gb / grid-connection-queue

United Kingdom grid connection queue data sources

Where can I get the list of grid connection requests in the United Kingdom, with project, technology, capacity (MW), connection node, status and date?

Research reviewed
2026-11-27
Sources tested
2026-11-27
Access checked
2026-11-27
Published
2026-11-27
Sources
4 on this page · 0 in the detail

Answer

Official data
Partial coverage
Non official data
Not checked
Confidence
Medium

NESO publishes GB TEC contracts and a separate Scottish embedded register; SONI publishes Northern Ireland connection agreements and effective applications. Distribution operators publish their own registers. These datasets mix connected and future projects and do not provide a complete list of all UK applications.

Confidence reason: Both NESO CSVs and SONI workbook were downloaded; a distribution CSV is blocked and full UK coverage remains unchecked.

Local search terms

  • Transmission Entry Capacity — Contracted TEC, not all applications.
  • Gate 2 — Prioritised connection agreement after applicable assessment and countersignature.
  • Embedded Capacity Register — Distribution operator register; distinct from NESO Scottish Embedded register.

Requested attributes

AttributeCoverageSourcesScope and limitations
Project projectPartially coveredtec embedded soni distributionNames and project IDs are available in tested NESO and SONI records.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Technology technologyPartially coveredtec embedded soni distributionNESO has Plant Type; SONI groups rows in technology sections.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Requested capacity capacity_mwPartially coveredtec embedded soni distributionNESO connected and cumulative TEC; SONI export/import differ.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Connection node connection_nodePartially coveredtec embedded soni distributionNESO connection site and SONI point coordinates are available.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Request status statusPartially coveredtec embedded soni distributionStatus and agreement stage exist; Gate blank is unspecified.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Request or event date event_datePartially coveredtec embedded soni distributionNESO MW Effective From is not the request date; SONI has connection dates.

Not checked: The tested NESO files give capacity-effective dates, SONI reports connection dates or status, and Northern Powergrid reports offer acceptance. Application submission dates were not established across these registers.

Latest available data latest_dataPartially coveredtec embedded soniNESO files dated 26 November 2026; SONI latest linked 17 August 2026.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Historical coverage historical_seriesPartially coveredtec embedded soniNESO cites FOI archives for 2014–2025; SONI links previous editions.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Update frequency update_frequencyPartially coveredtec embedded soni distributionNESO states twice weekly, SSEN monthly; SONI schedule not established.

Not checked: UK-wide coverage and missing distribution, request-date or history details remain to be checked.

Main caveats

  • TEC is a contract register, not all requests; NESO reports no public demand connection register.
  • An empty Gate field is not Gate 1 or Gate 2: NESO populates it after an agreement is countersigned.
  • Effective capacity dates are not application dates; connected MW and cumulative stage MW are different.
  • NESO warns repeated capacity across stages or technologies can cause duplicates.
  • Distribution coverage varies: Northern Powergrid ECR omits unaccepted enquiries; SONI omits cluster agreements.

Sources

tecNESO Transmission Entry Capacity register

National Energy System Operator · Official · CSV · Direct download · License: NESO Open Data Licence

TEC agreements, including existing and future projects.

Landing url
https://www.neso.energy/data-portal/transmission-entry-capacity-tec-register
Data url
https://api.neso.energy/dataset/cbd45e54-e6e2-4a38-99f1-8de6fd96d7c1/resource/17becbab-e3e8-473f-b303-3806f43a6a10/download/tec-register-26-november-2026.csv
Coverage note
Great Britain; projects holding TEC agreements for existing or future connections, including embedded projects.
Date of data
26 November 2026
Language
en
Location precision
No location
Has coordinates
No
Test
2026-11-27 · Download · HTTP 200

Caveats

  • Not a complete UK-wide list of all applications.

Complete procedure available in the full detail

embeddedNESO Embedded Register

National Energy System Operator · Official · CSV · Direct download · License: NESO Open Data Licence

NESO Scottish embedded generation.

Landing url
https://www.neso.energy/data-portal/embedded-register
Data url
https://api.neso.energy/dataset/4b0e109c-aa23-45ac-86c1-0bda557d1aab/resource/68b6f3a1-e1bf-403b-9062-0269fc758d77/download/embedded-register-26-november-2026.csv
Coverage note
Scotland: embedded generation connected or contracted to connect.
Date of data
26 November 2026
Language
en
Location precision
No location
Has coordinates
No
Test
2026-11-27 · Download · HTTP 200

Caveats

  • Not a complete UK-wide list of all applications.

Complete procedure available in the full detail

soniConnections Register

SONI · Official · XLSX · Direct download · License: unknown

Northern Ireland applications and agreements.

Landing url
https://www.soni.ltd.uk/industry/connections-and-applications
Data url
https://cms.soni.ltd.uk//sites/default/files/2026-08/20260817%20Connections%20Register%2017%20Aug%202026%20%28Excel%29.xlsx
Coverage note
Northern Ireland transmission and selected distribution TUoS cases. SONI excludes connections below 5 MW and cluster substation agreements.
Date of data
17 August 2026
Language
en
Location precision
Exact
Has coordinates
Yes
Test
2026-11-27 · Download · HTTP 200

Caveats

  • Not a complete UK-wide list of all applications.

Complete procedure available in the full detail

distributionDistribution operators’ embedded capacity registers: sample

Distribution network operators · Official · JSON, CSV or web · API · License: varies by operator

Operator registers cover distribution-connected and accepted projects; Northern Powergrid data are queryable.

Coverage note
Northern Powergrid tested in northeast England and Yorkshire; SSEN and NGED data downloads were blocked.
Date of data
13 November 2026 for Northern Powergrid
Language
en
Location precision
Exact
Has coordinates
Yes
Example access test
2026-11-27 · API query · HTTP 200
Members summary
Listed: 4 · Tested: 4 · Data found: 2

Three DNO group examples reviewed, chosen for accessible dataset leads; not all GB operators are covered.

See member links and checks in the detail (distribution)

Caveats

  • Coverage and access differ by operator; ECRs omit many unaccepted enquiries.

Complete procedure available in the full detail

Additional sources in the detail: 0. Read the full detail; locate each source by its source_id.

Document access

Where published information is in workbooks or case documents, extract only their stated status; the example does not fill all missing requests.

Research provenance

Pass count
1
Minutes estimate
12
Pages opened
Not stated
PassDate
12026-11-27

Minutes are researcher estimates. Counts describe documented passes, not publication approval. Missing history or effort is not reconstructed.

Record metadata: Schema version: 1.0 · Country: gb · Country name: United Kingdom · Topic: grid-connection-queue · Territory: gb · Territory level: Country · Parent url: No parent territory · Html url: https://georutter.org/gb/grid-connection-queue/