Germany battery storage in permitting data sources

Where can I get a list of stand-alone battery storage (BESS) projects currently in permitting in Germany, with location, power (MW), developer, permitting stage and date?

Answer

No single German registry tracks BESS in permitting. Most stand-alone BESS are not BImSchG-listed and undergo confidential district Baugenehmigung (~400 authorities; >=4 MW within 200 m of substations privileged per § 35(1) Nr.12 BauGB since 23.12.2025) or municipal Bebauungsplan procedures. Closest official source is BNetzA's MaStR (753 planned >=1 MW units, 13.1 GW; 303 non-EEG/non-backup), but pre-grant filing is voluntary and only 65 hold post-grant permit data. Municipal consultations publish unstructured on UVP-Verbund and state DiPlanung/Bauleitplanung portals; EC JRC (WoodMac-backed) adds partial pipeline data.

Official data
Partial coverage
Non official data
Partial coverage
Published
2026-11-19
Research reviewed
2026-11-15
Access checked
No complete access check recorded

Requested attributes

AttributeCoverageSourcesScope and limitations
Project location locationCovered
  • s001
  • s002
MaStR provides municipality for 753/753 planned >=1 MW units, parcels for 539/753, and lat/lon in DE for 744/753 (9 masked). JRC adds coords.
Power power_mwCovered
  • s001
  • s002
MaStR reports Bruttoleistung & Nettonennleistung in kW (divide by 1000 for MW) plus NutzbareSpeicherkapazitaet in kWh. JRC reports MW & MWh.
Developer developerPartially covered
  • s001
MaStR exposes AnlagenbetreiberName (operator/SPV) for 698/753 legal entities >=1 MW.

Not published: Natural-person owners are withheld per § 15(1) Nr.2 MaStRV (55/753 >=1 MW unshown); EC JRC publishes no developer column.

Permitting stage permitting_stagePartially covered
  • s001
  • s002
MaStR shows BetriebsStatus='In Planung' + linked SGE permits (65/753); JRC uses Announced (618), Permitted (8), Under construction (19).

Not published: Pending Baugenehmigung and § 3(1)/§ 3(2) BauGB consultation milestones are not tracked in MaStR or JRC, only in municipal/UVP notices.

Stage date stage_datePartially covered
  • s001
MaStR list API gives EinheitRegistrierungsdatum, GeplantesInbetriebsnahmeDatum, and GenehmigungRegistrierungsdatum (65/753).

Not published: List API omits Datum and DatumDerAntragstellung (found on detail HTML/XML for 65 granted permits only); JRC omits all permitting dates.

Main caveats

Sources

Marktstammdatenregister (MaStR) — Planned Battery Storage Units

Source id
s001
Publisher
Bundesnetzagentur (BNetzA)
Official
Yes
Landing url
https://www.marktstammdatenregister.de/MaStR/Einheit/Einheiten/ErweiterteOeffentlicheEinheitenuebersicht
Data url
https://www.marktstammdatenregister.de/MaStR/Einheit/EinheitJson/GetErweiterteOeffentlicheEinheitStromerzeugung?sort=Bruttoleistung-desc&page=1&pageSize=250&group=&filter=Betriebs-Status~eq~'31'~and~Energietr%C3%A4ger~eq~'2496'~and~Speichertechnologie~eq~'524'~and~Land~eq~'84'~and~Bruttoleistung+der+Einheit~gt~999
Access
direct_download
Format
JSON
License
Datenlizenz Deutschland – Namensnennung – Version 2.0
Language
de
Has coordinates
Yes
Location precision
exact
Summary
Marktstammdatenregister (MaStR) — Planned Battery Storage Units
Coverage note
national (Germany)
Date of data
2026-11-15 (daily snapshot at 00:00:00 CET; latest Einheit record update 2026-11-14)
Caveats
  • Consult the main caveats and the complete reading traps and access evidence in the detail.
Test
Tested on
2026-11-15
Method
api_query
Http status
200
Problems
  • Unfiltered queries return Total=0; technology and country filters are required.
  • records_total=2,948,611 represents all German battery storage units (all statuses/sizes); 30,952 are In Planung across all sizes; 753 are In Planung >=1 MW.
Example
Complete procedure available in the full detail
Members summary
Not a grouped source

European Energy Storage Inventory

Source id
s002
Publisher
European Commission Joint Research Centre (EC JRC) / Wood Mackenzie
Official
No
Landing url
https://ses.jrc.ec.europa.eu/european-energy-storage-inventory
Data url
https://ses.jrc.ec.europa.eu/storage-inventory-tool/api/projects
Access
api
Format
JSON
License
Commercial underlying data (Wood Mackenzie Limited) displayed under EC JRC disclaimer
Language
en
Has coordinates
Yes
Location precision
municipality
Summary
European Energy Storage Inventory
Coverage note
Europe (1,191 records in Germany)
Date of data
No dataset snapshot date published on portal or API response
Caveats
  • Consult the main caveats and the complete reading traps and access evidence in the detail.
Test
Tested on
2026-11-15
Method
api_query
Http status
200
Problems
  • Of 1,191 DE projects, 645 are pre-operational battery projects (618 Announced, 8 Permitted, 19 Under construction); lacks developer, permitting date, and stand-alone fields.
  • Dataset mixes commercial Wood Mackenzie intelligence (redistribution constraints apply) and lacks publication date metadata.
Example
Example request
curl -sS -H "X-App-Request: map-widget" "https://ses.jrc.ec.europa.eu/storage-inventory-tool/api/projects"
Example result
Base64+XOR payload; decoded object sample: {"id":"167950","title":"Total Arnsberg BESS","status":{"id":"379","name":"Permitted"},"power":"8","capacity":"16","facility":{"region":"North Rhine-Westphalia","country":{"name":"Germany"},"latitude":"51.410000","longitude":"8.050000"},"technology":{"name":"Lithium-ion batteries"}}
Members summary
Not a grouped source

Additional sources in the detail: 0. Read the full detail; locate each source by its source_id.

Document access

Summary
Not stated

Local search terms

Confidence

Confidence
high
Confidence reason
Direct inspection of MaStR XSD/PDF schemas (rev 26.2), live API queries (753 records >=1 MW), MaStRV legal text (§§ 5, 15), BNetzA/SMARD reports, UVP portals, and state DiPlanung procedures confirms exact structural gaps.

Research provenance

Pass count
1
Models
  • Gemini 4 Hydrogen
Minutes estimate
22
Pages opened
88
Passes
  • Pass
    1
    Date
    2026-11-15
    Model
    Gemini 4 Hydrogen
Note
Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed.

Record metadata

Schema version
1.0
Country
de
Country name
Germany
Topic
battery-storage-in-permitting
Territory
de
Territory level
country
Parent url
No parent territory
Html url
https://georutter.org/de/battery-storage-in-permitting/