{"schema_version":"1.0","country":"us","country_name":"United States","topic":"hydrogen-plants-in-permitting","question":"Where can I get a list of hydrogen production projects currently in permitting in the United States, with location, capacity (MW), developer, permitting stage and date?","territory":"us","territory_level":"country","parent_url":null,"published_on":"2026-11-24","research_reviewed_on":"2026-11-24","access_checked_on":"2026-11-24","answer":{"official_data":"partial","non_official_data":"not_tested","summary":"No single list gives stage and date for electrolysis projects in permitting. DOE Record 24001 (May 2024) lists 43 planned rows without developers or dates; stage, developer and MW come from dockets: Lancaster Clean Energy Center (CEQA approval 2024-03-11, 400 MWe) and Plug Power's Graham, Texas project (DOE FONSI 2025-01-10, twelve 10 MW; agreed for sale July 2026). DOE hub pages are hub-level and stale; the PNWH2 award was reported rescinded in October 2025.","main_caveats":["DOE Record 24001 is dated May 2024: it lists Graham, TX as Planned/Under Construction although Plug Power agreed in July 2026 to sell that project; it has no developer or stage date.","A DOE FONSI (Graham, 2025-01-10) and a CEQA approval (Lancaster, 2024-03-11) are not financing, construction or operation: no building or start-of-construction document was found for either.","MW bases differ: 120 MW of electrolyzers, 45 tpd of hydrogen and 164 MW of grid interconnection describe Graham; Lancaster's '400 MWe' is undefined. None converts into another.","DOE hub pages predate the 2025 cuts (Canary Media: awards to two hubs rescinded) and show no electrolyzer-level project, MW or permit; DOE's EIS-0571 dates are anticipated only.","Only California and Texas dockets were opened; Washington, Oregon and other state portals and the IEA project file (account required) were not checked."],"confidence":"medium","confidence_reason":"Two projects were traced from portal and DOE documents to dated stages and DOE's table counts reconcile, but no hub project was matched to a docket and most projects, states and the IEA file were not checked.","attributes":[{"attribute":"location","covered":"partial","source_ids":["ceqanet-hydrogen","doe-nepa-hydrogen","doe-record-24001"],"note":"Lancaster CA (parcels, cross streets) and Graham TX (2264 FM 209) are documented to address level; DOE Table 1 gives city and state for planned rows; no list has coordinates.","gap":"not_checked","gap_note":"Only two projects were traced to site documents; hub projects and other states' dockets were not opened."},{"attribute":"capacity_mw","covered":"partial","source_ids":["ceqanet-hydrogen","doe-nepa-hydrogen","doe-record-24001"],"note":"Lancaster 400 MWe of electrolyzers; Graham twelve 10 MW units (45 tpd, a separate measure); DOE gives kW for 43 planned rows. Hub documents give tons per day only.","gap":"not_checked","gap_note":"Basis of DOE's kW and of Lancaster's 'MWe' not defined; capacity for other projects was not checked."},{"attribute":"developer","covered":"partial","source_ids":["ceqanet-hydrogen","doe-nepa-hydrogen","operator-project-announcements"],"note":"Element New Energy Lancaster 1, LLC (Lancaster) and Plug Power (Graham) are named in dockets; DOE Table 1 omits developers and hub pages name consortia.","gap":"not_checked","gap_note":"Developers of the other 41 planned rows and of hub projects were not identified."},{"attribute":"permitting_stage","covered":"partial","source_ids":["ceqanet-hydrogen","doe-nepa-hydrogen","operator-project-announcements"],"note":"Lancaster: CEQA approval (MND) 2024-03-11. Graham: DOE FONSI 2025-01-10, work paused since Dec 2023, sale agreed July 2026. DOE's statuses are only Planned/Under Construction.","gap":"not_checked","gap_note":"No national stage field; hub projects have no site-specific review yet; construction status of Lancaster after March 2024 was not verified."},{"attribute":"stage_date","covered":"partial","source_ids":["ceqanet-hydrogen","doe-nepa-hydrogen","operator-project-announcements"],"note":"Dated events for two projects: Lancaster NOD 2024-03-12 (approved 03-11); Graham EA public comment from 2024-12-06, FONSI 2025-01-10, sale release 2026-07-13.","gap":"not_checked","gap_note":"No list gives stage dates; DOE Record 24001 has none; EIS-0571 dates are anticipated."}]},"sources":[{"source_id":"ceqanet-hydrogen","name":"CEQAnet: California CEQA records for hydrogen production projects (example SCH 2024020266, Lancaster Clean Energy Center)","publisher":"California Governor's Office of Land Use and Climate Innovation (LCI), State Clearinghouse","official":true,"landing_url":"https://ceqanet.lci.ca.gov/","data_url":null,"access":"web_viewer_only","format":"HTML record pages, per-document CSV export and PDF attachments","license":"Unknown","language":"en","has_coordinates":null,"location_precision":"address","adds":"Dated local approvals with applicant, parcels and electrolyzer MW in the project description; the only permit-stage record opened for an electrolysis plant with MW.","first_seen_pass":1,"rank":1,"summary":"City of Lancaster CEQA record: Lancaster Clean Energy Center (Element New Energy Lancaster 1, LLC), 400 MWe of electrolyzers with 650 MW PV; MND 2024-02-07, approved 2024-03-11.","coverage_note":"California only; one hydrogen project opened; approval stage, not construction.","data_date":"2024-03-12","caveats":["Keyword search not scriptable.","Approval is not construction or operation."],"coverage":{"geographic":"California projects filed under CEQA; one hydrogen project followed to its approval. Search results listed other hydrogen records (SCH 2021040263, 2020080018, 2018069014) that were not opened."},"fine_print":{"unit":{"value":"Capacity is given in the free-text description: '400 MWe of electrolyzers', 650 MW PV, 330 MWh storage, hydrogen storage in tonnes.","quote":"a green hydrogen production plant incorporating 400 MWe of electrolyzers","url":"https://ceqanet.lci.ca.gov/2024020266/1","attempts":[]},"inclusion_rule":{"value":"Documents filed by lead agencies: mitigated negative declaration, notice of determination, exemptions.","quote":null,"url":"https://ceqanet.lci.ca.gov/","attempts":[]},"reference_date":{"value":"Records opened on 2026-11-24; Lancaster notice of determination received 2024-03-12.","quote":"Document Type NOD - Notice of Determination Received 3/12/2024","url":"https://ceqanet.lci.ca.gov/2024020266/2","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://ceqanet.lci.ca.gov/","note":"Continuous postings; no schedule stated."}]},"exclusions":{"value":"Not all electrolyzer projects (small pilots are often exempt); only California; approval is not construction.","quote":null,"url":null,"attempts":[]}},"key_fields":[{"field":"SCH Number; Document Type; Received/Approved On","meaning":"Project key, document (MND, NOD) and filing/approval dates."},{"field":"Lead Agency; Approving Agency","meaning":"City of Lancaster for the example."},{"field":"Document Description","meaning":"Free text with applicant (Element New Energy Lancaster 1, LLC), 650 MW PV, 400 MWe electrolyzers, storage tanks."},{"field":"Location (cross streets, parcel numbers, acres)","meaning":"1,338 acres in two sites; parcels 3384-018-001 to -004 and others."}],"how_to_use":{"example_request":"curl -sL https://ceqanet.lci.ca.gov/2024020266/1 ; curl -sL https://ceqanet.lci.ca.gov/2024020266/2 ; the attachment link on each record page is /2024020266/2/Attachment/<id>.","example_result":"SCH 2024020266, Lead Agency City of Lancaster: document 1 MND received 2/7/2024 (state review 2/7-3/8/2024); document 2 NOD received 3/12/2024, approved 3/11/2024. Applicant Element New Energy Lancaster 1, LLC; 650 MW PV, 330 MWh storage, 400 MWe electrolyzers.","steps":["Find the project from a developer or city announcement.","Open the SCH record's documents 1, 2, 3 and read type, dates and description.","Read the notice-of-determination PDF to confirm the approving agency and approval date."],"reading_traps":["Keyword search is a Google Custom Search widget and cannot be scripted; the structured /Search ignored a free-text parameter.","A notice of determination shows the CEQA approval; it does not say construction began or when it will.","The description says '400 MWe of electrolyzers' (Lancaster's own release says '400 MWe of hydrogen production'); the basis is not defined.","Titles are permit numbers (Conditional Use Permit No. 23-019), written with and without a period."]},"test":{"tested_on":"2026-11-24","method":"page_only","http_status":200,"content_type":"text/html; charset=utf-8","size_bytes":37712,"records_total":null,"records_for_country":null,"problems":["Free-text search is a Google Custom Search widget; a /Search 'q' parameter returned unrelated documents."]},"evidence":[{"claim":"Applicant and electrolyzer capacity.","url":"https://ceqanet.lci.ca.gov/2024020266/1","quote":"The applicant (Element New Energy Lancaster 1, LLC) proposes to construct and operate the Lancaster Clean Energy Center, a green hydrogen production plant powered by photovoltaic (PV) solar."},{"claim":"Approval date.","url":"https://ceqanet.lci.ca.gov/2024020266/2","quote":"Approving Agency City of Lancaster Approving Agency Role Lead Agency Approved On 3/11/2024"},{"claim":"Mitigated negative declaration review period.","url":"https://ceqanet.lci.ca.gov/2024020266/1","quote":"State Review Period Start 2/7/2024 State Review Period End 3/8/2024"}],"members":[],"members_summary":null},{"source_id":"doe-nepa-hydrogen","name":"DOE Office of NEPA Policy and Compliance pages for hydrogen production projects (DOE/EA-2281 Limestone; DOE/EIS-0571 Pacific Northwest Hydrogen Hub)","publisher":"U.S. Department of Energy, Office of NEPA Policy and Compliance","official":true,"landing_url":null,"data_url":null,"access":"pdf","format":"HTML project pages and PDF environmental assessment (5.9 MB, 5,764 text lines)","license":"Unknown","language":"en","has_coordinates":false,"location_precision":"address","adds":"Federal environmental-review documents with developer, site, electrolyzer MW, hydrogen output, state permit table and dated milestones; Limestone's EA lists twelve 10 MW electrolyzers.","first_seen_pass":1,"rank":2,"summary":"DOE NEPA records: Limestone (Plug Power, Graham TX) EA with twelve 10 MW electrolyzers, 45 tpd, FONSI signed 2025-01-10; Pacific Northwest Hub EIS scope (about 10 projects) without sites or MW.","coverage_note":"Only DOE-financed projects; two pages opened; Limestone's later fate is outside DOE's page.","data_date":"2025-01-10","caveats":["FONSI is not a loan or a building permit.","EIS schedule dates are anticipated, not confirmed."],"coverage":{"geographic":"DOE-funded or financed projects only: Graham, Texas (EA-2281) and a three-state hub (EIS-0571); other hydrogen NEPA pages were not enumerated."},"fine_print":{"unit":{"value":"Electrolyzer power in MW (twelve 10 MW units) and hydrogen output in tons per day (45 tpd), stated separately.","quote":"Twelve 10-megawatt (MW) electrolyzers A 15 tpd and 30 tpd hydrogen liquefaction system (45 tpd total)","url":"https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf","attempts":[]},"inclusion_rule":{"value":"Projects for which DOE considers federal financial assistance (loan guarantee or hub funding).","quote":"to consider the environmental impacts associated with providing financial assistance (a federal loan guarantee) to support the development of a green hydrogen production facility in Graham, Texas","url":"https://www.energy.gov/nepa/doeea-2281-limestone-green-hydrogen-production-project","attempts":[]},"reference_date":{"value":"EA-2281 page last updated 2026-03-05; FONSI signed 1/10/2025 (page header date January 1, 2025); EIS-0571 page last updated 2026-03-05 with schedule dates from 2024-2026.","quote":"This was last updated March 5, 2026 .","url":"https://www.energy.gov/nepa/doeea-2281-limestone-green-hydrogen-production-project","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.energy.gov/nepa/doeeis-0571-pacific-northwest-hydrogen-hub","note":"The EIS-0571 schedule shows Draft EIS August 2025 and Final EIS April 2026 but the page was last updated 2026-03-05 and shows no later milestone."}]},"exclusions":{"value":"Projects without federal funding have no DOE NEPA page; financing decisions are separate from the FONSI.","quote":"This Finding of No Significant Impact should not be construed as a final decision about issuance of a loan guarantee.","url":"https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf","attempts":[]}},"key_fields":[{"field":"Applicant; Project site","meaning":"Plug Power, Inc.; 2264 FM 209, Graham, Young County, Texas (about 8 miles southwest of Graham)."},{"field":"Project description","meaning":"Twelve 10 MW electrolyzers, 45 tpd liquefaction, 13.5-mile transmission line, powered by Young Wind Farm."},{"field":"Appendix B Permits and approvals","meaning":"Federal, state and local permits with status and dates."},{"field":"FONSI signature date; public comment period","meaning":"1/10/2025; 30-day comment period from December 6, 2024."},{"field":"EIS-0571 Project Schedule","meaning":"Anticipated milestones (NOI December 18, 2024; Draft EIS August 2025; Final EIS April 2026; ROD May 2026)."}],"how_to_use":{"example_request":"curl -sL -o ea2281.pdf https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf ; pdftotext -layout ea2281.pdf ea2281.txt ; read sections 1.4-2.3, the FONSI on page 41 and Appendix B (lines 5372 onward).","example_result":"Applicant Plug Power, Inc.; 'Twelve 10-megawatt (MW) electrolyzers'; '45 tons per day (tpd) of green hydrogen'; FONSI signed 1/10/2025; 'As of December 2023, all construction activities associated with the Project have ceased but are anticipated to resume in 2025 following loan guarantee approval.'","steps":["Open the project page, then the Final EA/FONSI article and PDF.","Take applicant, site, MW and tpd from the project description.","Read Appendix B for each permit's status and date, and the FONSI page for the decision date.","Check later company filings for what happened after the FONSI."],"reading_traps":["The FONSI covers the environmental effects of a loan guarantee, not a permit to build or a financing decision.","Three different numbers describe Graham: 120 MW of electrolyzers, 45 tpd of hydrogen and, in 2026, 164 MW of grid interconnection; none converts into another.","Page dates differ from document dates (page January 1, 2025; signature 1/10/2025; the draft comment period is typed 'through January 6, 2024').","The EIS-0571 schedule dates are anticipated; the page does not show whether the Draft or Final EIS was issued."]},"test":{"tested_on":"2026-11-24","method":"download","http_status":200,"content_type":"application/pdf","size_bytes":5905754,"records_total":null,"records_for_country":null,"problems":[]},"evidence":[{"claim":"Applicant and plant size.","url":"https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf","quote":"Plug Power, Inc. (Plug Power or the Applicant), is proposing to construct a green hydrogen production facility in Young County, Texas ... The Project will consist of twelve 10 MW electrolyzers"},{"claim":"Construction paused as of the EA.","url":"https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf","quote":"As of December 2023, all construction activities associated with the Project have ceased but are anticipated to resume in 2025 following loan guarantee approval."},{"claim":"FONSI is not a financing decision.","url":"https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf","quote":"This Finding of No Significant Impact should not be construed as a final decision about issuance of a loan guarantee."},{"claim":"Hub EIS scope.","url":"https://www.energy.gov/nepa/doeeis-0571-pacific-northwest-hydrogen-hub","quote":"As currently proposed, the Hub would encompass approximately 10 projects, including clean hydrogen production facilities that could produce 300-400 metric tons per day of clean hydrogen"}],"members":[{"name":"DOE/EA-2281 Limestone Green Hydrogen Production Project (Graham TX)","landing_url":"https://www.energy.gov/nepa/doeea-2281-limestone-green-hydrogen-production-project","data_url":"https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf","access":"pdf","tested":true,"data_found":true,"note":"EA and FONSI read in full for applicant, site, MW, permits and dates."},{"name":"DOE/EIS-0571 Pacific Northwest Hydrogen Hub","landing_url":"https://www.energy.gov/nepa/doeeis-0571-pacific-northwest-hydrogen-hub","data_url":null,"access":"web_viewer_only","tested":true,"data_found":true,"note":"Hub-level scope (about 10 projects, 300-400 metric tons per day); no site-specific project, MW or permit stage."}],"members_summary":{"total":null,"listed":2,"tested":2,"data_found":2,"scope_note":"Universe not counted: DOE NEPA pages for hydrogen production were found through search, not by listing. Two pages were opened; hub-related categorical exclusions (HyVelocity, Heartland) appeared in search results and were not opened.","pattern":"Search energy.gov/nepa for 'hydrogen' with the project or hub name; pages are titled DOE/EA-#### or DOE/EIS-####."},"member_scope":{"total":null,"note":"Universe not counted: DOE NEPA pages for hydrogen production were found through search, not by listing. Two pages were opened; hub-related categorical exclusions (HyVelocity, Heartland) appeared in search results and were not opened.","pattern":"Search energy.gov/nepa for 'hydrogen' with the project or hub name; pages are titled DOE/EA-#### or DOE/EIS-####."}},{"source_id":"doe-record-24001","name":"DOE Hydrogen Program Record 24001, Electrolyzer Installations in the United States (planned and under-construction rows)","publisher":"U.S. Department of Energy, Hydrogen Program (HFTO)","official":true,"landing_url":"https://www.hydrogen.energy.gov/library/program-records","data_url":"https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf","access":"pdf","format":"PDF (Table 1)","license":"Unknown","language":"en","has_coordinates":false,"location_precision":"municipality","adds":"National list of 43 planned or under-construction electrolyzer rows (4.41 GW) with city, kW and a two-value status; no developer and no stage date.","first_seen_pass":1,"rank":3,"summary":"43 planned or under-construction electrolyzer rows (657 MW under construction, 3.75 GW planned) with city, kW and status; May 2024.","coverage_note":"No developer, no stage date; 18 months old; cancelled projects still listed.","data_date":"2024-05","caveats":["No developer or dates.","Stale: Graham, TX has since been put up for sale."],"coverage":{"geographic":"United States; planned items only if funded or firmly committed; 120 kW or more per site."},"fine_print":{"unit":{"value":"Power in kW per row; basis not stated.","quote":"Power (kW)","url":"https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf","attempts":[]},"inclusion_rule":{"value":"This Record focuses on plans that have been funded (for example DOE projects or other financing already in place).","quote":"this Record focuses on plans that have been funded (e.g., DOE projects or other financing already in place).","url":"https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf","attempts":[]},"reference_date":{"value":"May 2024.","quote":"Record: 24001 Date: May 4, 2024","url":"https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf","attempts":[]},"update_frequency":{"value":"Roughly yearly; no newer record on the program page on 2026-11-24.","quote":null,"url":"https://www.hydrogen.energy.gov/library/program-records","attempts":[]},"exclusions":{"value":"Listed without attribution to any company; announced but unfunded projects are not included.","quote":"listed without attribution to any individual electrolyzer company or to specific end users","url":"https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf","attempts":[]}},"key_fields":[{"field":"Location; Power (kW); Status","meaning":"Status is Planned or Planned/Under Construction for the rows used here."}],"how_to_use":{"example_request":"curl -sL -o rec24001.pdf https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf ; pdftotext -layout rec24001.pdf rec24001.txt ; parse Table 1 rows and keep statuses 'Planned' and 'Planned/Under Construction'.","example_result":"43 rows: 21 Planned/Under Construction (657,290 kW) and 22 Planned (3,750,715 kW). Examples: 'Graham, TX 120,000 Planned/Under Construction', 'Alabama, NY 200,000 Planned/Under Construction', 'Delta, UT 220,000 Planned', 'Mendota, CA 80,000 Planned'.","steps":["Parse the table as in card hydrogen-plants.","Keep non-installed rows.","Look up each row's developer and permit stage in permit portals or news."],"reading_traps":["May 2024: projects since cancelled or sold are still listed (the Graham, TX row is the project Plug Power agreed to sell in July 2026).","No developer, no stage date, no stage definitions beyond two labels.","Rows without a city (for example 'TX 1,600,000 Planned') cannot be matched to a docket."]},"test":{"tested_on":"2026-11-24","method":"download","http_status":200,"content_type":"application/pdf","size_bytes":288896,"records_total":113,"records_for_country":43,"problems":[]},"evidence":[{"claim":"Totals under construction and planned.","url":"https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf","quote":"Current installed capacity is approximately 116 MW, with another approximately 657 MW under construction and 3.8 GW planned (firm commitments)."},{"claim":"Graham row.","url":"https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf","quote":"Graham, TX 120,000 Planned/Under Construction"}],"members":[],"members_summary":null},{"source_id":"doe-h2hubs-pages","name":"DOE Regional Clean Hydrogen Hubs selection pages (example: Pacific Northwest Hydrogen Hub, PNWH2)","publisher":"U.S. Department of Energy, Office of Clean Energy Demonstrations (OCED)","official":true,"landing_url":null,"data_url":null,"access":"web_viewer_only","format":"HTML pages","license":"Unknown","language":"en","has_coordinates":false,"location_precision":"none","adds":"Hub-level announcements: selectee, states, federal cost share and project type, not electrolyzer-level dockets; the opened page predates the 2025 terminations.","first_seen_pass":1,"rank":4,"summary":"DOE hub selection pages give consortium, states and cost share only (PNWH2: up to $1 billion); the page predates the October 2025 rescission of two hubs' awards reported by Canary Media.","coverage_note":"Hub-level; no electrolyzer docket; one hub page opened; list page returns 404.","data_date":"2025-01-27","caveats":["Page is stale relative to news of terminations.","No project-level MW or stage."],"coverage":{"geographic":"Seven regional hubs per news (not enumerated on an official list page: DOE's hubs overview URLs returned 404); only the PNWH2 page was opened."},"fine_print":{"unit":{"value":"Dollars (federal cost share) and tons of CO2; no electrolyzer MW on the page.","quote":"Federal Cost Share: Up to $1 billion","url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","attempts":[]},"inclusion_rule":{"value":"Selected hubs under the Bipartisan Infrastructure Law.","quote":null,"url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","attempts":[]},"reference_date":{"value":"Page last updated January 27, 2025.","quote":"This was last updated January 27, 2025 .","url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","note":"The page still shows the hub as selected on 2026-11-24 although news reports say its award was terminated in October 2025."}]},"exclusions":{"value":"No project list, MW, permit stage or dates on the opened page.","quote":null,"url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","attempts":[]}},"key_fields":[{"field":"Selectee name; Location; Federal Cost Share; Prime Contractor","meaning":"Pacific Northwest Hydrogen Association; Washington, Oregon and Montana; up to $1 billion."},{"field":"Project Summary","meaning":"Hub concept: production 'exclusively via electrolysis'."}],"how_to_use":{"example_request":"curl -sL https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","example_result":"Selectee Pacific Northwest Hydrogen Association; locations Washington, Oregon and Montana; Federal Cost Share up to $1 billion; page last updated January 27, 2025.","steps":["Open the hub page for the consortium and states.","Follow the NEPA page for scope; site-specific reviews come later.","Check news for award status: Canary Media (2025-10-10) and CATF (2026-05-11)."],"reading_traps":["The hub page says nothing about the October 2025 termination of this hub's award reported by Canary Media; do not treat it as current.","Hub awards fund consortia of projects; no single electrolyzer docket is named.","The DOE hubs overview URLs tried returned 404, so the list of seven hubs is only available from news."]},"test":{"tested_on":"2026-11-24","method":"page_only","http_status":200,"content_type":"text/html","size_bytes":113380,"records_total":null,"records_for_country":null,"problems":["DOE's regional-hubs overview URLs (energy.gov/oced/regional-clean-hydrogen-hubs-0 and /cmei/oced/regional-clean-hydrogen-hubs) returned 404."]},"evidence":[{"claim":"Hub selection and cost share.","url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","quote":"Selectee name: Pacific Northwest Hydrogen Association (PNWH2) Location: Washington, Oregon, and Montana Federal Cost Share: Up to $1 billion"},{"claim":"Awards to two hubs rescinded (news).","url":"https://www.canarymedia.com/articles/hydrogen/hydrogen-hub-cuts-trump-doe-list","quote":"the Department of Energy rescinded $2.2 billion in awards to two of the seven regional hydrogen hubs established under the bipartisan Infrastructure Investment and Jobs Act."},{"claim":"Retain/modify list covers five hubs (news).","url":"https://www.catf.us/2026/05/continued-uncertainty-department-energy-circulates-latest-retain-modify-awards-list/","quote":"the retain/modify list includes awards for five of the seven hydrogen hubs projects"}],"members":[{"name":"Pacific Northwest Hydrogen Hub (PNWH2)","landing_url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","data_url":null,"access":"web_viewer_only","tested":true,"data_found":false,"note":"Hub-level text only; no project, MW or permit information."}],"members_summary":{"total":7,"listed":1,"tested":1,"data_found":0,"scope_note":"Seven hubs per Canary Media and CATF; only PNWH2 was opened. ARCHES (California) and PNWH2 awards were rescinded per Canary Media (2025-10-10); CATF (2026-05-11) says DOE's retain/modify list covers awards for five of the seven hubs.","pattern":"Open each hub's DOE page and its NEPA page, then search the hub's partners' permit dockets."},"member_scope":{"total":7,"note":"Seven hubs per Canary Media and CATF; only PNWH2 was opened. ARCHES (California) and PNWH2 awards were rescinded per Canary Media (2025-10-10); CATF (2026-05-11) says DOE's retain/modify list covers awards for five of the seven hubs.","pattern":"Open each hub's DOE page and its NEPA page, then search the hub's partners' permit dockets."}},{"source_id":"operator-project-announcements","name":"Developer and city announcements on project status (Plug Power Graham sale release; City of Lancaster release)","publisher":"Plug Power Inc.; City of Lancaster, CA (via GlobeNewswire and PR Newswire reprints)","official":true,"landing_url":null,"data_url":null,"access":"web_viewer_only","format":"HTML press-release reprints","license":"Unknown","language":"en","has_coordinates":false,"location_precision":"municipality","adds":"What happened after the permits: Plug Power's July 2026 agreement to sell its Graham, Texas project, and Lancaster's March 2024 approval announcement with 400 MWe.","first_seen_pass":1,"rank":5,"summary":"Plug Power agreed on 2026-07-13 to sell its Graham, Texas project (land and 164 MW of interconnection) to Stream; the City of Lancaster announced its commission's approval on 2024-03-20.","coverage_note":"Two projects; reprints of releases; closing of the Graham sale not confirmed.","data_date":"2026-07-13","caveats":["Plug's release does not name Limestone or electrolyzers.","Sale closing only expected, not confirmed."],"coverage":{"geographic":"Two projects: Graham TX and Lancaster CA."},"fine_print":{"unit":{"value":"Interconnection in MW and dollars in the Plug release; MWe of 'hydrogen production' in Lancaster's release.","quote":"comprised of land and associated 164 MW of grid interconnection assets","url":"https://hydrogen-central.com/plug-power-announces-sale-of-graham-texas-project-and-staged-closing-of-new-york-gateway-project-with-stream-data-centers-expects-80-million-in-near-term-liquidity-as-part-of-275-million-plus-init/","attempts":[]},"inclusion_rule":{"value":"Whatever the company or city decides to announce.","quote":null,"url":null,"attempts":[]},"reference_date":{"value":"Plug release dated July 13, 2026 (reprinted 2026-07-22); Lancaster release dated March 20, 2024.","quote":"SLINGERLANDS, N.Y., July 13, 2026 (GLOBE NEWSWIRE)","url":"https://hydrogen-central.com/plug-power-announces-sale-of-graham-texas-project-and-staged-closing-of-new-york-gateway-project-with-stream-data-centers-expects-80-million-in-near-term-liquidity-as-part-of-275-million-plus-init/","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://hydrogen-central.com/plug-power-announces-sale-of-graham-texas-project-and-staged-closing-of-new-york-gateway-project-with-stream-data-centers-expects-80-million-in-near-term-liquidity-as-part-of-275-million-plus-init/","note":"One-off releases; no later closing confirmation opened."}]},"exclusions":{"value":"Company releases do not give permit numbers; the Plug release does not mention electrolyzers or the name Limestone.","quote":null,"url":"https://hydrogen-central.com/plug-power-announces-sale-of-graham-texas-project-and-staged-closing-of-new-york-gateway-project-with-stream-data-centers-expects-80-million-in-near-term-liquidity-as-part-of-275-million-plus-init/","attempts":[]}},"key_fields":[{"field":"Plug release: Graham, Texas Project","meaning":"'land and associated 164 MW of grid interconnection assets' sold to Stream for up to $76.5 million; closing expected on or about July 31, 2026."},{"field":"Lancaster release","meaning":"Planning Commission approval; '400 MWe of hydrogen production'; 650 MW PV; 330 MWh storage."}],"how_to_use":{"example_request":"curl -sL https://hydrogen-central.com/plug-power-announces-sale-of-graham-texas-project-and-staged-closing-of-new-york-gateway-project-with-stream-data-centers-expects-80-million-in-near-term-liquidity-as-part-of-275-million-plus-init/ ; curl -sL https://www.prnewswire.com/news-releases/lancaster-commission-approves-element-resources-green-hydrogen-production-facility-302094037.html","example_result":"Plug (2026-07-13): 'Plug has signed a definitive agreement to sell its Graham, Texas Project, comprised of land and associated 164 MW of grid interconnection assets, to Stream for up to $76.5 million'. Lancaster (2024-03-20): 'the Lancaster Planning Commission has approved Element Resources' Lancaster Clean Energy Center'.","steps":["Take the developer name from the permit record.","Search the developer's newsroom or wire for the project name and city.","Compare the announcement's status with the permit record."],"reading_traps":["Plug's release names a 'Graham, Texas Project' and 164 MW of interconnection; it does not say Limestone or electrolyzers, so its identity with the EA project is inferred from the shared city and developer.","Closing of the sale was only expected on or about 2026-07-31; no confirmation was opened.","Releases are reprints: Hydrogen Central (Plug) and PR Newswire (City of Lancaster)."]},"test":{"tested_on":"2026-11-24","method":"page_only","http_status":200,"content_type":"text/html","size_bytes":126453,"records_total":null,"records_for_country":null,"problems":[]},"evidence":[{"claim":"Plug agrees to sell the Graham project.","url":"https://hydrogen-central.com/plug-power-announces-sale-of-graham-texas-project-and-staged-closing-of-new-york-gateway-project-with-stream-data-centers-expects-80-million-in-near-term-liquidity-as-part-of-275-million-plus-init/","quote":"Plug has signed a definitive agreement to sell its Graham, Texas Project, comprised of land and associated 164 MW of grid interconnection assets, to Stream for up to $76.5 million"},{"claim":"Lancaster approval announcement.","url":"https://www.prnewswire.com/news-releases/lancaster-commission-approves-element-resources-green-hydrogen-production-facility-302094037.html","quote":"the Lancaster Planning Commission has approved Element Resources' Lancaster Clean Energy Center—a renewable hydrogen production facility utilizing photovoltaic (PV) solar for its power supply."},{"claim":"Lancaster size.","url":"https://www.prnewswire.com/news-releases/lancaster-commission-approves-element-resources-green-hydrogen-production-facility-302094037.html","quote":"The renewable hydrogen production plant will incorporate 400 MWe of hydrogen production and liquefied and gaseous hydrogen storage."}],"members":[{"name":"Plug Power: sale of Graham, Texas Project (2026-07-13)","landing_url":"https://hydrogen-central.com/plug-power-announces-sale-of-graham-texas-project-and-staged-closing-of-new-york-gateway-project-with-stream-data-centers-expects-80-million-in-near-term-liquidity-as-part-of-275-million-plus-init/","data_url":null,"access":"web_viewer_only","tested":true,"data_found":true,"note":"Reprint dated 2026-07-22 of a GlobeNewswire release."},{"name":"City of Lancaster: Planning Commission approves Lancaster Clean Energy Center (2024-03-20)","landing_url":"https://www.prnewswire.com/news-releases/lancaster-commission-approves-element-resources-green-hydrogen-production-facility-302094037.html","data_url":null,"access":"web_viewer_only","tested":true,"data_found":true,"note":"PR Newswire release issued by the City."}],"members_summary":{"total":null,"listed":2,"tested":2,"data_found":2,"scope_note":"No universe: only the two projects traced in this card were checked.","pattern":"Search the developer's newsroom for the project's city and name."},"member_scope":{"total":null,"note":"No universe: only the two projects traced in this card were checked.","pattern":"Search the developer's newsroom for the project's city and name."}},{"source_id":"iea-hydrogen-projects","name":"IEA Hydrogen Production and Infrastructure Projects Database (hydrogen production projects file)","publisher":"International Energy Agency (IEA)","official":false,"landing_url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","data_url":null,"access":"registration_required","format":"XLSX per its page (also .Stat Data Explorer)","license":"CC BY 4.0","language":"en","has_coordinates":null,"location_precision":null,"adds":"Worldwide project database (June 2026) that tracks projects by status; US rows and stage fields not inspected because the download needs a free IEA account.","first_seen_pass":1,"rank":6,"summary":"IEA global hydrogen production projects file (June 2026, CC BY 4.0, free account); not inspected.","coverage_note":"Registration required.","data_date":"2026-06-18","caveats":["Not tested."],"coverage":{"geographic":"Worldwide; the US subset was not counted."},"fine_print":{"unit":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","note":"Not described on the overview page."}]},"inclusion_rule":{"value":"Projects for hydrogen production for energy or climate-mitigation purposes.","quote":"tracks data on projects for the production of hydrogen for energy or climate change-mitigation purposes and the development of hydrogen infrastructure","url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","attempts":[]},"reference_date":{"value":"File dated 2026-06-18.","quote":"Hydrogen production projects 18/06/2026 XLSX","url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","attempts":[]},"update_frequency":{"value":"Annually.","quote":"The Hydrogen Production and Infrastructure Projects Database is updated annually.","url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","attempts":[]},"exclusions":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","note":"File not opened."}]}},"key_fields":[],"how_to_use":{"example_request":"","example_result":"","steps":["Download the production projects XLSX with a free IEA account and filter the United States.","Check whether the status field distinguishes permitting, FID and construction."],"reading_traps":["Content unverified; account required; global file."]},"test":{"tested_on":"2026-11-24","method":"page_only","http_status":200,"content_type":"text/html","size_bytes":251296,"records_total":null,"records_for_country":null,"problems":["Download requires an IEA account: 'You are either not logged in or your login session has expired, please login again or create an IEA account to download data.'"]},"evidence":[{"claim":"File date and licence.","url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","quote":"Hydrogen production projects 18/06/2026 XLSX ... Licence CC BY 4.0"}],"members":[],"members_summary":null},{"source_id":"cleg-hydrogen-projects-map","name":"Clean Energy Group, Hydrogen Projects in the US mapping tool (Tableau Public)","publisher":"Clean Energy Group (non-profit)","official":false,"landing_url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","data_url":null,"access":"web_viewer_only","format":"Tableau Public embedded dashboard","license":"Unknown","language":"en","has_coordinates":null,"location_precision":null,"adds":"Map of US hydrogen production projects of all types by status including 'permitting' (April 2025); data not extractable by script.","first_seen_pass":1,"rank":7,"summary":"Clean Energy Group's map of US hydrogen projects by status (construction, development, permitting, online), April 2025; not extractable.","coverage_note":"All production routes; viewer only.","data_date":"2025-04","caveats":["Not tested."],"coverage":{"geographic":"United States hydrogen production projects of every production route."},"fine_print":{"unit":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","note":"Not stated."}]},"inclusion_rule":{"value":"Projects from EPA FLIGHT, EIA's refinery capacity report and desk research.","quote":"All information included in this tool is based on data from the Environmental Protection Agency's Facility Level Information on GreenHouse gasses Tool (FLIGHT), the Energy Information Administration's Refinery Capacity Report, and Clean Energy Group's own desk research.","url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","attempts":[]},"reference_date":{"value":"April 2025.","quote":"Last updated April 2025.","url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","attempts":[]},"update_frequency":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","note":"Not stated."}]},"exclusions":{"value":null,"quote":null,"url":null,"attempts":[{"url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","note":"Dashboard not extracted."}]}},"key_fields":[],"how_to_use":{"example_request":"","example_result":"","steps":["Use the status filter (construction, development, permitting, online) in a browser."],"reading_traps":["Includes fossil and pyrolysis projects; April 2025 is before the 2025 cancellations and 2026 sales."]},"test":{"tested_on":"2026-11-24","method":"page_only","http_status":200,"content_type":"text/html","size_bytes":107471,"records_total":null,"records_for_country":null,"problems":["A Tableau Public CSV request for the workbook returned 404 with an AWS WAF script."]},"evidence":[{"claim":"Status categories in the map.","url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","quote":"Users can browse this mapping tool based on the status of the project (construction, development, permitting, online)"}],"members":[],"members_summary":null}],"sector":{"regulator":{"name":"Local lead agencies and state agencies (permits); U.S. DOE (NEPA and financing); EPA and TCEQ for air permits","url":"https://www.energy.gov/nepa"},"operators":{"structure":"many","note":"Developers include Plug Power, Element Resources and utilities; no census was found.","census_url":null},"publication_obligation":{"exists":"yes","norm":"NEPA for federally financed projects; CEQA for California approvals.","url":"https://www.energy.gov/nepa/doeea-2281-limestone-green-hydrogen-production-project","what_must_be_published":"Environmental assessments, FONSI and CEQA notices.","frequency":"Per project"},"consolidated_republication":{"found":"partial","note":"DOE republishes a yearly planned-project table without developers; no list of permitting stage and date for electrolysis projects was found.","checked_pages":[{"organization":"U.S. DOE Hydrogen Program","url":"https://www.hydrogen.energy.gov/library/program-records","saw":"Newest electrolyzer-installations record is 24001 (May 2024)."},{"organization":"U.S. DOE OCED","url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","saw":"Hub selection page, last updated January 27, 2025."},{"organization":"U.S. DOE Office of NEPA","url":"https://www.energy.gov/nepa/doeea-2281-limestone-green-hydrogen-production-project","saw":"Final EA and FONSI page for Limestone, last updated March 5, 2026."}]}},"national_registry":{"exists":"no_evidence_found","note":"No national list of electrolysis projects in permitting with stage, developer and date found. DOE Record 24001 (planned rows), DOE hub pages, the IEA file (account required) and Clean Energy Group's map (not extractable) were checked.","checked_pages":[{"organization":"U.S. DOE Hydrogen Program","url":"https://www.hydrogen.energy.gov/library/program-records","saw":"Program records; 24001 is the newest installations record."},{"organization":"U.S. DOE OCED","url":"https://www.energy.gov/cmei/oced/pacific-northwest-hydrogen-hub-pnwh2","saw":"Hub page without project-level data."},{"organization":"U.S. DOE NEPA Office","url":"https://www.energy.gov/nepa/doeeis-0571-pacific-northwest-hydrogen-hub","saw":"EIS schedule for the PNW hub; project-specific reviews come later."},{"organization":"International Energy Agency","url":"https://www.iea.org/data-and-statistics/data-product/hydrogen-production-and-infrastructure-projects-database","saw":"Projects database June 2026; download requires an account."},{"organization":"Clean Energy Group","url":"https://www.cleanegroup.org/initiatives/alternative-fuels/projects-in-the-us/","saw":"Tableau map with a permitting status; April 2025."}]},"if_unstructured":{"summary":"Stage and dates are in project-specific documents: CEQA records for California projects, DOE NEPA documents for federally financed projects, and company or city releases for later status.","recipe":["Start from a row of DOE Record 24001 (city, state, kW) or a developer announcement.","Search CEQAnet (California) or the state's permit portal for the city, developer and permit number.","For federally financed projects, search energy.gov/nepa for the project; read the project description, Appendix of permits and the FONSI date.","Search the developer's newsroom for what happened after the permit, and note any sale or pause.","Record MW, tons per day and interconnection MW in separate fields."],"location_method":"Use the address, parcel numbers or cross streets in the CEQA or NEPA document; no coordinates are published in the records opened.","cross_with":"DOE Record 24001 rows, the IEA project file and company releases.","where_published":[{"name":"CEQAnet","url":"https://ceqanet.lci.ca.gov/","what":"California CEQA filings with dates and applicants.","how_to_search_inside":"Advanced Search facets or open https://ceqanet.lci.ca.gov/<SCH>/<n>; keyword search is a Google widget.","example_document":{"url":"https://ceqanet.lci.ca.gov/2024020266/2","what_it_gives":"Notice of Determination SCH 2024020266: 'Approved On 3/11/2024'; 'Received 3/12/2024'; lead agency City of Lancaster (page 2 of the record)."}},{"name":"DOE Office of NEPA Policy and Compliance","url":"https://www.energy.gov/nepa","what":"Environmental assessments and EISs for DOE-financed hydrogen projects.","how_to_search_inside":"Search the site for the project or hub name; pages are titled DOE/EA-#### or DOE/EIS-####.","example_document":{"url":"https://www.energy.gov/sites/default/files/2025-01/final-fonsi-ea-2281-limestone-green-hydrogen-prod-2025-01.pdf","what_it_gives":"Final EA and FONSI for Limestone: 'Twelve 10-megawatt (MW) electrolyzers'; FONSI signed 1/10/2025; Appendix B (page B-1) lists permits and their status."}}]},"related_not_answering":[{"name":"Canary Media: hydrogen hub cuts (2025-10-10)","url":"https://www.canarymedia.com/articles/hydrogen/hydrogen-hub-cuts-trump-doe-list","why":"News on rescinded hub awards; context for hub status, not a project list or a permit record."},{"name":"CATF: DOE retain/modify awards list (2026-05-11)","url":"https://www.catf.us/2026/05/continued-uncertainty-department-energy-circulates-latest-retain-modify-awards-list/","why":"Analysis of funding status of hubs; says nothing on electrolyzer permits."},{"name":"DOE/EIS-0571 Pacific Northwest Hydrogen Hub","url":"https://www.energy.gov/nepa/doeeis-0571-pacific-northwest-hydrogen-hub","why":"Programmatic scope (about 10 projects, 300-400 metric tons per day); no site, MW, developer or permit stage."}],"open_questions":[{"question":"Can any Hydrogen Hub announcement be matched to a specific electrolyzer docket?","starting_point":"PNWH2 (up to $1 billion) lists project locations in news, but DOE's EIS says site-specific reviews follow funding decisions; its hub page and NEPA page do not show the reported termination.","next_step":"Open the other six hubs' pages and the partners' permit dockets (for example HyVelocity partners in Texas, ARCHES in California)."},{"question":"Is the Lancaster Clean Energy Center under construction?","starting_point":"CEQAnet and the City's 2024-03-20 release show approval; search results mentioned 2025 coverage and a liquefaction order that were not opened.","next_step":"Check City of Lancaster building permits and Element Resources' recent releases."},{"question":"Was the sale of Plug Power's Graham, Texas project to Stream completed, and what happens to the Limestone electrolyzer plan and the DOE loan guarantee?","starting_point":"Release of 2026-07-13 expects closing around 2026-07-31; it does not mention electrolyzers or Limestone.","next_step":"Check Plug Power's next quarterly report and DOE LPO's loan pages."},{"question":"What do the IEA file and Clean Energy Group map say about US electrolysis projects in permitting?","starting_point":"IEA June 2026 file needs an account; the Tableau map could not be exported.","next_step":"A person downloads the IEA file and opens the map in a browser."},{"question":"Which Washington, Oregon and Texas dockets exist for electrolysis projects (for example EFSEC, Washington Ecology, TCEQ)?","starting_point":"Searches returned UK permits and a Washington programmatic fact sheet only; the Graham EA says TCEQ coverage is by Permit by Rule.","next_step":"Open those agencies' project pages directly."}],"history":[{"pass":1,"date":"2026-11-24","role":"research","model":"claude-sonnet-5-5","rules_version":"2026-11-24-eeuu-gases-renovables","note":"First pass; reasoning effort and minutes not recorded. Pages count is approximate.","headline":{"official_data":"partial","non_official_data":"not_tested","national_registry":"no_evidence_found"},"sources":{"total":7,"new":7,"dropped":0},"negatives":{},"effort":{"pages":20,"minutes":null}}],"local_terms":[{"term":"CEQAnet / Notice of Determination (NOD) / Mitigated Negative Declaration (MND)","language":"en","meaning":"California portal and documents; open each document of the SCH number for stage and date."},{"term":"DOE/EA-#### Final Environmental Assessment and FONSI","language":"en","meaning":"DOE NEPA documents for financed projects; energy.gov/nepa pages carry the applicant, site and permits."},{"term":"Regional Clean Hydrogen Hubs (H2Hubs)","language":"en","meaning":"Seven DOE-selected hubs; hub pages are consortium-level."},{"term":"Hydrogen Program Record 24001","language":"en","meaning":"DOE table of installed and planned electrolyzers; planned rows have no developer."},{"term":"Conditional Use Permit (CUP) No. ...","language":"en","meaning":"City or county use permit that appears as the CEQAnet title (for example CUP 23-019)."},{"term":"Loan Programs Office (LPO) conditional commitment / loan guarantee","language":"en","meaning":"DOE financing step referred to in the Graham EA; a FONSI is not the financing decision."},{"term":"Permit by Rule (PBR), TCEQ","language":"en","meaning":"Texas air authorisation noted in the Graham EA (coverage began September 2023); no public docket was found."},{"term":"retain/modify list","language":"en","meaning":"DOE's 2026 list of awards it may keep; CATF reports it covers five of seven hubs."}],"provenance":{"pass_count":1,"models":["claude-sonnet-5-5"],"minutes_estimate":null,"pages_opened":20,"passes":[{"pass":1,"date":"2026-11-24","model":"claude-sonnet-5-5"}],"note":"Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed."},"card_url":"https://georutter.org/v1/us/hydrogen-plants-in-permitting.json","detail_url":"https://georutter.org/v1/us/hydrogen-plants-in-permitting/detail.json","html_url":"https://georutter.org/us/hydrogen-plants-in-permitting/","country_url":"https://georutter.org/v1/countries/us.json"}