au / battery-storage

Australia battery storage data sources

Where can I get a list of battery storage (BESS) installations in operation in Australia, with location, power (MW), energy (MWh), operator and commissioning date?

Research reviewed
2026-11-26
Sources tested
2026-11-26
Access checked
2026-11-26
Published
2026-11-27
Sources
5 on this page · 3 in the detail

Answer

Official data
Partial coverage
Non official data
Usable data
Confidence
Medium

No single official national list exists. For the NEM (QLD, NSW/ACT, VIC, SA, TAS) AEMO's quarterly NEM Generation Information xlsx lists each battery unit with status, MW AC, MWh and owner (58 units across 'In Service' and 'In Commissioning', Oct 2026); NEMWEB MMS tables add registered participant, station address and registration dates. Neither gives coordinates and commissioning dates are mostly blank. For WA's WEM, AEMO's daily facilities CSV gives only code, participant and System Size (combined import and export rating). Open Electricity (non-official, CC BY-NC) covers NEM+WEM with coordinates, MW, MWh, owner and start date. NT/off-grid not verified.

Confidence reason: NEM and WEM official files were downloaded and cross-checked; NT/off-grid, AER and DCCEEW pages could not be opened (403/timeouts) and Overpass was unavailable.

Local search terms

  • NEM Generation Information — AEMO's quarterly xlsx of existing and proposed NEM generating/storage units; filter Technology Type 'Battery Storage'.
  • DUID (Dispatchable Unit Identifier) — Unit code that joins GI, MMS tables, SCADA and Open Electricity.
  • Bidirectional unit (BIDIRECTIONAL) — MMS DISPATCHTYPE for batteries registered under the IESS rules (from mid-2024).
  • Electric Storage Resource (ESR) — WEM term for storage; battery facility codes contain '_ESR' (or '_BESS').
  • System Size — WEM facility capacity in MW; for storage it adds withdrawal to sent-out capacity.
  • Full Commercial Use Date (FCUD) — GI field: date units are expected to become operationally available after NER 5.7.3 tests.
  • In Commissioning / In Service — GI statuses: hold point >=30% capacity passed / commissioning signed off by AEMO.
  • BESS — Battery energy storage system; common in AEMO site names (e.g. 'Orana BESS').

Requested attributes

AttributeCoverageSourcesScope and limitations
Installation location locationPartially coveredopenelectricity_facilities nemweb_mms_registration ga_battery_storage_facilities aemo_nem_geninfo osm_battery_plantsNEM official: MMS station address/locality; GA points (July 2024 fleet); GI only region. WEM: none official. Coordinates NEM+WEM: Open Electricity (non-official).

Not checked: Official coordinates not published for the current NEM or WEM fleet (GI, MMS, WEM CSV checked); NT/off-grid documents returned HTTP 403 and remain unchecked.

Power power_mwPartially coveredaemo_nem_geninfo nemweb_mms_registration wem_facilities openelectricity_facilitiesNEM: MW AC per unit (GI) and registered/max MW (MMS). WEM: System Size counts export plus withdrawal; SCADA gives actual MW.

Not checked: WEM discharge MW not published as such (System Size only); off-grid systems (NT, Horizon Power, NWIS) not verified (HTTP 403 / no list).

Stored energy energy_mwhPartially coveredaemo_nem_geninfo nemweb_mms_registration openelectricity_facilities osm_battery_plantsNEM: nameplate MWh per unit (GI) and MAXSTORAGECAPACITY (MMS), disagreeing for 10 units. WEM: only non-official per unit; WATC gives an aggregate.

Not checked: Official per-installation MWh not published for the WEM (facilities CSV, CRC files, ESM Rules checked; WEM ESOO 403); off-grid not verified.

Operator operatorPartially coveredaemo_nem_geninfo nemweb_mms_registration wem_facilities openelectricity_facilities osm_battery_plantsOfficial: GI Site Owner and MSATS Custodian, MMS registered participant name, WEM Market Participant. No field labelled operator.

Not checked: Operator as such not published by AEMO (GI definitions, MMS, WEM CSV checked); OSM 'operator' tag only per mapped element; off-grid not verified.

Commissioning date commissioning_datePartially coveredaemo_nem_geninfo nemweb_mms_registration openelectricity_facilitiesGI FCUD in 14/58 rows (19/24 in Jul 2024 release) and Change Log status dates; MMS dates are registration. Open Electricity commencement_date for all.

Not checked: No official in-service date field for the WEM (facilities CSV) or for most NEM units; WA pages give text dates; off-grid not verified.

Main caveats

  • Registration is not operation: MMS START_DATE and 'COMMISSIONED' mark registration (often the 2024 IESS re-registration); GI 'In Service' needs AEMO sign-off after commissioning tests.
  • GI status can lag: Waratah Super Battery (WTAHB1) is 'Committed' in the Oct 2026 release while MMS SCADA shows it discharging up to 556.8 MW in Oct 2026.
  • WEM 'System Size' adds withdrawal to export capacity: KWINANA_ESR1 System Size 200 vs ~100 MW peak in Oct 2026 SCADA; use a documented export rating. SCADA shows observed output only.
  • GI and MMS give MW and MWh per generating unit (DUID row); a site or hybrid spans several rows and 'Max Site Capacity (AC)' caps the site.
  • Official files name owner, MSATS custodian or registered participant, not an operator; they can differ (MREHA3: owner Equis SPV, participant SEC Energy).
  • Open Electricity is non-official, CC BY-NC 4.0 and excludes AI training/grounding from its standard licence; its MW, MWh and dates can differ from AEMO.

Sources

aemo_nem_geninfoNEM Generation Information (October 2026 release) with KCI datafile

Australian Energy Market Operator (AEMO) · Official · XLSX · Direct download · License: AEMO copyright; use per AEMO website copyright permissions

Official quarterly xlsx of every NEM unit with status, MW AC, MWh, owner and DUID; 58 battery rows In Service/In Commissioning (54 sites) in the Oct 2026 release.

Landing url
https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-planning-data/generation-information
Data url
https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en
Coverage note
NEM only; location only as NEM region; commissioning date mostly blank (Change Log gives status-change release dates).
Date of data
2026-10-30
Language
en
Location precision
No location
Has coordinates
No
Test
2026-11-26 · Download · HTTP 200
  • Landing page and file URL without ?rev= return HTTP 403 (Cloudflare challenge) to automated clients.

Caveats

  • Status can lag actual operation (Waratah 'Committed' while dispatching).
  • Site Owner/Custodian are not an explicit operator field.

Example request

curl -sL -o gi.xlsx 'https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/generation_information/2026/nem-generation-information-oct-2026.xlsx?rev=e4625386b864409786cd79986dd0ac04&sc_lang=en'  # sheet 'Generator Information', header row 4; Technology Type='Battery Storage'; Commitment Status in ('In Service','In Commissioning')

Example result

Hornsdale Power Reserve Unit 1 | HPRG1 | DUID HPR1 | SA1 | In Service | 100 MW AC | 117 MWh | Site Owner Hornsdale Power Reserve Pty Ltd | Custodian HORNSPR (2nd row HPRG EXP: 50 MW, 61.3 MWh)

nemweb_mms_registrationNEMWEB MMS Data Model monthly archive: DUDETAIL, DUDETAILSUMMARY, STATION, STATIONOPERATINGSTATUS and DISPATCH_UNIT_SCADA

Australian Energy Market Operator (AEMO) · Official · ZIP of CSV (AEMO MMS I/D/C row format) · Direct download · License: unknown

AEMO MMS monthly CSVs: every registered NEM battery (BIDIRECTIONAL DUID) with registered and max MW, MAXSTORAGECAPACITY, participant, station address/locality and registration dates; SCADA shows first output.

Landing url
https://nemweb.com.au/Reports/Current/
Data url
https://nemweb.com.au/Data_Archive/Wholesale_Electricity/MMSDM/2026/MMSDM_2026_10/MMSDM_Historical_Data_SQLLoader/DATA/PUBLIC_ARCHIVE%23DUDETAIL%23FILE01%23202610010000.zip
Coverage note
NEM registered units only (70 bidirectional DUIDs, Oct 2026); no in-service flag.
Date of data
2026-11-09
Language
en
Location precision
Address
Has coordinates
No
Test
2026-11-26 · Download · HTTP 200

Caveats

  • Registration dates are not commissioning dates (IESS re-registration in 2024).
  • MAXSTORAGECAPACITY and GI MWh disagree for 10 units.

Complete procedure available in the full detail

wem_facilitiesWEM Market Data: Facilities (post-reform) and Facility SCADA

Australian Energy Market Operator (AEMO), Western Australia · Official · CSV · Direct download · License: unknown

Daily CSV of all WEM registered facilities with participant and System Size (MW); 8 storage facilities identifiable by ESR/BESS codes on 2026-11-26.

Landing url
https://data.wa.aemo.com.au/
Data url
https://data.wa.aemo.com.au/datafiles/post-facilities/facilities.csv
Coverage note
Western Australia SWIS only; no MWh, location or dates.
Date of data
2026-11-26
Language
en
Location precision
No location
Has coordinates
No
Test
2026-11-26 · Download · HTTP 200
  • AEMO's WEM registered facilities web page returns HTTP 403 to automated clients; the data portal file is served.

Caveats

  • System Size for storage counts export plus withdrawal (about 2x discharge MW).
  • Storage identified only by facility code.

Complete procedure available in the full detail

ga_battery_storage_facilitiesBattery Storage Facilities (MapServer layer)

Geoscience Australia · Official · ArcGIS REST MapServer (JSON); File GDB zip on eCat · API · License: CC BY 4.0 (service copyright text); data.gov.au shows 'notspecified'

Official GA point layer of NEM batteries with coordinates, MW, MWh, owner and status copied from AEMO GI July 2024 (40 records, 25 In Service).

Landing url
https://ecat.ga.gov.au/geonetwork/srv/api/records/747fc5c7-efcc-4df4-99d2-7d314d29ce57
Data url
https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer/0/query?where=1%3D1&outFields=*&returnGeometry=true&outSR=4326&f=json
Coverage note
NEM only and stale (July 2024 inventory).
Date of data
2024-07
Language
en
Location precision
Exact
Has coordinates
Yes
Test
2026-11-26 · API query · HTTP 200
  • Two records have latitude 0.0 (Hazelwood BESS).

Caveats

  • Two records with latitude 0.0.
  • Misses batteries commissioned after mid-2024.

Example request

https://services.ga.gov.au/gis/rest/services/BatteryStorageFacilities/MapServer/0/query?where=1%3D1&outFields=*&returnGeometry=true&outSR=4326&f=json

Example result

Victorian Big Battery | In Service | Owner Victorian Big Battery Pty Ltd | FCUD 'December 2021' | lat -38.03872 lon 144.29587

openelectricity_facilitiesOpen Electricity facilities (NEM and WEM)

Open Electricity (The Superpower Institute) · Non-official · HTML page with embedded JavaScript data object; API (JSON) requires an API key · Web viewer only · License: CC BY-NC 4.0 (standard licence); commercial use and AI training/grounding need an Enterprise licence

Non-official facility list (NEM + WEM) with coordinates, MW, MWh, commencement date and owner; 68 operating battery units on 2026-11-26.

Landing url
https://openelectricity.org.au/facilities
Data url
https://openelectricity.org.au/facilities
Coverage note
Covers NEM and WA SWIS; no NT or off-grid systems found.
Date of data
2026-11-26
Language
en
Location precision
Exact
Has coordinates
Yes
Test
2026-11-26 · Download · HTTP 200
  • Data embedded as a JavaScript literal in the page; API requires a key (HTTP 401 without one).

Caveats

  • CC BY-NC 4.0; AI training/grounding excluded from the standard licence.
  • Commencement date and MWh can differ from AEMO figures.

Example request

curl -sL -o facilities.html 'https://openelectricity.org.au/facilities'  # parse embedded objects {code:...,network_id:...,location:{lat,lng},units:[{fueltech_id:"battery",status_id,capacity_maximum,capacity_storage,commencement_date}]}

Example result

Kwinana Battery 2 | WEM | lat -32.202465 lng 115.778452 | KWINANA_ESR2 battery operating | capacity_registered 225 | capacity_storage 900 | commencement_date 2024-09-26 | owner Synergy

Additional sources in the detail: 3. Read the full detail; locate each source by its source_id.

Document access

Official structured data cover the NEM (no coordinates, few commissioning dates) and WA's SWIS (no MWh, location or dates). Missing pieces come from AEMO's release archive and Change Log and from WA government pages and reports; NT/off-grid documents could not be opened.

Research provenance

Pass count
1
Minutes estimate
40
Pages opened
64
PassDate
12026-11-26

Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed.

Record metadata: Schema version: 1.0 · Country: au · Country name: Australia · Topic: battery-storage · Territory: au · Territory level: Country · Parent url: No parent territory · Html url: https://georutter.org/au/battery-storage/