Germany battery storage in permitting data sources
Where can I get a list of stand-alone battery storage (BESS) projects currently in permitting in Germany, with location, power (MW), developer, permitting stage and date?
Answer
No single German registry tracks BESS in permitting. Most stand-alone BESS are not BImSchG-listed and undergo confidential district Baugenehmigung (~400 authorities; >=4 MW within 200 m of substations privileged per § 35(1) Nr.12 BauGB since 23.12.2025) or municipal Bebauungsplan procedures. Closest official source is BNetzA's MaStR (753 planned >=1 MW units, 13.1 GW; 303 non-EEG/non-backup), but pre-grant filing is voluntary and only 65 hold post-grant permit data. Municipal consultations publish unstructured on UVP-Verbund and state DiPlanung/Bauleitplanung portals; EC JRC (WoodMac-backed) adds partial pipeline data.
- Official data
- Partial coverage
- Non official data
- Partial coverage
- Published
- 2026-11-19
- Research reviewed
- 2026-11-15
- Access checked
Requested attributes
| Attribute | Coverage | Sources | Scope and limitations |
|---|---|---|---|
Project location location | Covered |
| MaStR provides municipality for 753/753 planned >=1 MW units, parcels for 539/753, and lat/lon in DE for 744/753 (9 masked). JRC adds coords. |
Power power_mw | Covered |
| MaStR reports Bruttoleistung & Nettonennleistung in kW (divide by 1000 for MW) plus NutzbareSpeicherkapazitaet in kWh. JRC reports MW & MWh. |
Developer developer | Partially covered |
| MaStR exposes AnlagenbetreiberName (operator/SPV) for 698/753 legal entities >=1 MW. Not published: Natural-person owners are withheld per § 15(1) Nr.2 MaStRV (55/753 >=1 MW unshown); EC JRC publishes no developer column. |
Permitting stage permitting_stage | Partially covered |
| MaStR shows BetriebsStatus='In Planung' + linked SGE permits (65/753); JRC uses Announced (618), Permitted (8), Under construction (19). Not published: Pending Baugenehmigung and § 3(1)/§ 3(2) BauGB consultation milestones are not tracked in MaStR or JRC, only in municipal/UVP notices. |
Stage date stage_date | Partially covered |
| MaStR list API gives EinheitRegistrierungsdatum, GeplantesInbetriebsnahmeDatum, and GenehmigungRegistrierungsdatum (65/753). Not published: List API omits Datum and DatumDerAntragstellung (found on detail HTML/XML for 65 granted permits only); JRC omits all permitting dates. |
Main caveats
- Pre-permit MaStR registration is voluntary for non-BImSchG projects; 753 planned >=1 MW BESS in MaStR vs 18,158 grid requests (573.5 GW) and 1,937 commitments (54.2 GW) in 2025.
- Pending Baugenehmigungen (~400 district Bauaufsichtsbehörden) are non-public administrative files; MaStR's Genehmigung schema requires a mandatory grant date (Datum), so pending applications cannot appear there.
- No explicit stand-alone boolean exists in MaStR: 443/753 planned >=1 MW units link to an EEG facility (many PV+BESS), while 303 non-EEG/non-backup units serve as an imperfect stand-alone proxy.
- 276/753 planned >=1 MW MaStR battery units already carry overdue planned commissioning dates (< 2026-11-15), inflating the apparent active pipeline.
- MaStR list JSON returns GenehmigungRegistrierungsdatum (upload date), not actual Genehmigungsdatum / DatumDerAntragstellung (which require scraping unit detail HTML or parsing the 3.2 GB XML dump).
Sources
Marktstammdatenregister (MaStR) — Planned Battery Storage Units
- Source id
- s001
- Publisher
- Bundesnetzagentur (BNetzA)
- Official
- Yes
- Landing url
- https://www.marktstammdatenregister.de/MaStR/Einheit/Einheiten/ErweiterteOeffentlicheEinheitenuebersicht
- Data url
- https://www.marktstammdatenregister.de/MaStR/Einheit/EinheitJson/GetErweiterteOeffentlicheEinheitStromerzeugung?sort=Bruttoleistung-desc&page=1&pageSize=250&group=&filter=Betriebs-Status~eq~'31'~and~Energietr%C3%A4ger~eq~'2496'~and~Speichertechnologie~eq~'524'~and~Land~eq~'84'~and~Bruttoleistung+der+Einheit~gt~999
- Access
- direct_download
- Format
- JSON
- License
- Datenlizenz Deutschland – Namensnennung – Version 2.0
- Language
- de
- Has coordinates
- Yes
- Location precision
- exact
- Summary
- Marktstammdatenregister (MaStR) — Planned Battery Storage Units
- Coverage note
- national (Germany)
- Date of data
- 2026-11-15 (daily snapshot at 00:00:00 CET; latest Einheit record update 2026-11-14)
- Caveats
- Consult the main caveats and the complete reading traps and access evidence in the detail.
- Test
- Tested on
- 2026-11-15
- Method
- api_query
- Http status
- 200
- Problems
- Unfiltered queries return Total=0; technology and country filters are required.
- records_total=2,948,611 represents all German battery storage units (all statuses/sizes); 30,952 are In Planung across all sizes; 753 are In Planung >=1 MW.
- Example
- Members summary
European Energy Storage Inventory
- Source id
- s002
- Publisher
- European Commission Joint Research Centre (EC JRC) / Wood Mackenzie
- Official
- No
- Landing url
- https://ses.jrc.ec.europa.eu/european-energy-storage-inventory
- Data url
- https://ses.jrc.ec.europa.eu/storage-inventory-tool/api/projects
- Access
- api
- Format
- JSON
- License
- Commercial underlying data (Wood Mackenzie Limited) displayed under EC JRC disclaimer
- Language
- en
- Has coordinates
- Yes
- Location precision
- municipality
- Summary
- European Energy Storage Inventory
- Coverage note
- Europe (1,191 records in Germany)
- Date of data
- No dataset snapshot date published on portal or API response
- Caveats
- Consult the main caveats and the complete reading traps and access evidence in the detail.
- Test
- Tested on
- 2026-11-15
- Method
- api_query
- Http status
- 200
- Problems
- Of 1,191 DE projects, 645 are pre-operational battery projects (618 Announced, 8 Permitted, 19 Under construction); lacks developer, permitting date, and stand-alone fields.
- Dataset mixes commercial Wood Mackenzie intelligence (redistribution constraints apply) and lacks publication date metadata.
- Example
- Example request
curl -sS -H "X-App-Request: map-widget" "https://ses.jrc.ec.europa.eu/storage-inventory-tool/api/projects"
- Example result
Base64+XOR payload; decoded object sample: {"id":"167950","title":"Total Arnsberg BESS","status":{"id":"379","name":"Permitted"},"power":"8","capacity":"16","facility":{"region":"North Rhine-Westphalia","country":{"name":"Germany"},"latitude":"51.410000","longitude":"8.050000"},"technology":{"name":"Lithium-ion batteries"}}
- Members summary
Additional sources in the detail: 0. Read the full detail; locate each source by its source_id.
Document access
- Summary
Local search terms
- Term
- Marktstammdatenregister (MaStR)
- Language
- de
- Meaning
- Federal core energy market data register operated by BNetzA
- Term
- Vorhabenbezogener Bebauungsplan
- Language
- de
- Meaning
- Project-specific municipal zoning plan required when BESS lacks § 35 BauGB privilege
- Term
- Baugenehmigung
- Language
- de
- Meaning
- State building permit issued by district untere Bauaufsichtsbehörde (unpublished while pending)
- Term
- Untere Bauaufsichtsbehörde
- Language
- de
- Meaning
- District/city building authority (~400 nationwide) handling § 35(1) Nr. 12 BauGB BESS permits
- Term
- Bauleitplanung
- Language
- de
- Meaning
- Municipal urban land-use planning (Flächennutzungsplan + Bebauungsplan public consultations)
- Term
- UVP-Vorprüfung
- Language
- de
- Meaning
- Environmental impact screening; triggered for BESS mainly by ancillary forest clearing (Waldumwandlung)
- Term
- Netzanschlussbegehren
- Language
- de
- Meaning
- Grid connection request submitted to TSO/DSO (18,158 in 2025; distinct from permitting)
- Term
- Stromspeicher
- Language
- de
- Meaning
- Electricity storage unit/installation in MaStR (Energieträger ID 2496, Technologie 524 = Batterie)
Confidence
- Confidence
- high
- Confidence reason
- Direct inspection of MaStR XSD/PDF schemas (rev 26.2), live API queries (753 records >=1 MW), MaStRV legal text (§§ 5, 15), BNetzA/SMARD reports, UVP portals, and state DiPlanung procedures confirms exact structural gaps.
Research provenance
- Pass count
- 1
- Models
- Gemini 4 Hydrogen
- Minutes estimate
- 22
- Pages opened
- 88
- Passes
- Pass
- 1
- Date
- 2026-11-15
- Model
- Gemini 4 Hydrogen
- Note
- Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed.
Record metadata
- Schema version
- 1.0
- Country
- de
- Country name
- Germany
- Topic
- battery-storage-in-permitting
- Territory
- de
- Territory level
- country
- Parent url
- Html url
- https://georutter.org/de/battery-storage-in-permitting/