us / hydrogen-plants-in-permittingUnited States hydrogen plants in permitting data sources
Where can I get a list of hydrogen production projects currently in permitting in the United States, with location, capacity (MW), developer, permitting stage and date?
- Research reviewed
- 2026-11-24
- Sources tested
- 2026-11-24
- Access checked
- 2026-11-24
- Published
- 2026-11-24
- Sources
- 5 on this page · 2 in the detail
Answer
- Official data
- Partial coverage
- Non official data
- Not checked
- Confidence
- Medium
No single list gives stage and date for electrolysis projects in permitting. DOE Record 24001 (May 2024) lists 43 planned rows without developers or dates; stage, developer and MW come from dockets: Lancaster Clean Energy Center (CEQA approval 2024-03-11, 400 MWe) and Plug Power's Graham, Texas project (DOE FONSI 2025-01-10, twelve 10 MW; agreed for sale July 2026). DOE hub pages are hub-level and stale; the PNWH2 award was reported rescinded in October 2025.
Local search terms
- CEQAnet / Notice of Determination (NOD) / Mitigated Negative Declaration (MND) — California portal and documents; open each document of the SCH number for stage and date.
- DOE/EA-#### Final Environmental Assessment and FONSI — DOE NEPA documents for financed projects; energy.gov/nepa pages carry the applicant, site and permits.
- Regional Clean Hydrogen Hubs (H2Hubs) — Seven DOE-selected hubs; hub pages are consortium-level.
- Hydrogen Program Record 24001 — DOE table of installed and planned electrolyzers; planned rows have no developer.
- Conditional Use Permit (CUP) No. ... — City or county use permit that appears as the CEQAnet title (for example CUP 23-019).
- Loan Programs Office (LPO) conditional commitment / loan guarantee — DOE financing step referred to in the Graham EA; a FONSI is not the financing decision.
- Permit by Rule (PBR), TCEQ — Texas air authorisation noted in the Graham EA (coverage began September 2023); no public docket was found.
- retain/modify list — DOE's 2026 list of awards it may keep; CATF reports it covers five of seven hubs.
Requested attributes
| Attribute | Coverage | Sources | Scope and limitations |
|---|---|---|---|
Project location location | Partially covered | ceqanet-hydrogen doe-nepa-hydrogen doe-record-24001 | Lancaster CA (parcels, cross streets) and Graham TX (2264 FM 209) are documented to address level; DOE Table 1 gives city and state for planned rows; no list has coordinates. Not checked: Only two projects were traced to site documents; hub projects and other states' dockets were not opened. |
Capacity capacity_mw | Partially covered | ceqanet-hydrogen doe-nepa-hydrogen doe-record-24001 | Lancaster 400 MWe of electrolyzers; Graham twelve 10 MW units (45 tpd, a separate measure); DOE gives kW for 43 planned rows. Hub documents give tons per day only. Not checked: Basis of DOE's kW and of Lancaster's 'MWe' not defined; capacity for other projects was not checked. |
Developer developer | Partially covered | ceqanet-hydrogen doe-nepa-hydrogen operator-project-announcements | Element New Energy Lancaster 1, LLC (Lancaster) and Plug Power (Graham) are named in dockets; DOE Table 1 omits developers and hub pages name consortia. Not checked: Developers of the other 41 planned rows and of hub projects were not identified. |
Permitting stage permitting_stage | Partially covered | ceqanet-hydrogen doe-nepa-hydrogen operator-project-announcements | Lancaster: CEQA approval (MND) 2024-03-11. Graham: DOE FONSI 2025-01-10, work paused since Dec 2023, sale agreed July 2026. DOE's statuses are only Planned/Under Construction. Not checked: No national stage field; hub projects have no site-specific review yet; construction status of Lancaster after March 2024 was not verified. |
Stage date stage_date | Partially covered | ceqanet-hydrogen doe-nepa-hydrogen operator-project-announcements | Dated events for two projects: Lancaster NOD 2024-03-12 (approved 03-11); Graham EA public comment from 2024-12-06, FONSI 2025-01-10, sale release 2026-07-13. Not checked: No list gives stage dates; DOE Record 24001 has none; EIS-0571 dates are anticipated. |
Main caveats
- DOE Record 24001 is dated May 2024: it lists Graham, TX as Planned/Under Construction although Plug Power agreed in July 2026 to sell that project; it has no developer or stage date.
- A DOE FONSI (Graham, 2025-01-10) and a CEQA approval (Lancaster, 2024-03-11) are not financing, construction or operation: no building or start-of-construction document was found for either.
- MW bases differ: 120 MW of electrolyzers, 45 tpd of hydrogen and 164 MW of grid interconnection describe Graham; Lancaster's '400 MWe' is undefined. None converts into another.
- DOE hub pages predate the 2025 cuts (Canary Media: awards to two hubs rescinded) and show no electrolyzer-level project, MW or permit; DOE's EIS-0571 dates are anticipated only.
- Only California and Texas dockets were opened; Washington, Oregon and other state portals and the IEA project file (account required) were not checked.
Sources
ceqanet-hydrogenCEQAnet: California CEQA records for hydrogen production projects (example SCH 2024020266, Lancaster Clean Energy Center)
California Governor's Office of Land Use and Climate Innovation (LCI), State Clearinghouse · Official · HTML record pages, per-document CSV export and PDF attachments · Web viewer only · License: Unknown
City of Lancaster CEQA record: Lancaster Clean Energy Center (Element New Energy Lancaster 1, LLC), 400 MWe of electrolyzers with 650 MW PV; MND 2024-02-07, approved 2024-03-11.
- Landing url
- https://ceqanet.lci.ca.gov/
- Coverage note
- California only; one hydrogen project opened; approval stage, not construction.
- Date of data
- 2024-03-12
- Language
en- Location precision
- Address
- Has coordinates
- Test
- 2026-11-24 · Page only · HTTP 200
- Free-text search is a Google Custom Search widget; a /Search 'q' parameter returned unrelated documents.
Caveats
- Keyword search not scriptable.
- Approval is not construction or operation.
Example request
curl -sL https://ceqanet.lci.ca.gov/2024020266/1 ; curl -sL https://ceqanet.lci.ca.gov/2024020266/2 ; the attachment link on each record page is /2024020266/2/Attachment/<id>.
Example result
SCH 2024020266, Lead Agency City of Lancaster: document 1 MND received 2/7/2024 (state review 2/7-3/8/2024); document 2 NOD received 3/12/2024, approved 3/11/2024. Applicant Element New Energy Lancaster 1, LLC; 650 MW PV, 330 MWh storage, 400 MWe electrolyzers.
doe-nepa-hydrogenDOE Office of NEPA Policy and Compliance pages for hydrogen production projects (DOE/EA-2281 Limestone; DOE/EIS-0571 Pacific Northwest Hydrogen Hub)
U.S. Department of Energy, Office of NEPA Policy and Compliance · Official · HTML project pages and PDF environmental assessment (5.9 MB, 5,764 text lines) · PDF · License: Unknown
DOE NEPA records: Limestone (Plug Power, Graham TX) EA with twelve 10 MW electrolyzers, 45 tpd, FONSI signed 2025-01-10; Pacific Northwest Hub EIS scope (about 10 projects) without sites or MW.
- Coverage note
- Only DOE-financed projects; two pages opened; Limestone's later fate is outside DOE's page.
- Date of data
- 2025-01-10
- Language
en- Location precision
- Address
- Has coordinates
- No
- Example access test
- 2026-11-24 · Download · HTTP 200
- Members summary
- Listed: 2 · Tested: 2 · Data found: 2
Universe not counted: DOE NEPA pages for hydrogen production were found through search, not by listing. Two pages were opened; hub-related categorical exclusions (HyVelocity, Heartland) appeared in search results and were not opened.
Search energy.gov/nepa for 'hydrogen' with the project or hub name; pages are titled DOE/EA-#### or DOE/EIS-####.See member links and checks in the detail (
doe-nepa-hydrogen)
Caveats
- FONSI is not a loan or a building permit.
- EIS schedule dates are anticipated, not confirmed.
doe-record-24001DOE Hydrogen Program Record 24001, Electrolyzer Installations in the United States (planned and under-construction rows)
U.S. Department of Energy, Hydrogen Program (HFTO) · Official · PDF (Table 1) · PDF · License: Unknown
43 planned or under-construction electrolyzer rows (657 MW under construction, 3.75 GW planned) with city, kW and status; May 2024.
- Landing url
- https://www.hydrogen.energy.gov/library/program-records
- Data url
- https://www.hydrogen.energy.gov/docs/hydrogenprogramlibraries/pdfs/24001-electrolyzer-installations-united-states.pdf
- Coverage note
- No developer, no stage date; 18 months old; cancelled projects still listed.
- Date of data
- 2024-05
- Language
en- Location precision
- Municipality
- Has coordinates
- No
- Test
- 2026-11-24 · Download · HTTP 200
Caveats
- No developer or dates.
- Stale: Graham, TX has since been put up for sale.
doe-h2hubs-pagesDOE Regional Clean Hydrogen Hubs selection pages (example: Pacific Northwest Hydrogen Hub, PNWH2)
U.S. Department of Energy, Office of Clean Energy Demonstrations (OCED) · Official · HTML pages · Web viewer only · License: Unknown
DOE hub selection pages give consortium, states and cost share only (PNWH2: up to $1 billion); the page predates the October 2025 rescission of two hubs' awards reported by Canary Media.
- Coverage note
- Hub-level; no electrolyzer docket; one hub page opened; list page returns 404.
- Date of data
- 2025-01-27
- Language
en- Location precision
- No location
- Has coordinates
- No
- Example access test
- 2026-11-24 · Page only · HTTP 200
- DOE's regional-hubs overview URLs (energy.gov/oced/regional-clean-hydrogen-hubs-0 and /cmei/oced/regional-clean-hydrogen-hubs) returned 404.
- Members summary
- Total: 7 · Listed: 1 · Tested: 1 · Data found: 0
Seven hubs per Canary Media and CATF; only PNWH2 was opened. ARCHES (California) and PNWH2 awards were rescinded per Canary Media (2025-10-10); CATF (2026-05-11) says DOE's retain/modify list covers awards for five of the seven hubs.
Open each hub's DOE page and its NEPA page, then search the hub's partners' permit dockets.See member links and checks in the detail (
doe-h2hubs-pages)
Caveats
- Page is stale relative to news of terminations.
- No project-level MW or stage.
operator-project-announcementsDeveloper and city announcements on project status (Plug Power Graham sale release; City of Lancaster release)
Plug Power Inc.; City of Lancaster, CA (via GlobeNewswire and PR Newswire reprints) · Official · HTML press-release reprints · Web viewer only · License: Unknown
Plug Power agreed on 2026-07-13 to sell its Graham, Texas project (land and 164 MW of interconnection) to Stream; the City of Lancaster announced its commission's approval on 2024-03-20.
- Coverage note
- Two projects; reprints of releases; closing of the Graham sale not confirmed.
- Date of data
- 2026-07-13
- Language
en- Location precision
- Municipality
- Has coordinates
- No
- Example access test
- 2026-11-24 · Page only · HTTP 200
- Members summary
- Listed: 2 · Tested: 2 · Data found: 2
No universe: only the two projects traced in this card were checked.
Search the developer's newsroom for the project's city and name.See member links and checks in the detail (
operator-project-announcements)
Caveats
- Plug's release does not name Limestone or electrolyzers.
- Sale closing only expected, not confirmed.
Additional sources in the detail: 2. Read the full detail; locate each source by its source_id.
Document access
Stage and dates are in project-specific documents: CEQA records for California projects, DOE NEPA documents for federally financed projects, and company or city releases for later status.
Research provenance
- Pass count
- 1
- Minutes estimate
- Pages opened
- 20
| Pass | Date |
|---|---|
| 1 | 2026-11-24 |