8-8831-ee71816fec53: tested all 4 TSOs (including 50Hertz 75-node JSON API and TransnetBW 52-node HTML map), Saarland Geoportal, 18 DSOs, VNBdigital, BNetzA/EnWG and GridChecker.","headline":{"official_data":"partial","non_official_data":"partial","national_registry":"no_evidence_found"},"sources":{"total":4,"new":4,"dropped":0},"negatives":{"overturned":0,"confirmed":0},"effort":{"pages":86,"minutes":40}}],"local_terms":[{"term":"Kapazitätskarte / Netzanschlusskarte","language":"de","meaning":"Geographic hosting-capacity or grid-connection map published by a TSO or DSO per substation or grid area."},{"term":"Verfügbare Einspeisekapazität / Verfügbare Lastkapazität","language":"de","meaning":"Available connection capacity for generation feed-in (Einspeisung) versus demand/offtake (Last / Bezug)."},{"term":"Umspannwerk (UW) / Schaltanlage","language":"de","meaning":"Transformer substation or switchgear station serving as a grid connection node."},{"term":"Schaltfeldverfügbarkeit","language":"de","meaning":"Availability of physical switchgear bays at an EHV/HV substation, published by 50Hertz and Amprion."},{"term":"Online-Netzauskunft / Mittelspannungsauskunft / SNAP","language":"de","meaning":"Interactive DSO self-service pre-check portals returning an indicative MV connection point for a queried coordinate and MW."},{"term":"Reifegradverfahren","language":"de","meaning":"Joint maturity-based ('first ready, first served') allocation procedure introduced on 1 April 2026 by all 4 German TSOs for large loads and battery storage."},{"term":"Zuteilungsverfahren / Repartierungsverfahren","language":"de","meaning":"Criteria-based or pro-rata capacity allocation procedures used by congested German DSOs for large connection requests."},{"term":"Übertragungsnetzbetreiber (ÜNB) / Verteilernetzbetreiber (VNB)","language":"de","meaning":"Transmission system operators (4 in Germany) and distribution system operators (~865 in electricity)."}],"provenance":{"pass_count":1,"models":["Gemini 4 Carbon"],"minutes_estimate":40,"pages_opened":86,"passes":[{"pass":1,"date":"2026-11-26","model":"Gemini 4 Carbon"}],"note":"Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed."},"card_url":"https://georutter.org/v1/de/grid-hosting-capacity.json","detail_url":"https://georutter.org/v1/de/grid-hosting-capacity/detail.json","html_url":"https://georutter.org/de/grid-hosting-capacity/","country_url":"https://georutter.org/v1/countries/de.json"}