{"schema_version":"1.0","country":"fr","country_name":"France","topic":"battery-storage-in-permitting","question":"Where can I get a list of stand-alone battery storage (BESS) projects currently in permitting in France, with location, power (MW), developer, permitting stage and date?","territory":"fr","territory_level":"country","parent_url":null,"published_on":"2026-11-19","research_reviewed_on":"2026-11-15","access_checked_on":null,"answer":{"official_data":"partial","non_official_data":"partial","summary":"No unified French registry tracks all stand-alone BESS currently in permitting. Nationally, the Ministry portal NOVAE exposes an open API and Excel export for R.122-2 environmental screening (cas par cas) and opinions, including open cases, though MW and developer appear only inside attached PDFs and smaller sites below thresholds are omitted. Major full-EIA consultations appear on projets-environnement.gouv.fr. Most BESS (>600 kW Li-ion) file an ICPE 2925-2 Déclaration whose receipts are scattered across 101 departmental Préfectures, while pending building permits are excluded from Sitadel (CRPA L.311-2).","main_caveats":["NOVAE inProgress=true omits 'À COMPLÉTER' dossiers (missing open standalone BESS 005778/KK P in Œuilly, 5 MW); query without inProgress or filter documentStatus manually.","Most 1-20+ MW standalone BESS require only ICPE 2925-2 Déclaration (>600 kW) plus Permis de construire/DP, so projects below R.122-2 thresholds never appear in NOVAE unless filed voluntarily.","Sitadel excludes all pending building permits ('en cours d'instruction') under CRPA art. L.311-2, omits permits without floor area, and strips project descriptions.","Géorisques ICPE covers only active/ended Autorisation and Enregistrement facilities, excluding 2925-2 Déclaration-only BESS and pending applications.","Grid queue datasets (ODRÉ, Enedis data-fair, EDF Corse-Outremer, RTE Cartostock, Caparéseau) publish substation MW headroom or regional totals, never named permitting projects."],"confidence":"high","confidence_reason":"Verified across Ministry portals, live NOVAE/projets-environnement/ODRÉ/Enedis/EDF APIs, Géorisques/Sitadel docs and files, DDT77 BESS guide, 4 Préfecture 2925-2 pages/PDFs and commercial pages.","attributes":[{"attribute":"location","covered":"partial","source_ids":["s001","s002","s003"],"note":"NOVAE API/XLSX gives commune/dept/region (Cerfa PDFs may give DMS/Lambert coords); Préfecture 2925-2 PDFs give lieu-dit and Lambert-93 X/Y; source 2 has GeoJSON points.","gap":"not_published","gap_note":"NOVAE JSON/Excel omits coordinates; municipal pending building permit locations are not published in open structured datasets."},{"attribute":"power_mw","covered":"partial","source_ids":["s001","s003"],"note":"Absent from NOVAE JSON/Excel and Sitadel; available inside NOVAE Cerfa/decision PDFs (MW/MWh) and Préfecture 2925-2 PDFs (max charging kW, often MWh).","gap":"not_published","gap_note":"Neither NOVAE metadata nor Sitadel nor Géorisques exposes structured MW for permitting-stage BESS; requires reading PDFs or paid commercial trackers."},{"attribute":"developer","covered":"partial","source_ids":["s001","s002","s003"],"note":"Omitted from NOVAE API/XLSX; stated inside NOVAE Cerfa/decision PDFs, Préfecture 2925-2 PDFs (Raison sociale + SIRET), and full-EIA inquiry files.","gap":"not_published","gap_note":"Structured national open datasets do not expose developer/applicant names for pending PC or R.122-2 dossiers without downloading PDFs."},{"attribute":"permitting_stage","covered":"partial","source_ids":["s001","s002","s003"],"note":"NOVAE tracks R.122-2 stage (En cours d'instruction, À COMPLÉTER, Dossier Clos); source 2 tracks EIA consultations; source 3 shows ICPE 2925-2 filing (15-day rule).","gap":"not_published","gap_note":"There is no cross-procedure tracker linking R.122-2 screening, ICPE 2925-2 declaration, grid queue, and pending DDT/Préfet building-permit stage."},{"attribute":"stage_date","covered":"partial","source_ids":["s001","s002","s003"],"note":"NOVAE provides publishedDate, updatedDate and submission date; Préfecture 2925-2 PDFs carry exact filing timestamp; source 2 provides consultation start/end dates.","gap":"not_published","gap_note":"Pending urbanism application filing/instruction dates remain unpublished in Sitadel and offline at town halls/DDTs."}]},"sources":[{"source_id":"s001","name":"NOVAE — Portail de l'évaluation environnementale (Cas par cas et avis Ae)","publisher":"Ministère de la Transition écologique (CGDD / DREAL / IGEDD)","official":true,"landing_url":"https://evaluation-environnementale.ecologie.gouv.fr/","data_url":"https://gatew-evaluation-environnementale.developpement-durable.gouv.fr/api/PublishedDocument/Get","access":"api","format":"JSON, XLSX, PDF","license":"Licence Ouverte Etalab 2.0","language":"fr","has_coordinates":false,"location_precision":"municipality","publisher_type":"national_government","adds":"Central structured JSON API, Excel export and PDF attachments across all French regions for R.122-2 screening and environmental opinions, including open dossiers.","first_seen_pass":1,"rank":1,"summary":"NOVAE — Portail de l'évaluation environnementale (Cas par cas et avis Ae)","coverage_note":"France (métropole et DROM — 13 regions observed in standalone BESS subset including Martinique)","data_date":"Continuous live portal since 2025-09-03; API snapshot tested 2026-11-15 (latest publishedDate 2026-11-12)","caveats":["Consult the main caveats and the complete reading traps and access evidence in the detail."],"coverage":{"geographic":"France (métropole et DROM — 13 regions observed in standalone BESS subset including Martinique)"},"fine_print":{"unit":{"value":"Environmental assessment or cas-par-cas dossier per project/plan","quote":"Demande d’examen au cas par cas préalable à la réalisation d’une étude d’impact pour un projet","url":"https://gatew-evaluation-environnementale.developpement-durable.gouv.fr/api/PublishedDocument/Get?start=0&length=10&descending_order_id=true&inProgress=true","attempts":[]},"inclusion_rule":{"value":"Mandatory exclusive filing via NOVAE since 2025-09-03 for project/plan R.122-2 cas par cas and Ae opinions","quote":"Depuis le 3 septembre 2025, le dépôt des demandes d’examen au cas par cas ou des saisines de l’Autorité environnementale relatives à un projet, un plan, un schéma ou un programme se fera exclusivement par le portail de l’évaluation environnementale, appelé NOVAe","url":"https://www.nouvelle-aquitaine.developpement-durable.gouv.fr/autorite-environnementale-et-evaluation-r14.html","attempts":[]},"reference_date":{"value":"Continuous live portal since 2025-09-03; API snapshot tested 2026-11-15 (latest publishedDate 2026-11-12)","quote":"Depuis le 3 septembre 2025, le dépôt des demandes d’examen au cas par cas ou des saisines de l’Autorité environnementale relatives à un projet, un plan, un schéma ou un programme se fera exclusivement par le portail de l’évaluation environnementale, appelé NOVAe","url":"https://www.nouvelle-aquitaine.developpement-durable.gouv.fr/autorite-environnementale-et-evaluation-r14.html","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":["Inspected https://evaluation-environnementale.ecologie.gouv.fr/assets/i18n/fr.json and Angular main/chunk bundles: no update frequency SLA documented in portal UI text.","Checked DREAL Nouvelle-Aquitaine and DREAL Centre-Val de Loire NOVAE pages (https://www.centre-val-de-loire.developpement-durable.gouv.fr/important-a-partir-du-3-septembre-2025-nouveau-a5013.html): describes live workflow since 2025-09-03 without stated refresh cadence."]},"exclusions":{"value":"Excludes ICPE Enregistrement and ESSOC cas par cas, plus smaller BESS below R.122-2 thresholds unless voluntarily submitted under R.122-2-1 III","quote":"Attention, cette nouvelle procédure n’est pas valable pour les demandes d’examen au cas par cas « enregistrement ICPE » et pour les cas par cas « ESSOC » pour lesquelles les saisines restent inchangées.","url":"https://www.nouvelle-aquitaine.developpement-durable.gouv.fr/autorite-environnementale-et-evaluation-r14.html","attempts":[]}},"key_fields":[{"field":"id","meaning":"Internal record sequence ID used by PublishedDocument/Get"},{"field":"documentId","meaning":"Document identifier passed to PublishedDocument/GetByDocumentId to retrieve attachment IDs"},{"field":"referenceNumber","meaning":"Official dossier reference (e.g. 021061/KK P, 012142/A P, 005778/KK P)"},{"field":"projectTitle","meaning":"Project title (e.g. 'Projet de stockage d’énergie par batterie sur la commune de Batilly-en-Gâtinais (45340)')"},{"field":"documentStatus","meaning":"Workflow stage: 'En cours d'instruction', 'À COMPLÉTER', 'Recevable', 'Validé Niveau I', 'En Cours', 'Dossier Clos'"},{"field":"categoryName","meaning":"Procedure type (project cas par cas, Ae opinion, etc.)"},{"field":"authority","meaning":"Competent environmental authority (e.g. Préfet de région)"},{"field":"municipality","meaning":"Commune and department code (e.g. 'Batilly-en-Gâtinais (45)')"},{"field":"department","meaning":"Department code and name (e.g. '45-Loiret')"},{"field":"region","meaning":"Region name"},{"field":"publishedDate","meaning":"ISO timestamp of publication on the portal"},{"field":"publishedAttachmentIds","meaning":"Comma-separated attachment IDs downloadable via /api/Attachment/PublishedDownload?ctsFileId={id}"}],"how_to_use":{"example_request":"https://gatew-evaluation-environnementale.developpement-durable.gouv.fr/api/PublishedDocument/Get?start=0&length=100&descending_order_id=true&searchAll=batterie","example_result":"{\"totalCount\":68,\"count\":68,\"data\":[{\"id\":11270,\"documentId\":26369,\"publishedAttachmentIds\":\"458012\",\"projectTitle\":\" Projet de stockage d’énergie par batterie sur la commune de Batilly-en-Gâtinais (45340)\",\"municipality\":\"Batilly-en-Gâtinais (45)\",\"department\":\"45-Loiret\",\"region\":\"Centre-Val de Loire\",\"referenceNumber\":\"021061/KK P\",\"documentStatus\":\"Dossier Clos\",\"publishedDate\":\"2026-10-08T10:28:34.11413\"}]}","steps":["Query GET /api/PublishedDocument/Get with searchAll keywords ('batterie', 'batteries', 'stockage', 'BESS') using length=250 and start=0,250,... without inProgress=true so 'À COMPLÉTER' dossiers are included (or export Excel via /api/PublishedDocument/ExportToExcel?start=0&searchAll=batterie).","Deduplicate by id and filter projectTitle to separate stand-alone BESS from co-located solar PV+battery, hydro STEP, hydrogen, gigafactory, recycling and municipal name matches ('Bessin', 'Bessée').","Inspect documentStatus: 'En cours d'instruction' and 'À COMPLÉTER' are open in NOVAE; recent 'Dossier Clos' cas par cas decisions (within ~12 months) typically denote projects now moving into urbanism (PC) and ICPE permitting.","For each kept project, call /api/PublishedDocument/GetByDocumentId?documentId={documentId} and download Cerfa/decision PDFs via /api/Attachment/PublishedDownload?ctsFileId={id} to extract MW, MWh, developer name/SIRET and DMS/Lambert coordinates (e.g. ctsFileId=116049 for Œuilly, ctsFileId=458012 for Batilly-en-Gâtinais)."],"reading_traps":["inProgress=true returns 373 records ('En cours d'instruction', 'Recevable', 'Validé Niveau I', 'En Cours') but SILENTLY EXCLUDES 'À COMPLÉTER', omitting open stand-alone BESS 2080/10805 (005778/KK P, Œuilly 5 MW).","In PublishedDocument/Get?searchAll=BESS, full-text matches town names containing 'Bess' (e.g. Cricqueville-en-Bessin, L'Argentière-la-Bessée ALDI store), inflating hits unless titles are filtered.","JSON and ExportToExcel omit MW/MWh, developer and coordinates completely; those fields reside only inside attached Cerfa or signed decision PDFs.","HEAD requests to PublishedDocument/Get return HTTP 405 Method Not Allowed; always use HTTP GET.","71 of 73 non-PV/non-factory standalone BESS-matched dossiers in NOVAE show documentStatus='Dossier Clos' because environmental cas-par-cas concludes in ~35 days prior to building permit/ICPE construction permitting."]},"test":{"tested_on":"2026-11-15","method":"api_query","http_status":200,"content_type":"application/json; charset=utf-8","size_bytes":null,"records_total":12092,"records_for_country":12092,"problems":["HEAD returns 405 Method Not Allowed; ExportToExcel fails silently or returns subsets if start/filters vary; inProgress=true excludes 'À COMPLÉTER'; MW and developer missing from structured fields."]},"evidence":[{"claim":"Le footer NOVAE indique que les contenus du site sont proposés sous licence Etalab 2.0 (conforme aux mentions légales ministérielles).","url":"https://www.ecologie.gouv.fr/mentions-legales","quote":"Sauf mention explicite de propriété intellectuelle détenue par des tiers, les contenus de ce site sont proposés sous licence ouverte Etalab 2.0."},{"claim":"Un dossier réel de BESS autonome dans NOVAE contient puissance (108 MW / 72 MVA / 432 MWh), développeur et date dans sa décision PDF.","url":"https://gatew-evaluation-environnementale.developpement-durable.gouv.fr/api/Attachment/PublishedDownload?ctsFileId=458012","quote":"Projet de stockage d’énergie par batterie sur la commune de Batilly-en-Gâtinais (45340)"},{"claim":"Les projets soumis au cas par cas sont déposés exclusivement sur NOVAE depuis le 3 septembre 2025.","url":"https://www.nouvelle-aquitaine.developpement-durable.gouv.fr/autorite-environnementale-et-evaluation-r14.html","quote":"Depuis le 3 septembre 2025, le dépôt des demandes d’examen au cas par cas ou des saisines de l’Autorité environnementale relatives à un projet, un plan, un schéma ou un programme se fera exclusivement par le portail de l’évaluation environnementale, appelé NOVAe"}],"members":[],"members_summary":null},{"source_id":"s002","name":"projets-environnement.gouv.fr — Projets soumis à étude d'impact (diffusion)","publisher":"Ministère de la Transition écologique (CGDD / GarAnce)","official":true,"landing_url":"https://www.projets-environnement.gouv.fr/pages/home/","data_url":"https://www.projets-environnement.gouv.fr/api/explore/v2.1/catalog/datasets/projets-environnement-diffusion/records","access":"api","format":"JSON, CSV (Opendatasoft v2.1)","license":"Licence Ouverte (Etalab)","language":"fr","has_coordinates":true,"location_precision":"exact","publisher_type":"national_government","adds":"Provides GeoJSON site coordinates, public consultation status (vp_status='ouvert' for ongoing enquête publique / PPVE) and inquiry links/PDFs for major EIA / autorisation environnementale projects.","first_seen_pass":1,"rank":2,"summary":"projets-environnement.gouv.fr — Projets soumis à étude d'impact (diffusion)","coverage_note":"France (national)","data_date":null,"caveats":["Consult the main caveats and the complete reading traps and access evidence in the detail."],"coverage":{"geographic":"France (national)"},"fine_print":{"unit":null,"inclusion_rule":null,"reference_date":null,"update_frequency":null,"exclusions":null},"key_fields":[{"field":"dc_title","meaning":"Project title"},{"field":"descriptif_du_projet","meaning":"Project summary description"},{"field":"dc_subject_category","meaning":"R.122-2 nomenclature rubric (e.g. '30. Installations photovoltaïques...')"},{"field":"vp_status","meaning":"Public consultation status ('ouvert', 'clos', 'non defini')"},{"field":"dc_type","meaning":"Procedure type (Permis de construire, Autorisation environnementale, etc.)"},{"field":"dc_date","meaning":"Record / publication ISO date"},{"field":"localisation","meaning":"GeoJSON Point geometry [lon, lat]"},{"field":"source","meaning":"Origin system ('Portail de l'évaluation environnementale', GarAnce, etc.)"},{"field":"adresse_url","meaning":"External URL to consultation page or inquiry PDF when provided"}],"how_to_use":{"example_request":"https://www.projets-environnement.gouv.fr/api/explore/v2.1/catalog/datasets/projets-environnement-diffusion/records?limit=5&order_by=dc_date%20desc&where=dc_title%20like%20%22%25batterie%25%22","example_result":"{\"total_count\":3,\"results\":[{\"dc_title\":\"Centrale solaire et stockage par batterie\",\"descriptif_du_projet\":\"Parc photovoltaïque et stockage par batteries  à Neulliac (56)\",\"vp_status\":null,\"dc_type\":[\"Permis de construire\"],\"dc_date\":\"2026-08-31T10:40:23+00:00\",\"localisation\":{\"type\":\"Feature\",\"geometry\":{\"coordinates\":[-3.001184,48.131144],\"type\":\"Point\"}}}]}","steps":["Query the Opendatasoft v2.1 endpoint filtering dc_title and descriptif_du_projet rather than generic search() full-text.","Filter vp_status='ouvert' to capture projects currently in public consultation (enquête publique or PPVE).","Extract GeoJSON coordinates from localisation and check adresse_url / sicodei PDF links for MW and developer (often null in structured fields)."],"reading_traps":["Dataset metadata field metas.default.modified reports '2018-03-22T13:54:46+00:00' even though live records reach 2026-11-13.","ODSQL full-text search('batterie') matches inside attachment text and unrelated projects; filter specifically on dc_title and descriptif_du_projet.","Contains only projects subject to full environmental impact assessment (étude d'impact / AENV): 0 pure standalone BESS currently have vp_status='ouvert'; the 3 battery-titled matches are hybrid solar PV+BESS.","vp_creator_corporatename (developer) and adresse_url are frequently null in exported records."]},"test":{"tested_on":"2026-11-15","method":"api_query","http_status":200,"content_type":"application/json; charset=utf-8","size_bytes":null,"records_total":6440,"records_for_country":6440,"problems":["Excludes projects not subject to full EIA; developer and MW are mostly missing from structured columns; stale dataset metadata modified date (2018-03-22)."]},"evidence":[{"claim":"Le catalogue projets-environnement-diffusion contient 6 440 dossiers sous Licence Ouverte Etalab avec coordonnées GeoJSON.","url":"https://www.projets-environnement.gouv.fr/pages/home/","quote":"Consultation des projets soumis à étude d'impact"}],"members":[],"members_summary":null},{"source_id":"s003","name":"Déclarations ICPE 2925-2 (Preuves de dépôt) — Préfectures départementales","publisher":"Préfectures de département (101 préfectures)","official":true,"landing_url":"https://entreprendre.service-public.gouv.fr/vosdroits/F33414","data_url":null,"access":"pdf","format":"PDF, HTML","license":"Licence Ouverte Etalab 2.0 (gouv.fr default)","language":"fr","has_coordinates":true,"location_precision":"exact","publisher_type":"regional_government","adds":"Covers lithium-ion BESS >600 kW under ICPE Déclaration (rubrique 2925-2) that skip NOVAE and Sitadel, giving developer/SIRET, max kW, MWh, exact Lambert-93 coordinates and filing timestamp.","first_seen_pass":1,"rank":3,"summary":"Déclarations ICPE 2925-2 (Preuves de dépôt) — Préfectures départementales","coverage_note":"Decentralized across all 101 French departments (4 preuves/index + 1 guide sampled)","data_date":null,"caveats":["Consult the main caveats and the complete reading traps and access evidence in the detail."],"coverage":{"geographic":"Decentralized across all 101 French departments (4 preuves/index + 1 guide sampled)"},"fine_print":{"unit":null,"inclusion_rule":null,"reference_date":null,"update_frequency":null,"exclusions":null},"key_fields":[{"field":"Référence du dossier","meaning":"Teledeclaration receipt reference (e.g. A-6-6HRCTIZPA)"},{"field":"Date de transmission","meaning":"Exact submission date and time triggering the 15-day standstill (R.512-48)"},{"field":"Raison sociale / N° SIRET","meaning":"Operator / project SPV legal name and 14-digit SIRET"},{"field":"Localisation (X, Y Lambert 93)","meaning":"Address/lieu-dit and Lambert-93 metric coordinates (EPSG:2154)"},{"field":"Tableau des rubriques (2925-2)","meaning":"ICPE sub-rubric, maximum charging power (kW), regime D and optional MWh"},{"field":"Permis de construire (OUI/NON)","meaning":"Indicates whether an accompanying urbanism building permit is required"}],"how_to_use":{"example_request":"curl -4sSL -o preuve_verrieres.pdf https://www.vienne.gouv.fr/contenu/telechargement/51156/314801/file/fichierAccuseReception_stockage_d_energie_par_batteries_lithium_verrieres.pdf && pdftotext preuve_verrieres.pdf -","example_result":"Vous venez de déposer un dossier de demande de déclaration ICPE concernant le projet Stockage d'énergie par batterie lithium sur la commune principale de l'AIOT LD LA BARRIERE 86410 VERRIERES... transmise le 06/11/2026... Raison sociale PHOTOSOL DEVELOPPEMENT... X : 514667 Y : 6590260 Projection : Lambert 93... 2925-2 Puissance maximale 20000 kW D 50 MWh","steps":["Search site:<departement>.gouv.fr for 'preuve de dépôt' '2925-2' or 'stockage' 'batterie' across departmental Préfectures.","Download each fichierAccuseReception*.pdf (use OCR if scanned like Aude APC).","Extract reference, filing date, Raison sociale + SIRET, X/Y Lambert-93 coordinates (convert EPSG:2154 to WGS84), 2925-2 kW, MWh and PC OUI/NON flag."],"reading_traps":["No central index links all 101 Préfecture websites; some departments (e.g. Meuse) use generic filenames ('fichierAccuseReception.pdf') without project names in titles.","Filing a 2925-2 declaration requires only a 15-day standstill before operation (R.512-48), but larger BESS (Permis de construire = OUI) cannot operate until PC and grid connection finish.","Some departmental orders (e.g. Aude APC 2025-05-09) are image-only scanned PDFs requiring OCR.","Under Art. R.512-49, proofs remain online for at least 3 years without indicating whether construction or commissioning later completed; cross-check ODRÉ En service."]},"test":{"tested_on":"2026-11-15","method":"download","http_status":200,"content_type":"application/pdf","size_bytes":null,"records_total":null,"records_for_country":null,"problems":["Decentralized across 101 Préfectures with inconsistent navigation and occasional scanned PDFs; Python urllib TLS failed on some gouv.fr hosts whereas curl -4 succeeded."]},"evidence":[{"claim":"Les batteries Li-ion > 600 kW relèvent uniquement de la déclaration ICPE 2925-2 dès le 1er conteneur, avec PC instruit par la DDT et guichet unique communal.","url":"https://www.seine-et-marne.gouv.fr/contenu/telechargement/68608/563235/file/Annexe%20_aidem%C3%A9moire_batteries%20de%20stockage.pdf","quote":"Les installations de stockage d’électricité par batteries lithium-ion de plus de 600 kW sont soumis uniquement au régime de la déclaration ICPE au titre de la rubrique 2925-2"},{"claim":"Chaque preuve de dépôt 2925-2 mentionne la raison sociale, la puissance en kW, la date et les coordonnées Lambert 93.","url":"https://www.vienne.gouv.fr/contenu/telechargement/51156/314801/file/fichierAccuseReception_stockage_d_energie_par_batteries_lithium_verrieres.pdf","quote":"L’installation ne peut ni être mise en service, ni exploitée dans les 15 jours suivant la délivrance de la preuve de dépôt de la déclaration initiale (R. 512-48 alinea 2 du code de l'environnement)"}],"members":[{"name":"Préfecture de la Vienne (86)","landing_url":"https://www.vienne.gouv.fr/Actions-de-l-Etat/Environnement-risques-naturels-et-technologiques/Installations-classees/Industrielles/Stockage-d-energie-par-batterie-La-Barriere-Verrieres","data_url":"https://www.vienne.gouv.fr/contenu/telechargement/51156/314801/file/fichierAccuseReception_stockage_d_energie_par_batteries_lithium_verrieres.pdf","access":"pdf","tested":true,"data_found":null,"note":"Tested 2026-11-06 Preuve de dépôt PDF (A-6-6HRCTIZPA): PHOTOSOL DEVELOPPEMENT, 20000 kW / 50 MWh, Verrières (86), X:514667 Y:6590260 Lambert-93, PC=OUI."},{"name":"Préfecture de Loir-et-Cher (41)","landing_url":"https://www.loir-et-cher.gouv.fr/Publications/Publications-legales/Installations-classees/Installations-relevant-du-regime-de-la-declaration2/CELLETTES-NWJ-MET-3","data_url":"https://www.loir-et-cher.gouv.fr/contenu/telechargement/37516/289624/file/fichierAccuseReception.pdf","access":"pdf","tested":true,"data_found":null,"note":"Tested 2025-05-07 Preuve de dépôt PDF (A-5-SOUV5B2K8): NWJ MET 3, 1250 kW, Cellettes (41), X:579742 Y:6714412 Lambert-93, PC=NON."},{"name":"Préfecture de l'Aude (11)","landing_url":"https://www.aude.gouv.fr/Actions-de-l-Etat/Environnement-eau-foret-chasse-risques-naturels-technologiques/Plans-et-projets-d-amenagement-susceptibles-d-impacter-l-environnement/Installations-classees-pour-la-protection-de-l-Environnement-ICPE/Preuve-de-depot-de-la-declaration/Annee-2025/AIOT-N-0100037758-Societe-AFR-EDT-3-a-Castelnau-d-Aude-Arrete-prefectoral-du-9-mai-2025","data_url":"https://www.aude.gouv.fr/contenu/telechargement/33063/227613/file/APC_2925D_AFREDT3_CastelnauDAUDE_LesGraves_sign%C3%A92025-05-09.pdf","access":"pdf","tested":true,"data_found":null,"note":"Scanned PDF (no embedded text layer) for 2925-D supplementary prefectural order (AFR EDT 3, Castelnau-d'Aude)."},{"name":"Préfecture de la Meuse (55)","landing_url":"https://www.meuse.gouv.fr/Actions-de-l-Etat/Environnement/ICPE/Declarations-ICPE-procedure-et-formulaires/Preuves-de-depot-declarations-initiales","data_url":null,"access":"pdf","tested":true,"data_found":null,"note":"Departmental index listing generic fichierAccuseReception*.pdf links without project titles in filenames."},{"name":"Préfecture de Seine-et-Marne (77)","landing_url":"https://www.seine-et-marne.gouv.fr/Actions-de-l-Etat/Climat-Energies/Transition-energetique-et-developpement-des-ENR/Developpement-du-stockage-d-electricite-en-Seine-et-Marne","data_url":"https://www.seine-et-marne.gouv.fr/contenu/telechargement/68608/563235/file/Annexe%20_aidem%C3%A9moire_batteries%20de%20stockage.pdf","access":"pdf","tested":true,"data_found":null,"note":"Official DDT 77 BESS permitting guide (2025-09-01) detailing DP/PC, 2925-2 declaration, cas par cas, CDPENAF and R.423-3 guichet unique."}],"members_summary":{"total":null,"listed":5,"tested":5,"data_found":0,"scope_note":"Inherited members; data findings were not reclassified during this structural migration. Consult each member note.","pattern":null},"member_scope":{"total":null,"note":"Inherited members; data findings were not reclassified during this structural migration. Consult each member note.","pattern":null}},{"source_id":"s004","name":"Modo Energy — France Battery Buildout & Terminal","publisher":"Modo Energy","official":false,"landing_url":"https://modoenergy.com/research/en/france-battery-buildout-bess-construction-energy-storage-november-2025","data_url":null,"access":"paid","format":"Web portal / reports (paid)","license":"Proprietary commercial license","language":"en","has_coordinates":false,"location_precision":"municipality","publisher_type":"commercial","adds":"Commercial asset and development pipeline tracking utility-scale (>1 MW) and distributed French BESS projects, MW/MWh and developers behind a paid subscription.","first_seen_pass":1,"rank":4,"coverage":{"geographic":"France"},"fine_print":{"unit":null,"inclusion_rule":null,"reference_date":null,"update_frequency":null,"exclusions":null},"key_fields":[],"how_to_use":{"example_request":null,"example_result":null,"steps":["Requires an institutional Modo Energy Terminal subscription to inspect individual pipeline and construction assets in France."],"reading_traps":["Commercial intelligence dataset focused on grid-scale buildout and revenue benchmarking; not an exhaustive real-time registry of all early-stage municipal permitting filings."]},"test":{"tested_on":"2026-11-15","method":"page_only","http_status":200,"content_type":"text/html; charset=utf-8","size_bytes":null,"records_total":null,"records_for_country":null,"problems":["Project database and full research report require paid commercial subscription."]},"evidence":[{"claim":"Modo Energy tracks the operational and under-construction French BESS fleet by developer, MW and MWh (paid platform).","url":"https://modoenergy.com/research/en/france-battery-buildout-bess-construction-energy-storage-november-2025","quote":"Large-scale projects are emerging. Harmony Energy’s 100 MW / 200 MWh battery is operational, and large builds are underway at Cernay (TAG Energy, 240 MW / 480 MWh) and Saleux (Kallista Energy, 120 MW / 240 MWh)."}],"members":[],"members_summary":null},{"source_id":"s005","name":"Wood Mackenzie — Energy Storage Data Hub & Project Tracker","publisher":"Wood Mackenzie","official":false,"landing_url":"https://www.woodmac.com/industry/power-and-renewables/energy-storage-data-hub/","data_url":null,"access":"paid","format":"Enterprise Data Hub / CSV / portal (paid)","license":"Proprietary commercial license","language":"en","has_coordinates":false,"location_precision":null,"publisher_type":"commercial","adds":"Global commercial facility-level storage project tracker covering France announced and under-construction FTM/BTM assets under enterprise subscription (and feeding EC JRC aggregate inventory).","first_seen_pass":1,"rank":5,"coverage":{"geographic":"Global including France"},"fine_print":{"unit":null,"inclusion_rule":null,"reference_date":null,"update_frequency":null,"exclusions":null},"key_fields":[],"how_to_use":{"example_request":null,"example_result":null,"steps":["Accessible only with a Wood Mackenzie Energy Storage Service / Lens enterprise license."],"reading_traps":["Commercial subscription tracker; project-level permitting granularity depends on analyst updates and developer disclosures."]},"test":{"tested_on":"2026-11-15","method":"page_only","http_status":200,"content_type":"text/html; charset=utf-8","size_bytes":null,"records_total":null,"records_for_country":null,"problems":["Requires paid enterprise subscription."]},"evidence":[{"claim":"Wood Mackenzie provides facility-level energy storage tracking behind an enterprise subscription and supplies commercial data to the EC JRC inventory.","url":"https://ses.jrc.ec.europa.eu/storage-inventory","quote":"The European Energy Inventory Storage dataset is mainly based on public data and data from Wood Mackenzie."}],"members":[],"members_summary":null}],"sector":{"regulator":{"name":"Ministère de la Transition écologique (CGDD / DGPR / DREAL / Préfectures) et Commission de régulation de l'énergie (CRE)","url":"https://www.ecologie.gouv.fr/politiques-publiques/installations-classees-protection-lenvironnement"},"operators":{"structure":"many","note":"BESS projects are developed by many private developers and permitted across 101 departmental Préfectures/DDTs (ICPE 2925-2 and State-level building permits R.422-2), 18 regional DREALs/DRIEAT (R.122-2 via NOVAE) and communes (guichet unique R.423-3); grids are operated by RTE, Enedis, EDF SEI and local ELD.","census_url":null},"publication_obligation":{"exists":"yes","norm":"Code de l'environnement art. R.512-49 (publication 3 ans sur le site de la préfecture des preuves de dépôt ICPE déclaration), art. R.122-3-1 / R.181-36 (portail évaluation environnementale & consultation du public), et Code de l'urbanisme art. R.423-6 (affichage en mairie).","url":"https://www.ecologie.gouv.fr/politiques-publiques/lautorisation-environnementale","what_must_be_published":"Preuves de dépôt ICPE 2925-2 (avec raison sociale, SIRET, puissance kW, localisation Lambert-93, date), dossiers/décisions d'examen au cas par cas, avis d'enquête publique / PPVE, et affichage physique en mairie des demandes de permis de construire.","frequency":"Continuous / upon filing or decision (ICPE receipts published for at least 3 years; 15-day standstill under R.512-48)."},"consolidated_republication":{"found":"partial","note":"Environmental assessment screening (NOVAE) and EIA consultations (projets-environnement) are consolidated nationally, whereas ICPE 2925-2 receipts remain fragmented across 101 departmental Préfecture websites and pending PC remain unpublished.","checked_pages":[{"organization":"Ministère de la Transition écologique (NOVAE)","url":"https://evaluation-environnementale.ecologie.gouv.fr/","saw":"National portal consolidating R.122-2 cas par cas and Ae opinions since 2025-09-03 via public REST API and Excel export (12,092 records)."},{"organization":"Ministère de la Transition écologique (projets-environnement.gouv.fr)","url":"https://www.projets-environnement.gouv.fr/api/explore/v2.1/catalog/datasets/projets-environnement-diffusion","saw":"National Opendatasoft v2.1 API aggregating 6,440 projects undergoing EIA public consultations / GarAnce."},{"organization":"DREAL Nouvelle-Aquitaine","url":"https://www.nouvelle-aquitaine.developpement-durable.gouv.fr/autorite-environnementale-et-evaluation-r14.html","saw":"Confirms mandatory exclusive filing on NOVAe since 2025-09-03, excluding ICPE Enregistrement and ESSOC cas par cas."},{"organization":"BRGM / Ministère (Géorisques)","url":"https://www.georisques.gouv.fr/donnees/bases-de-donnees/installations-industrielles","saw":"Consolidates only Autorisation and Enregistrement ICPE facilities already in operation or ending, excluding 2925-2 Déclarations and pending cases."},{"organization":"SDES / Ministère (Sitadel)","url":"https://data.statistiques.developpement-durable.gouv.fr/dido/api/v1/datasets/6513f0189d7d312c80ec5b5b","saw":"Consolidates building permits nationally but explicitly excludes pending applications (en cours d'instruction) under CRPA art. L.311-2."}]}},"national_registry":{"exists":"no_evidence_found","note":"No unified national registry lists all stand-alone BESS projects in permitting in France. NOVAE covers only projects triggering R.122-2 screening/opinions; Géorisques excludes Declaration-only (2925-2) and pending ICPE; Sitadel excludes pending PC (CRPA L.311-2); ODRÉ lists only commissioned assets (En service); grid queues publish aggregates only.","checked_pages":[{"organization":"Ministère de la Transition écologique (NOVAE / ICPE / Autorisation env.)","url":"https://www.ecologie.gouv.fr/politiques-publiques/installations-classees-protection-lenvironnement","saw":"Explains Déclaration (15-day rule), Enregistrement, and Autorisation regimes without any central register of pending Declarations or standalone BESS."},{"organization":"Commission de régulation de l'énergie (CRE)","url":"https://www.cre.fr/actualites/toute-lactualite/la-cre-consulte-les-acteurs-sur-la-procedure-de-raccordement-des-installations-de-stockage-au-reseau-public-de-transport-delectricite-dans-les-zones-a-gabarit.html","saw":"Addresses storage connection demand rules in RTE zones à gabarit (1 GW), publishes no project-level BESS queue."},{"organization":"RTE (Réseau de Transport d'Électricité)","url":"https://analysesetdonnees.rte-france.com/reseaux/cartostock","saw":"Publishes Cartostock substation hosting capacity (MW) only; no named BESS project permitting or connection queue."},{"organization":"ODRÉ (Open Data Réseaux Énergies)","url":"https://odre.opendatasoft.com/api/explore/v2.1/catalog/datasets/registre-national-installation-production-stockage-electricite-agrege","saw":"National generation & storage registry holds 938 battery rows, all 100% commissioned (regime='En service')."},{"organization":"SDES (Statistiques Développement Durable — Sitadel)","url":"https://data.statistiques.developpement-durable.gouv.fr/dido/api/files/52ce326b-45b2-42ce-a2e7-4a60554ef559","saw":"Official Sitadel note states pending applications ('en cours d'instruction') cannot be released under CRPA art. L.311-2."},{"organization":"BRGM / Géorisques","url":"https://www.georisques.gouv.fr/donnees/bases-de-donnees/installations-industrielles","saw":"Confirms national ICPE open database excludes Declaration-regime facilities (such as 2925-2) and pending filings."},{"organization":"Enedis & EDF SEI (Open Data)","url":"https://opendata.edf.fr/api/explore/v2.1/catalog/datasets/file-dattente-producteur/records?limit=100","saw":"Both Enedis data-fair (4,745 rows) and EDF Corse-Outremer (75 rows) aggregate queue counts and MW by department/territory and filiere only."}]},"if_unstructured":{"summary":null,"recipe":["Pull all keyword matches ('batterie', 'batteries', 'stockage', 'BESS') from NOVAE /api/PublishedDocument/Get without inProgress=true and filter titles for standalone BESS; download Cerfa and decision PDFs via /api/Attachment/PublishedDownload?ctsFileId={id} to extract MW, MWh, developer/SIRET and coordinates.","Query projets-environnement-diffusion API (vp_status='ouvert' and full dataset) for battery/storage EIA consultations to capture any full-EIA BESS with GeoJSON points.","Crawl or query departmental Préfecture websites (<dept>.gouv.fr) for 'preuve de dépôt' '2925-2' and 'stockage' 'batterie' PDFs (running OCR on image PDFs) to capture sub-threshold BESS (1-20+ MW) that bypassed NOVAE.","Deduplicate by commune/SIRET/project name and subtract projects already commissioned in ODRÉ Registre national (regime='En service') or granted/closed in Sitadel."],"location_method":"Extract Lambert-93 (EPSG:2154) X/Y coordinates directly from ICPE 2925-2 proof-of-filing PDFs and convert to WGS84, or extract DMS/Lambert coordinates and cadastral parcel numbers (e.g. Batilly ZD 16/17; Œuilly 3°47'9\"E, 49°4'40\"N) from NOVAE Cerfa/decision PDFs and check on cadastre.gouv.fr / IGN Géoplateforme BD ORTHO.","cross_with":["ODRÉ Registre national des installations de production et de stockage d'électricité (filter out 'En service' commissioned BESS)","Sitadel DiDo (granted non-residential building permits with area/commune, though without project text)","Géorisques ICPE (operational/ended Autorisation and Enregistrement facilities)","RTE Cartostock / Enedis data-fair (substation grid hosting capacity near site)"],"where_published":[{"name":"Sites des Préfectures de département — Rubrique ICPE / Preuves de dépôt & RAA","url":"https://www.vienne.gouv.fr/Actions-de-l-Etat/Environnement-risques-naturels-et-technologiques/Installations-classees/Industrielles/Stockage-d-energie-par-batterie-La-Barriere-Verrieres","what":"Individual ICPE 2925-2 Declaration filing receipts (preuves de dépôt), supplementary prefectural orders (APC), and public inquiry / PPVE notices for BESS projects in each of France's 101 departments.","how_to_search_inside":"No unified national search; run site:<dept>.gouv.fr searches for 'preuve de dépôt' '2925-2' or 'stockage' 'batterie', or inspect each Préfecture's Publications / ICPE / Déclarations initiales / RAA pages.","example_document":{"url":"https://www.vienne.gouv.fr/contenu/telechargement/51156/314801/file/fichierAccuseReception_stockage_d_energie_par_batteries_lithium_verrieres.pdf","what_it_gives":"Filing ref A-6-6HRCTIZPA (2026-11-06), PHOTOSOL DEVELOPPEMENT (SIRET 51831044600084), Verrières (86410), Lambert-93 X:514667 Y:6590260, 2925-2 20,000 kW / 50 MWh, PC=OUI."}},{"name":"Mairies et DDT — Affichage en mairie des demandes de Permis de Construire","url":"https://www.seine-et-marne.gouv.fr/contenu/telechargement/68608/563235/file/Annexe%20_aidem%C3%A9moire_batteries%20de%20stockage.pdf","what":"Pending Permis de Construire / Déclaration préalable filings for grid-connected BESS (competence Préfet/DDT under L.422-2/R.422-2, but commune remains guichet unique under R.423-3; excluded from Sitadel under CRPA L.311-2).","how_to_search_inside":"Check physical municipal notice boards (affichage en mairie, R.423-6), municipal urbanism portals where provided, or departmental CDPENAF / pôles EnR minutes on Préfecture websites (e.g. Loiret).","example_document":{"url":"https://www.loir-et-cher.gouv.fr/contenu/telechargement/37516/289624/file/fichierAccuseReception.pdf","what_it_gives":"Shows how ~1 MW (<20 m²) projects like Cellettes NWJ MET 3 (1,250 kW) declare PC=NON while larger projects like Verrières (20 MW) declare PC=OUI."}},{"name":"IGEDD / Autorité environnementale nationale — Cas par cas État","url":"https://www.igedd.developpement-durable.gouv.fr/autorite-environnementale-2026-decisions-de-cas-a4349.html","what":"National-level cas par cas in-examination table ('Cas par cas en cours d'examen') and decisions for state-jurisdiction energy/substation projects.","how_to_search_inside":"Inspect the HTML 'Cas par cas en cours d'examen' section and year pages; links directly to Cerfa PDFs.","example_document":{"url":"https://www.igedd.developpement-durable.gouv.fr/autorite-environnementale-2026-decisions-de-cas-a4349.html","what_it_gives":"Lists open 2026 storage-linked cases (e.g. Villefontaine 38 and Saint-Quentin-Fallavier 38 PV+stockage with completeness dates and Cerfa PDF links)."}}]},"related_not_answering":[{"name":"Sitadel — Liste des permis de construire et autres autorisations d'urbanisme (locaux)","url":"https://data.statistiques.developpement-durable.gouv.fr/dido/api/v1/datasets/6513f0189d7d312c80ec5b5b","why":"Official SDES notice excludes pending applications ('en cours d'instruction') under CRPA art. L.311-2, omits permits without floor area and suppresses project descriptions."},{"name":"Géorisques — Base des Installations Classées (ICPE)","url":"https://www.georisques.gouv.fr/donnees/bases-de-donnees/installations-industrielles","why":"Covers only Autorisation and Enregistrement facilities already in operation or ending; omits 2925-2 Déclaration-only BESS and pending applications."},{"name":"ODRÉ — Registre national des installations de production et de stockage d'électricité (agrégé)","url":"https://odre.opendatasoft.com/api/explore/v2.1/catalog/datasets/registre-national-installation-production-stockage-electricite-agrege","why":"Covers only commissioned facilities (all 938 'Stockage non hydraulique / Batterie' records have regime='En service'), not projects in permitting."},{"name":"Enedis Open Data / EDF SEI / ODRÉ — Projets en développement et Files d'attente","url":"https://opendata.enedis.fr/data-fair/api/v1/datasets?q=raccordement&size=20","why":"Publishes regional/departmental/power-bracket aggregated MW counts (and 75 ZNI territory aggregates for EDF Corse-Outremer), no individual project names or permitting status."},{"name":"RTE Cartostock & Caparéseau","url":"https://analysesetdonnees.rte-france.com/reseaux/cartostock","why":"Interactive maps displaying remaining MW substation grid-hosting headroom for storage/renewables, not individual BESS projects in permitting."},{"name":"European Energy Storage Inventory (EC JRC)","url":"https://ses.jrc.ec.europa.eu/storage-inventory","why":"Public Qlik viewer aggregating operational, under-construction and announced European assets from public data and Wood Mackenzie; provides neither downloadable API nor French permitting stage tracking."}],"open_questions":["No government source quantifies how many >600 kW Li-ion stand-alone BESS files are currently within the 15-day ICPE 2925-2 standstill or awaiting DDT/Préfet Permis de construire nationwide across the 101 departments without full crawling/OCR.","Whether a pending BESS whose R.122-2 cas par cas closed on NOVAE ('Dossier Clos', e.g. Batilly-en-Gâtinais 108 MW on 2026-10-08) is currently in DDT PC instruction, delayed, or abandoned cannot be resolved without checking local municipal/DDT records."],"history":[{"pass":1,"date":"2026-11-15","role":"research","model":"Gemini 4 Hydrogen","rules_version":"6.5","note":"Initial survey: no unified national BESS permitting registry; NOVAE covers R.122-2 cas par cas, 101 Prefectures hold ICPE 2925-2 PDFs, Sitadel excludes pending PC.","headline":{"official_data":"partial","non_official_data":"partial","national_registry":"no_evidence_found"},"sources":{"total":5,"new":5,"dropped":0},"negatives":{"overturned":0,"confirmed":0},"effort":{"pages":78,"minutes":23}}],"local_terms":[{"term":"stockage d'électricité par batteries / BESS","language":"fr","meaning":"Battery energy storage system (stand-alone = autonome)"},{"term":"atelier de charge d'accumulateurs (rubrique 2925-2)","language":"fr","meaning":"ICPE rubric for non-H2 (Li-ion) battery systems >600 kW, subject to Déclaration (D)"},{"term":"preuve de dépôt","language":"fr","meaning":"Official ICPE Declaration filing receipt published on departmental Préfecture websites for 3 years (R.512-49)"},{"term":"examen au cas par cas","language":"fr","meaning":"Environmental screening (R.122-2) handled via NOVAE to decide if a full EIA is required"},{"term":"autorisation environnementale (AENV)","language":"fr","meaning":"Unified environmental permit required for major projects crossing AENV/EIA/IOTA/species thresholds"},{"term":"permis de construire (PC) / déclaration préalable (DP)","language":"fr","meaning":"Urban planning permits (>20 m² footprint triggers PC; instructed by DDT for Préfet under L.422-2/R.422-2)"},{"term":"enquête publique / PPVE","language":"fr","meaning":"Public inquiry or electronic public participation required before EIA-subject project decisions"},{"term":"poste source / capacité d'accueil","language":"fr","meaning":"HTB/HTA substation and grid hosting capacity mapped on RTE Cartostock and Caparéseau"}],"provenance":{"pass_count":1,"models":["Gemini 4 Hydrogen"],"minutes_estimate":23,"pages_opened":78,"passes":[{"pass":1,"date":"2026-11-15","model":"Gemini 4 Hydrogen"}],"note":"Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed."},"card_url":"https://georutter.org/v1/fr/battery-storage-in-permitting.json","detail_url":"https://georutter.org/v1/fr/battery-storage-in-permitting/detail.json","html_url":"https://georutter.org/fr/battery-storage-in-permitting/","country_url":"https://georutter.org/v1/countries/fr.json"}