us / grid-expansion-plansUnited States grid expansion plans data sources
Where can I get the planned new power lines and substations in the United States, with location, voltage, planned date and status?
- Research reviewed
- 2026-11-19
- Sources tested
- 2026-11-19
- Access checked
- 2026-11-19
- Published
- 2026-11-27
- Sources
- 5 on this page · 0 in the detail
Answer
- Official data
- Partial coverage
- Non official data
- Not checked
- Confidence
- Medium
PJM's live XML, CAISO's annual plan and status workbooks, and MISO's MTEP package list regional upgrades and give project descriptions, status and estimated in-service dates. The sources checked give locations by name, state or occasional point. No downloadable route geometry or national dataset was verified. Filter out equipment-only, canceled and completed work when looking for new lines and substations.
Local search terms
- RTEP (Regional Transmission Expansion Plan) — PJM's regional plan; its upgrades have b-numbers such as b3780.2
- MTEP (MISO Transmission Expansion Plan) — MISO's annual plan; Appendix A lists new projects recommended for approval
- TPP (Transmission Planning Process) — CAISO's annual cycle producing the Board-approved transmission plan
- TDF (Transmission Development Forum) — CAISO's twice-yearly status review of approved projects
- PTO (Participating Transmission Owner) — Utility that builds and owns a CAISO-approved project, e.g. PG&E or SCE
- ISD (in-service date) — Expected date a project enters service
- Baseline, Supplemental, Network upgrade — PJM project types: regional reliability, owner-driven, and generator-interconnection upgrades
- Re-scope — A previously approved project whose scope or cost was changed in a later plan
Requested attributes
| Attribute | Coverage | Sources | Scope and limitations |
|---|---|---|---|
Planned line or substation location location | Partially covered | pjm-upgrades caiso-plan-appendix-h miso-mtep25 | Substation or line names and state only (PJM Location, MISO From/To Sub, CAISO descriptions); no routes; 16 of 15,816 PJM rows embed a point. Not checked: No route geometry in the files tested; ERCOT, NYISO, SPP, the ISO-NE list file and project permit filings were not checked for routes. |
Voltage level voltage | Covered | pjm-upgrades miso-mtep25 caiso-plan-appendix-h | PJM Voltage in kV (pairs like 138/69; 642 blank), MISO Max kV and Min kV, CAISO kV in project names and descriptions. |
Planned date planned_date | Covered | pjm-upgrades miso-mtep25 caiso-plan-appendix-h caiso-tdf-workbooks | PJM ProjectedInServiceDate, MISO Expected ISD, CAISO expected in-service (Appendix H, TDF history); approval and required dates are separate fields. |
Project status status | Covered | pjm-upgrades miso-mtep25 caiso-tdf-workbooks | PJM Status (PL, EP, UC, IS, Cancelled), MISO Plan Status M1-M4, CAISO TDF Project Status (Initiating, Design, Construction, In-Service, Cancelled). |
Latest available data latest_data | Covered | pjm-upgrades caiso-plan-appendix-h miso-mtep25 | PJM XML modified 2026-11-19; CAISO plan updated 2026-08-27; MISO MTEP25 (Dec 2025) and MTEP26 draft (2026-11-06); CAISO TDF workbook retrieved only to Jul 2025. |
Historical coverage historical_series | Partially covered | caiso-tdf-workbooks pjm-upgrades miso-mtep25 | CAISO TDF keeps in-service date revisions Jan 2022-Jul 2025; PJM lists projects since 2005 but only its current state; MISO has one package per year. Not checked: No versioned archive of the PJM table found (only a 2023 XLS snapshot); CAISO TDF workbooks after Jul 2025 were not retrieved. |
Update frequency update_frequency | Partially covered | caiso-tdf-workbooks caiso-plan-appendix-h miso-mtep25 pjm-upgrades | CAISO states twice-yearly forums and an annual plan; MISO publishes annual MTEP packages; PJM refreshed its XML on the day tested but states no schedule. Not checked: PJM and MISO pages read state no update schedule; re-fetching file headers over several days would show PJM's real cadence. |
Main caveats
- No national list was found: PJM, CAISO and MISO were read, ERCOT was blocked (403), ISO-NE only via a PDF update, and NYISO, SPP, BPA and individual utilities were not opened.
- Files give names and state, not routes: only 16 of 15,816 PJM rows embed a coordinate; CAISO and MISO give substation names and text; CAISO route maps are images in the plan.
- The 19 Nov 2026 PJM snapshot had 15,816 upgrades and 5,637 pending or active records. Filter out breakers, relays, reconductoring and other work outside the scope of new lines and substations.
- Listing or approval is not construction: PJM Board approval, MISO 'Appendix A Approved' and CAISO plan approval precede permits; expected in-service dates are revised often.
- Versions change under one URL: CAISO's main plan URL now serves the 2026-08-27 update, MISO's MTEP26 package is a draft, and PJM's XML is overwritten in place.
Sources
pjm-upgradesPJM RTEP Project Status & Cost Allocation upgrades table (XML and XLS export)
PJM Interconnection, L.L.C. · Official · XML, one Upgrade element per upgrade (the page table also exports to XLS) · Direct download · License: Unknown
Live XML with description, kV, state, location text, status and dates. The 19 Nov 2026 snapshot had 15,816 upgrades, including 5,637 pending or active records.
- Landing url
- https://www.pjm.com/planning/m/project-construction
- Data url
- https://www.pjm.com/pjmfiles/media/planning/projectConstruction-data/projectCostUpgrades.xml
- Coverage note
- PJM footprint only; names and state, no routes (16 rows embed a point); many rows are equipment upgrades, not new lines or substations.
- Date of data
- File modified 2026-11-19
- Language
en- Location precision
- No location
- Has coordinates
- No
- Test
- 2026-11-19 · Download · HTTP 200
- The page's 'Latest TCIC version' XLS is a 2023 snapshot (last modified 2023-07-12).
Caveats
- Active status means queue-linked and not yet under agreement
- A 2023 XLS on the same page is stale
Example request
curl -sL -o projectCostUpgrades.xml 'https://www.pjm.com/pjmfiles/media/planning/projectConstruction-data/projectCostUpgrades.xml' ; parse each <Upgrade>, keep Status in (PL, EP, UC, UC-ISP, Active, On Hold) and Equipment in ('Transmission Line', 'Substation')Example result
UpgradeId b3780.2: 'Peach Bottom to Graceton (PECO) - New 500 kV transmission line', Voltage 500, State PA, Status UC, ProjectedInServiceDate 10/23/2028, PJMBoardApprovalDate 7/12/2023, TransmissionOwner PECO, LastUpdated 11/4/2026.
caiso-plan-appendix-hCAISO 2025-2026 Transmission Plan (Board approved 2026-05-19, updated 2026-08-27) and Appendix H project descriptions
California Independent System Operator (CAISO) · Official · PDF (plan 181 pages; Appendix H 25 pages, one block per project) · PDF · License: Unknown
CAISO's annual plan lists 38 approved projects; Appendix H describes 33 with kV, miles, type, expected in-service date and cost, and plan tables give IDs and previously approved project status.
- Landing url
- https://www.caiso.com/documents/board-approved-2025-2026-transmission-plan.pdf
- Data url
- https://www.caiso.com/documents/board-approved-2025-2026-transmission-plan-appendix-h-projects.pdf
- Coverage note
- CAISO area only; text and PDF; no coordinates; dates are those at approval.
- Date of data
- Plan approved 2026-05-19, updated 2026-08-27
- Language
en- Location precision
- No location
- Has coordinates
- No
- Test
- 2026-11-19 · Download · HTTP 200
- The original 2026-05-19 plan text is no longer at the main plan URL, which serves the 2026-08-27 update.
Caveats
- Main plan URL now holds the 2026-08-27 update
- Many projects are upgrades, not new lines
Example request
curl -sL -o apph.pdf 'https://www.caiso.com/documents/board-approved-2025-2026-transmission-plan-appendix-h-projects.pdf' ; pdftotext -layout apph.pdf apph.txt ; split on lines starting with 'Name'
Example result
Name 'Trout Canyon - Lugo 500 kV Line': 'Build a new 500 kV transmission line from Trout Canyon 500 kV substation to Lugo 500 kV substation, approximately 180 miles, with 70% series compensation'; Type Policy; Expected In Service Date 2035; Project Cost $1,270 - $1,800 million (plan ID 2526-P-04, SCE).
caiso-tdf-workbooksCAISO Transmission Development Forum workbooks: Approved Projects - Transmission Planning Process
California Independent System Operator (CAISO) · Official · XLSX, one sheet per transmission owner (PGaE, SCE, SDGaE, VEA_GLW, DCRT, LSPower, CitizensEnergy, Lotus, HWT) · Direct download · License: Unknown
Twice-yearly CAISO workbooks track every approved transmission project with status, permit filing and construction milestones, and expected in-service dates by forum since 2022.
- Landing url
- https://stakeholdercenter.caiso.com/RecurringStakeholderProcesses/Transmission-development-forum
- Data url
- https://stakeholdercenter.caiso.com/InitiativeDocuments/Approved-Projects-Transmission-Planning-Process-Jul-2025.xlsx
- Coverage note
- Retrieved edition is July 2025 (230 projects); no kV or location columns; January and July 2026 editions not found.
- Date of data
- July 2025 forum
- Language
en- Location precision
- No location
- Has coordinates
- No
- Test
- 2026-11-19 · Download · HTTP 200
- The stakeholder page's static HTML lists documents only through the July 2025 forum; guessed names for the January and July 2026 workbooks returned HTTP 500.
Caveats
- Newer 2026 workbooks exist but were not located
- Includes finished and cancelled projects
Example request
curl -sL -o tdf_jul2025.xlsx 'https://stakeholdercenter.caiso.com/InitiativeDocuments/Approved-Projects-Transmission-Planning-Process-Jul-2025.xlsx' ; read sheet 'SCE' (row 1 headers)
Example result
SCE sheet: 'Alberhill 500 kV Method of Service', approved plan 2009, Expected In-Service at the Jul 2025 forum 47453 (2029-12-01 as Excel serial), Project Status 'Engineering', Expected CPUC Permit Application 40057 (2009-09-01).
miso-mtep25MISO Transmission Expansion Plan MTEP25 package: Appendix A new local reliability projects and facilities list
Midcontinent Independent System Operator (MISO) · Official · ZIP with XLSX workbooks and PDF chapters · Direct download · License: Unknown
MISO's MTEP25 package gives 432 Appendix A projects and 678 facility rows with from/to substations, kV, new miles, plan status M1-M4 and expected in-service date; a draft MTEP26 has 532 projects.
- Landing url
- https://www.misoenergy.org/planning/transmission-planning/mtep/
- Data url
- https://cdn.misoenergy.org/MTEP25731615.zip
- Coverage note
- MISO footprint; substation names and state only; interactive status reports need sign-in.
- Date of data
- MTEP25 package 2025-12-11; MTEP26 draft 2026-11-06
- Language
en- Location precision
- No location
- Has coordinates
- No
- Test
- 2026-11-19 · Download · HTTP 200
- MTEP Project Tracking pages (Appendix A Status Report, In-Service Projects, Projects Under Evaluation) redirect to a sign-in page.
Caveats
- Appendix A is recommended for approval, mostly M1 Proposed
- 'Other' project type mixes load-growth and local needs
Example request
curl -sL -o MTEP25.zip 'https://cdn.misoenergy.org/MTEP25731615.zip' ; unzip, open 'MTEP25 Appendix A - New Local Reliability Projects.xlsx', sheets 'MTEP25 Appendix A' (header row 2) and 'MTEP25 Facilities' (header row 1)
Example result
Facilities row PrjID 50628: Transformer Fayette/Wolf Creek - Edwards, Max kV 345, Min kV 138, Miles New 33, IN, Plan Status 'M2 - Appendix A Approved', Expected ISD 47299 (2029-06-30); owner Wabash Valley Power Association.
other-iso-rto-listsOther ISO and RTO planning lists (ISO-NE RSP Project List; ERCOT regional planning)
ISO New England; Electric Reliability Council of Texas (ERCOT) · Official · PDF update presentation (ISO-NE); ERCOT not reached · PDF · License: Unknown
ISO-NE posts semiannual RSP Project List updates as presentations with project IDs, descriptions, cost and owner; ERCOT's planning page was blocked.
- Coverage note
- ISO-NE only through one PDF of changes; the full list and ERCOT data were not retrieved.
- Date of data
- ISO-NE update 2025-10-23
- Language
en- Location precision
- No location
- Has coordinates
- No
- Example access test
- 2026-11-19 · Download · HTTP 200
- ERCOT planning page https://www.ercot.com/gridinfo/planning returned HTTP 403 to a default client, so no ERCOT planning list was read.
- Members summary
- Listed: 2 · Tested: 2 · Data found: 1
Universe: US grid planners outside CAISO, PJM and MISO (other ISO/RTOs and non-RTO utilities); no census page opened, so the total is not established. Listed and tested: ISO-NE (presentation only) and ERCOT (blocked). Not opened: NYISO, SPP, BPA, TVA and utility plans.
See member links and checks in the detail (
other-iso-rto-lists)
Caveats
- Presentation lists changes, not the whole list
- ERCOT returned 403
Example request
curl -sL -o isone_oct25.pdf 'https://www.iso-ne.com/static-assets/documents/100029/final_project_list_presentation_oct_2025.pdf' ; pdftotext -layout isone_oct25.pdf
Example result
Project 1672: 'Forest Ave Substation modification required to build a new 115 kV line from Sudbury Station 342 substation to Hudson substation', cost 8.5 ($M), Hudson Light and Power, placed in service since the June 2025 update.
Additional sources in the detail: 0. Read the full detail; locate each source by its source_id.
Document access
CAISO's approved projects live in PDF appendices and plan tables; extract them to get kV, miles and expected years. PJM and MISO publish tables; routes are only in plan figures and permit filings.
Research provenance
- Pass count
- 1
- Minutes estimate
- 12
- Pages opened
- 26
| Pass | Date |
|---|---|